RESOLUTION
�RESOLUTION ACCEPTING IMPROVEMENTS ON A PORTION OF AN ALLEY AS LISTED
BELOW:
WHEREAS, in conformance with the paving requirement provisions of City
Ordinance 1331, the subdivider of Ithica Addition Tracts "A" and "B", made
arrangements with Kerr Construction Company for the construction of paving
improvements on a certain alley dedicated in said subdivision under the
provisions of said Ordinance prior to the recording of the subdivision plat of
Ithica Addition Tracts "A" and "B" including the following alley:
The East - West alley between 22nd Place and 24th Street from the East lip
line of Ithaca Avenue to the North - South alley East of Ithaca Avenue.
AND WHEREAS, the construction of the above improvements on the above-
mentioned alley was performed under the supervision of the City Engineer, and
said improvements have been completed and have been inspected and found to have
been constructed in accordance with City specifications and in accordance with
the provisions of City Ordinance 1331.
THEREFORE, BE IT RESOLVED BY THE CITY OF LUBBOCK, TEXAS.
I.
That the improvements on said portions of the abovementioned alley be
and the same are hereby accepted and the City Engineer be and he is hereby
authorized to direct the payment.
II.
This resolution shall take effect and be in force from and after its passage.
PASSED AND APPROVED THIS 12th
ATTEST:
M, e
Evelyn Ga fga, CityeWry
APPROVED AS TO CONTENT:
Don JePings, pity Engineer
jAPP VED AS
C
hn Ross, Jr., City At o ey
DAY OF FEBRUARY 1981.
r
i
Bi 1 McAlister, Mayor
CONSOLIDATED FINAL ESTIMATE
.._............
ITHICA -ADDITION - TRKS A & B
Accepted February 12, 1981
QUANTITIES
S. Y.
Unit & L.F. Alley
Sub -Unit Location C & G Paving
A. 460-78 East - West alley 61.92 224.87
between 22nd Place
and 24th Street from
the East Lip Line
of Ithaca Avenue to
the North - South alley
East of Ithaca Avenue.
COST ESTIMATE
61.92 L. F. Curb & Gutter @ $ 5.55
224.87 S. Y. Alley Paving @ $ 22.75
64.50 L. F. C & G Removal @ $ 6.25
& Repair
CONTRACT COST
COST DISTRIBUTION
Unit & Contract
Sub Unit Cost
A-460.78 $5,862.58
Property
Owner Cost
$5,862.58
L. F.
C & G
Removal & Repair
64.50
$
343.66
$
5115.79
$
403.13
$
5862.58