BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock BE and is hereby authorized
and directed to execute for and on behalf of the City of Lubbock a
Change Order to the contract of 12/]3/79 between J. L. Frazier Company
and the City of Lubbock which is attached herewith and which shall be
spread upon the minutes of the Council and as spread upon the minutes of
this Council shall constitute and be a part of this Resolution as if
fully copied herein in detail.
Passed by the City Council this 26th
ATTEST:
Evelyn Ga fga, City.Secr ary-Treasurer
APPROVED AS TO CONTENT:
4 41
Marvin Coffee, DViftor of Aviation
APPROVED AS TO FORM:
I Le:�eL -
Angela 41rams, Assistant City Attorney
day of March ,1981.
r
LL ALIST$R, MAYOR
TO: R. L. FRAZIER COMPANY
5506 - 27th Street
Lubbock, Texas 79407
i
RESOLUTION #762 - 3/26/81
Change Order X61 - Reso 584 - 8/14/8D
Contract - Reso. #387 - 1/10/80
CHANGE ORDER NO. 2 Bid #5584
Transformer Vault &
Beacon Construction
ADAP Project No. 6-48-0138-14
Contract No. 1
Lubbock International Airport
Lubbock, Texas
General description of work included in contract:
The construction of a new transformer vault, installation of transformer
vault equipment, installation of standby engine -generator, installation of
airport rotating beacon, installing new lighting cable, installing duct, con-
struction of manholes, and other related items of work.
Original Amount of Contract . . . . . . .$362,543.00
Change Order No. 1 . . . (Add) 4,050.00
Change Order No. 2 . . . . . . (Add) 14,991.00
Adjusted Contract Price . . . . . . . $381,584.00
Adjustment in Construction Time:
Original Time for Completion 180 Calendar days
Change Order No. 1 None
Change Order No. 2 (Add)223 Calendar days
Adjusted Time for Completion 403 Calendar days
WHEREAS, it is desirable to make changes in the work to be constructed
under this project:
THIS AGREEMENT WITNESSETH: In consideration of the mutual advantage
gained, the Owner and the Contractor agree to the changes indicated below
and further agree that the amount of the contract shall be adjusted by the
amount shown above.
1. PROPOSAL ITEM NO. 3, "Electrical Equipment and Wiring Installed in Existing
Control Tower," shall be revised. The unit price shall be revised from
$479.00 to $979.00. The Quantity shall remain 1 job.
Deduct: 1 job @ $479.00 = $479.00
Add: 1 job @ $979.00 = $979.00
Sub- Total (Add) _ $500.00
2. PROPOSAL ITEM NO. 7, "Airport Rotating Beacon and Tower," shall be revised.
The unit price shall be revised from $24,046.00 to $24,296.00. The
Quantity shall remain 1 job.
Deduct: 1 job @ $24,046.00 = $24,046.00
Add: 1 job @ 24,296.00 = 24,296.00
Sub -Total (Add) $ 250.00
CHANGE ORDER NO. 2
Page 1 of 4
3. PROPOSAL ITEM NO. 11, "2 -inch Underground Duct," shall be revised. The
Quantity shall be revised from 320 L.F. to 1,045 L.F. The unit price
shall be unchanged.
Deduct: 370 L.F. @ $1.60 = $ 592.00
Add: 1,045 L.F. @ 1.60 1,672.00
Sub -total (Add) _ $1,080.00
4. PROPOSAL ITEM NO. 14, "4 -way, 4 -inch Underground Duct," shall be
revised. The Quantity shall be revised from 2,540 L.F. to 2,665 L.F.
The Unit price shall be unchanged.
Deduct: 2,540 L.F. @ $10.00 = $25,400.00
Add: 2,665 L.F. @ $10.00 = 26,665.00
Sub -Total (Add) _ $ 1,265.00
5. PROPOSAL ITEM NO. 20, "Underground Cable 1/c, 5KV," shall be revised.
The Quantity shall be revised from 100,000 L.F. to 103,300 L.F. The
Unit price shall be unchanged.
