HomeMy WebLinkAboutResolution - 1468 - Accept Paving Improvements - Kerr Co - Tract A, Fountains Addition - 09/08/1983RESOLUTION 1468 - 9/8/8
RESOLUTION
RESOLUTION ACCEPTING IMPROVEMENTS ON A PORTION OF STREETS AND AVENUES AS
LISTED BELOW:
WHEREAS, in conformance with the paving requirement provisions of City
Ordinance 1331, the subdivider of Fountains Addition Tract "A" made arrange-
ments with Kerr Construction Company for the construction of paving improve-
ments on certain streets dedicated in said subdivision under the provisions of
said Ordinance prior to the recording of the subdivision plat of the above men-
tioned addition including the following streets:
East -1/2 of Chicago Avenue from its intersection with the south
lip line of 50th Street to its intersection with a line 310 feet
south of the south lip line of 50th Street known and designated
as New Subdivision Sub -Unit Number 24 of Unit Number 2029.
East -1/2 of Chicago Avenue from its intersection with the south
property line of Fountains Addition, Tract "A" to its intersection
with the centerline of 53rd Street and designated as New Subdivision
Sub -Unit Number 25 of Unit Number 2029.
North -1/2 of 53rd Street from its intersection with the north east
lip line of Chicago Avenue to its intersection with the west end
of existing street stub at Bangor Avenue known and designated as
New Subdivision Sub -Unit Number 26 of Unit Number 2029.
AND WHEREAS, the construction of the above improvements on the above-
mentioned streets was performed under the supervision of the City Engineer,
and said improvements have been completed and have been inspected and found
to have been constructed in accordance with City Specifications and in accor-
dance with the provisions of City Ordinance 1331.
THEREFORE, BE IT RESOLVED BY THE CITY OF LUBBOCK, TEXAS.
I.
That the improvements on said portions of the abovementioned streets be
and the same are hereby accepted and the City Engineer be and he is hereby
authorized to direct the payment of the City's portion of the cost and to re-
lease escrow money in the amount of $10,212.59.
II.
This resolution shall take effect and be in force from and after its
passage.
PASSED AND APPROVED THIS 8TH DAY OF SEPTEMBER, 1983.
Alan H ry, May
ATTEST:
p
Evelyn Gaf ga, City S c a
APPROVED AS TO CONTENT:
Don J ings, Aity Engineer
APPROVED AS TO FORM:
J ' n Ross, Jr., City Attorney
. . 1
CONSOLIDATED FINAL COST
FOUNTAINS ADDITION
TRACT "A'
Accepted -9-.8-83
QUANTITIES
S.Y. L.F.
Unit & Paving L.F. C & G
Sub -Unit Location 6" Base C & G Removal
2029-24
E-1/2 of Chicago Avenue
@$ 6.80
$27,515.66
1,158.65
from SLL of 50th Street
@$ 5.90
$ 6,836.04
33.50
to 310 feet S. of SLL of
@$ 4.50
$ 150.75
CONTRACT
50th Street
834.79
316.51 33.50
2029-25
E-1/2 of Chicago Avenue
from SPL of Trk. "A",
Fountains Addition to
centerline of 53rd Str.
1,746.46
656.20
2029-26
N-1/2 of 53rd St. from
NE LL of Chicago Avenue
to WE of St. stub at
Bangor Avenue
1,465.17
185.94
Quantities
for Fountains Addt.-`.Tr. "A"
834.79
316.51 33.50
Quantities
for Newman Addt._.Tr. "A'
3,211.63
842.14
TOTAL QUANTITIES
4,046.42
1,158.65 33.50
COST ESTIMATE
4,046.42
S.Y. Paving 6" Base
@$ 6.80
$27,515.66
1,158.65
L.F. Curb & Gutter
@$ 5.90
$ 6,836.04
33.50
L.F. C & G Removal & Disposal
@$ 4.50
$ 150.75
CONTRACT
COST
$34,502.45
,. OF
COST DISTIRBUTION
Unit & Contract Property Pre -paid
Sub -Unit Cost Owner Cost Paving
2029-24 $ 7,694.73 $ 7,694.73
2029-25 $15,747.51 $15,747.51
2029-26 $11,060.21 $11,060.21
TOTAL $34,502.45 $34,502.45
------- Fountains Addt. Trk. "A"
$ 5,963.10 Newman Addt. Trk. "A"
$ 4,249.49 Newman Addt. Trk. "A'
$10,212.59*
* Prepaid paving amount to be released to Newman Addition, Tract "A",
Property owners for payment to paving contractor.