RESOLUTION 1640 - 4/12/84
RESOLUTION
RESOLUTION ACCEPTING IMPROVEMENTS ON A PORTION OF AN ALLEY AS
LISTED BELOW:
WHEREAS, in conformance with the paving requirement provisions
of City Ordinance 1331, the subdivider of Melonie Gardens Addition,
Lots 381-402 made arrangements with M & B Equipment Company for the
construction of paving improvements on an alley dedicated in said
subdivision under the provisions of said Ordinance prior to the recordin
of the subdivision plat of the above-mentioned Addition including the
following alley:
Alley paving from the east lip line of Gary: North of 75th St. to the
intersection of 75th St. and Flint Ave. known and designated as New -
Subdivision Sub -Unit No. 13 of Unit No. 2030.
AND WHEREAS, the construction of the above improvements on the
above-mentioned alley was performed under the supervision of the
City Engineer, and said improvements have been completed and have been
inspected and found to have been constructed in accordance with City
specifications and in accordance with the provisions of City Ordinance
1331.
THEREFORE, BE IT RESOLVED BY THE CITY OF LUBBOCK, TEXAS.
That the improvements on said portions of the above-mentioned
alley be and the same are hereby accepted and the City Engineer be
and he is hereby authorized to direct the payment of the City's portion
of the cost and to release escrow money in the amount of $22,045.69.
This resolution shall take effect and be in force from and
after its passage.
PASSED AND APPROVED THIS 12th DAY OF APRIL, 1984.
AlaV Henry, Mayor
ATTEST:
E elyn Gaf a, tity Se re r
i
APPROVED AS TO CONTENT:
& ��102
Don Jeings, ty Engineer
APPROVED AS TO FORM:
G
ohn Ross, Jr., City Attorney
CONSOLIDATED FINAL ESTIMATE
Melonie Gardens Addition Lots 381-402
Accepted April 12, 1984
UANTITIES
Unit &
Sub -Unit Location
S. Y.
Alley L. F.
Paving C & G
L. F.
Concrete
Sawing
L. F.
C & G
Removal & Disposal
NS 2030-13 N.S. & E. W. Alley
$19,887.08
56.52
L. F. Curb
North of 75th St.
@
$ 5.00
$ 282.60
from the East Lip
L. F. Concrete
Sawing
Line of Gary to the
Removal &
Intersection of 75th
@
$10.00
$ 215.00
at Flint Ave.
938.07 56.52
21.50
44.50
COST ESTIMATE
938.07
S. Y. Alley
Paving
@
$21.20
$19,887.08
56.52
L. F. Curb
& Gutter
@
$ 5.00
$ 282.60
21.50
L. F. Concrete
Sawing
Removal &
Disposal
@
$10.00
$ 215.00
44.50
L. F. C & G
Removal &
Disposal
@
7.50
$ 333.75
CONTRACT
COST
$20,718.43
COST DISTRIBUTION
Unit &
Sub -Unit
Construction
Cost
Developer
Cost
City to
Contractor
NS 2030-13
$20,718.43
$14,093.43
$6,625.00
DISBURSEMENT OF PREPAID FUNDS
$6,625.00 in prepaid account No. 384 to M & B Equipment Co.
$15,420.69 in prepaid account No. 393 returned to Bill Stinson
$22,045.69