Deduct: 100,000 L.F. @ $0.37 $37,000.00
Add: 103,300 L.F. @ 0.37 = 38,221.00
Sub -Total (Add) _ $ 1,221.00
6. PROPOSAL ITEM NO. 29, "Manhole, 2 -foot Square," (as added by Change
Order No. 1) shall be revised. The Quantity shall be revised from 5
each to 7 each. The Unit price shall be unchanged.
Deduct: 5 Each @ $950.00 = $ 4,750.00
Add: 7 Each @ 950.00 = 6,650.00
Sub -Total (Add) _ $ 11900.00
7. PROPOSAL, Add a new Item No. 31, "4 -way, 2 -inch Underground Duct, furnished
and installed in trench, including trenching and backfilling, per linear
foot: for the unit price of $4.60 per linear foot. The Quantity shall
be 500 L.F."
Add: 500 L.F. @ $4.60 $2,300.00
8. PROPOSAL, Add a new Item No. 32, "Cable Connections, Extra, furnished
and installed, complete, each: for the unit price of $25.00 each. The
Quantity shall be 19 each."
Add: 19 each @ $25.00 $ 475.00
9. PROPOSAL, Add a new Item No. 33 "Extra Labor, Equipment, and Materials
for installing additional manholes, duct, cable and related items near
the intersection of Runways 17R -35L and 8-26, complete for the lump
sum price of $4,000.00"
Add: 1 job @ $4,000.00 $4,000.00
10. PROPOSAL, Add a new Item No. 34, "Bore and clean existing duct that is
silted or blocked in such manner to prevent installation of new cable.
Boring and cleaning shall be done only when specifically authorized.
Boring and cleaning shall be done, including labor and materials, complete,
per linear foot: for the unit price of $10.00 per linear foot."
Add: 200 L.F. @ $10.00 _ $2,000.00
CHANGE ORDER NO. 2
Page 2 of 4
11. SECTION 2 - INSTALLATION OF AIRPORT TRANSFORMER VAULT EQUIPMENT AND
CONTROL TOWER EQUIPMENT
Page 2-11 Paragraph 2-5 (b) Control Tower, the following shall be
inserted:
"Two (2) - rotary brightness control switches, 5 - brightness levels,
for lighting on Runways 17R -35L and 8-26 shall be installed in the
runway lighting control panel. The two existing defective switches
shall be removed."
12. SECTION 7 - INSTALLATION OF AIRPORT ROTATING BEACON AND TOWER
Page 7-9, Paragraph 7-5, (a), Airport Rotating Beacon and Tower:
the following shall be inserted:
"Install an auxiliary contactor in a NEMA 12 Enclosure and install a
Hand/Automatic Switch in a weatherproof Box, all located at bottom of
the Beacon Tower."
13. CONSTRUCTION TIME
Adjust construction time by adding two hundred twenty three (223)
calendar days in accordance with Paragraph 42 of the General Conditions
in the Contract Documents. This additional time is for delays incurred
by the Contractor in receipt of certain critical equipment and for
delays caused by bad weather. Total construction time will be changed
to 403 consecutive calendar days.
The additional work involved with installation of,manholes, duct, cable,
and related work near the intersection of Runways 17R -35L and 8-26 shall
be done by the Contractor as soon as possible but only when the operation
of aircraft allows the Director of Aviation to permit work within the
area. This additional work will be done after the original contract
work has been substantially completed, therefore it is not included In
the above stated.construction time.
CHANGE ORDER NO. 2
Page 3 of 4
The aforementioned changes, and work affected thereby, are subject to
all contract stipulations and covenants.
The Owner and the Contractor agree that there will not be an adjustment
to the time allowed for completion of the project for the above listed
changes, except as set forth in Item No. 13 above.
IN WITNESS WHEREOF, the Owner and the Contractor have hereto set their
hands this the 26th day of March , 1981.
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
RECOMMENDED: PARKHILL, SMITH & COOPER, INC., Consulting Engineers
By l<
Project Engineer L%1981
APPROVED: R. L. FRAZIER COMPANY, Contractor
APPROVED: CITY OF LUBBOCK, TEXAS, Owner
By ._ Mayor '
1981
-ATTEST:
City Secretary
APPROVED AS TO CONTENT:
ai n Coffee, Di orof Aviation
APPROVED AS TO FORM: -
gelaams, Assistant City Attorney
CHANGE ORDER NO. 2
Page 4 of 4