HomeMy WebLinkAboutResolution - 718 - CO #4 To Contract - Anthony Mechanical Inc - Improvements Time Extension, SE WRP - 02/12/1981JWF:dh RESOLUTION #718 - 2/12/81
Amends Reso. #369, 12/12/79
RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock BE and is hereby authorized and
directed to execute for and on behalf of the City of Lubbock Change Order No.
4 with Anthony Mechanical, Incorporated, for a time extension of 42 days on
contract for improvements to the Southeast Water Reclamation Plant of the City
of Lubbock.
A copy of the Change Order No. 4 is attached herewith which shall be
spread upon the minutes of the Council and as spread upon the minutes of this
Council shall constitute and be a part of this Resolution as if fully copied
herein in detail.
Passed by the City Council this 12th day of February ` -- ,1981.
�LL
ATTEST:
fAxelyn Gaf fga, City S -Treasurer
I
APPROVE]) AS TO CONTENT:
/V I/ #A
Guy Wilpf n, Utilities Engineer
APPROVED AS TO FORM:
J. W V h Fullingim, Assistant ity Attorney
WHEREAS, it is desirable to make changes in the plans and specifications
for this project:
THIS AGREEMENT WITNESSETH: In consideration of the mutual advantages
gained, the Owner and the Contractor agree to the change shown herein and
in the attached exhibits and data, and the Owner and the Contractor agree
that the original contract between them shall be modified and amended to the
extent herein indicated.
IN WITNESS WHEREOF, the Owner and the Contractor have hereto set their
hands this the 12th day of February, 1981.
Anthony Mechanica I
,.
By
CITY OF LUBBOCK
OWNER -%
By
yor
ATTEST:
S cretary - Treasum [ .
RECOIMNDED R AAPPROV
Chie ngineer, Water Utilities
Engin ring
RESOLUTION #718 - 2/12/81
-,M
Amends Reso. #369 - 12/12/79
N9g1
11
Change Order No. 4
Phase No. 1 Renovation of Plant No. 1
S.E. Water Reclamation Plant
G. W. 0. 10982
TO:
Anthony Mechanical, Inc.
P. 0. Box 2706
Lubbock, Texas 79408
Original Amount of Contract
$ 408,059.00
Change Order #1
1,599.00
Amended Amount of Contract
409,658.00
Original Date of Completion
September 16, 1980
Change Order #2 (Additional
Time of Completion) 19 weeks
Amended Date of Completion
January 27, 1981
Change Order #3
$ 1,413.00
Amended Amount of Contract
$ 411,071.00
Change Order X64 (Additional
Time of Completion) 42 days
Amended Date of Completion
March 10, 1981
WHEREAS, it is desirable to make changes in the plans and specifications
for this project:
THIS AGREEMENT WITNESSETH: In consideration of the mutual advantages
gained, the Owner and the Contractor agree to the change shown herein and
in the attached exhibits and data, and the Owner and the Contractor agree
that the original contract between them shall be modified and amended to the
extent herein indicated.
IN WITNESS WHEREOF, the Owner and the Contractor have hereto set their
hands this the 12th day of February, 1981.
Anthony Mechanica I
,.
By
CITY OF LUBBOCK
OWNER -%
By
yor
ATTEST:
S cretary - Treasum [ .
RECOIMNDED R AAPPROV
Chie ngineer, Water Utilities
Engin ring