RESOLUTION 1363 - 4/14/83
RESOLUTION ACCEPTING IMPROMENTS ON PORTIONS OF STREETS AND/OR:AVENUES
AS LISTED BELOW:
WHEREAS, in conformance with the paving requirements provisions of City
Ordinance 1331, the subdivider of Security Park Development Lots "B-1 and "C"
made arrangements with Lubbock Asphalt Products Inc. for the construction of
paving improvements on certain streets dedicated in said subdivision under the
provisions of said Ordinance prior to the recording of the subdivision plat of
Security Park Development Lots "B-1" and "C" including the following streets:
South 1/2 of 38th Street from its intersection with the East lip line
of Belmont Avenue to its intersection with a line 15.00' West of the
West Property line of Bangor Avenue known and designated as New
Subdivision Unit Number 1689.
West 1/2 of Belmont Avenue from its intersection with .the Southeast lip
line of Brownfield Highway to its intersection with the South end of
radius at 38th Street known and designated as New Subdivision Sub -Unit
Number 18 of Unit Number 2019.
North 1/2 of 38th Street from its intersection with the East lip line
of Belmont Avenue to its intersection with a line 15.00' West of the
West Property Line of Bangor Avenue known and designated as New
Subdivision Sub -Unit Number 75 of Unit Number 2028.
East 1/2 of Belmont Avenue from its intersection with the Southeast
liprline of Brownfield Highway to its intersection with the South
end of radius at 38th Street known and designated as New Subdivision
Sub -Unit Number 76 of Unit Number 2028.
AND WHEREAS, the construction of the above improvements on the above-
mentioned streets was performed under the supervision of the City Engineer,
and said improvements have been completed and have been inspected and found
to have been constructed in accordance with City specifications and in
accordance with the provisions of City Ordinance 1331.
THEREFORE, BE IT RESOLVED BY THE CITY OF LUBBOCK, TEXAS.
I.
That the improvements on said portions of the abovementioned streets
be and the same are hereby accepted and the City Engineer be and he is
hereby authorized to direct the payment of the City's portion of the cost
in the amount of $9,193.53.,
RESOLUTION
(Page 2)
II.
Thislresolution shall take effect and be in force from and after
',its passage.
PASSED AND APPROVED THIS 14TH DAY OF APRIL, 1983.
� r
Bi McAlis'te , Mayor
ATTEST :
;Evelyn Ga fga; City Sg'crolv
APPROVED AS TO CONTENT:
Pon Jpnirigs.nity Engineer
APPROVED AS TO FORM:
C
n Rossi Jr., City tt
s )�
CONSOLIDATED FINAL ESTIMATE
SECURITY PARK DEVELOPMENT LOTS "B-1" & "C"
Accepted April 14, 1983.
QUANTITIES
S. Y.
Unit & Paving L.F.
Sub -Unit Location 6" Base C & G
NS 1689
S�2- of 38th St. from
the E.L.L. of Belmont
Ave. to 15.00' W. of
W.P.L. of Bangor Ave.
Temple Baptist Church 911.73
NS
W% of Belmont Ave. from
2019-18
the S.E. L.L. of
Brownfield Hwy. to the
S.ER at 38th St.
City Quantities 350.02
NS
N'k of 38th St. from the
2028-75
E.L.L. of Belmont Ave.
to 15.00' W. of W.P.L.
of Bangor Ave.
Developer Quantities 931.92
City Quantities
NS
2028-76 El� of Belmont Ave.
from the S.E. L.L. of
Brownfield Hwy. to the
S.E.R. at 38th St.
Developer Quantities 271.80
Temple Baptist Church 78.22
Total Developer
Quantities 1,203.71
Total Temple
Baptist Church
Quantities 989.95
Total City Quantities 350.02
470.30
534.80
i
S.Y. S. Y.
Alley Valley
Return Gutter
20.20
121.90
656.70
470.30
20.20
5.73
5.73
L. F.
C&G
Removal
and Pavement
Repair
36.00
36.00
TOTAL QUANTITIES 2,543.69 1,127.00 20.20 5.73 36.00
CONSOLIDATED FINAL ESTIMATE
SECURITY PARK DEVELOPMENT LOTS "B-1" & "C"
Accepted April 14, 1983
COST DISTRIBUTION
i
Unit &
Contract
Security Park
Templ.e.Baptist
city
City
Prepaid
Sub Unit
Cost
Developer Cost
Church Cost
Cost
Cost
NS 1689
$ 8,212.97
20.20
$ 8,212.97
Y.
Alley Return
NS 2019-18
2,205.13
5.73
$1,172.44
$1,032.69
NS 2028-75
9,492.00
$2,503.60
1 556.25
6,432.15*
NS 2028-76
2,994.08
2,501.29
492.79
TOTAL
$22,904.18
$5,004.89
$ 8,705.76
$1,728.69
$7,464.84
* $6,175.20 to
be refunded to
Developer
COST ESTIMATE
2,543.69
S.
Y.
Paving 6" Base
@
$ 6.30
1,127.00
L.
F.
Curb & Gutter
@
$ 5.25
20.20
S.
Y.
Alley Return
@
$26.00
5.73
S.
Y.
Valley Gutter
@
$26.00
36.00
L.
F.
C&G Removal & Pavement Repair
@
$ 8.00
$ 16,025.25
$ 5,916.75
$ 525.20
$ 148.98
$ 288.00
CONTRACT COST $ 22,904.18