HomeMy WebLinkAboutResolution - 1031 - CO#1 To Contract - Carrothers Co - Renovations, SE Water Reclamation Plant - 02/11/1982��$ 111gg2
JWF:da
RF.g0T.TTTTLIN
RESOLUTION 1031 — 2/11/82
(Amends Reso. 992, 12/10/81)
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock BE and is hereby authorized
and directed to execute for and on behalf of the City of Lubbock Change
Order No. 1 to a contract previously entered into by and between said
City and Carrothers Construction Co., Inc. for renovations to the Southeast
Water Reclamation Plant, Lubbock, Texas, attached herewith which shall
be spread upon theminutes of the Council and as spread upon the minutes
of this Council shall constitute and be a part of this Resolution as if
fully copied herein in detail
Passed by the City Council
ATTEST:
this 11th day of February ,1982.
AL-'H9NRY , MAY VIRO TEM
E elyn Gaf ga, City Sec'refa16qreasurer
APPROVED AS TO CONTENT:
Wi o D. Watson, Chief Water Utilities Engineer
APPROVED AS TO FORM:
-�h' Alm—
J. Wo7 Fullingim, Asst. C A orney
RESOLUTION 1031 - 2/11/82
(Amends Reso. 992, 12/10/81)
F1fiK
crrRETARY TREASURER
CHANGE ORDER'NUMBER'ONE
Renovations to the Southeast
Water Reclamation Plant
Lubbock, Texas
TO: Carrothers Construction Co., Inc.
P. 0. Box 269
Paola, Kansas 66071
General description of work included in contract: Renovations to the
Southeast Water Reclamation Plant.
Original Amount of Contract . . . . . . . $567,000.00
Change Order Number One . . . . . . -0-
Adjusted Contract Amount . . . . . . $567,000.00
Adjustment in Construction Time None
WHEREAS, it is desirable to modify the retainage provisions of the
construction contract for this project in order to comply with recently
enacted state legislation.
THIS AGREEMENT WITNESSETH: In consideration of the mutual advantage
gained, the Owner and the Contractor agree to the modifications of Paragraph
GC -46, page GC -15 of the General Conditions of the contract documents for
the project as follows, and further agree that there shall be no change
in the contract price or the completion date for the project.
Retainage shall be equal to 5% of the total amount of
the Engineer's statement for the project instead of 10%
as stated in the contract documents. Other provisions
of Paragraph GC -46 shall remain unchanged.
IN WITNESS WHEREOF, the Owner and the Contractor have hereto set their
hands this the iltb day of , 1982.
CHANGE ORDER NO. 1
Page 1 of 2
Recommended: PARKHILL, SMITH & COOPER, INC., Consulting Engineers
By roj. Engineer, , 1982
Approved: CARROTHERS CONSTRUCTION CO., INC., Contractor
By , • i i vac% , , 1982
Approved:
CITY OF LUBBOCK, TEXAS, Owner
CHANGE ORDER NO. 1
Page 2 of 2
rnT@m 2/11 , 1982