HomeMy WebLinkAboutResolution - 1735 - Accept Paving Improvements - MSC - Tract A, Charter Hospital Addition - 06/28/19846,
RESOLUTION 1735 - 6/28/84
i
RESOLUTION
RESOLUTION ACCEPTING IMPROVEMENTS AS LISTED BELOW:
WHEREAS, in conformance with the paving requirement provisions of
City Ordinance 1331, the subdivider of Charter Hospital Addition, Tract "A"
made arrangements with McDevitt S Street Company for the construction of
paving improvements dedicated in said subdivision under the provisions
of said Ordinance prior to the recording of the subdivision plat of the
abovementioned addition, including the following:
Erskine Street, curb and gutter only, from its intersection with the
east lip line of North Salem Avenue to its intersection with a line
235.02 feet east of the east lip line of North Salem Ave. known and
designated as New Subdi.vision Sub -Unit Number 43 of Unit Number 2029.
Concrete drainage channel from the east back of curb at North Salem
& Grinnel to the east -west drainage easement south of Grinnel Street
known and designated as New Subdivision Sub -Unit Number 44 of Unit
Number 2029.
.AND WHEREAS, the'_construction of the above improvements was.performed
under the supervision of the City Engineer, and said improvements have been
completed and have been inspected and found to have been constructed in
accordance with City specifications and in accordance with the provisions
of City Ordinance 1331.
THEREFORE, BE IT RESOLVED BY THE CITY OF LUBBOCK, TEXAS.
That the improvements be and the same are hereby accepted and the
City Engineer be and he is hereby authorized to notify the Developer -of -
acceptance by the Lubbock City Council.
This resolution shall take effect and be in force from and after
its passage.
PASSED AND APPROVED THIS 28th DAY OF
-ATTEST:
t
'City Secretary 1
APPROVED
AS TO
CONTENT:
;Don Jen
Ings,
City
Engineer
APPROVED AS TO FORM:
o n oss, Jr., ity torney
� t
i
CONSOLIDATED FINAL ESTIMATE
CHARTER HOSPITAL ADDITION
Tract "A"
Accepted June 28, 1984
QUANTITIES
Unit & L. F. S. Y.
Sub -Unit Location C & G Drainage
Channel
2029-43 Erskine St. from ELL of N.
Salem Ave. to 235.02' E of
ELL of N. Salem Ave.(C&G only) 247.29
2039-44 Concrete Drainage Channel
from E. back of curb at N.
Salem & Grinnell to E -W
Drainage Easement S of
Grinnell St. 40.36 260.17
Total Quantities 287.65 260.17
COST DISTRIBUTION
Unit &
Sub -Unit Contract Developer
Cost Cost
2029-43 $1,409.55 $1,409.55
2029-44 $6,994.47 $6,994.47
Total $8,404.02 $80404.02
CONSOLIDATED FINAL ESTIMATE
CHARTER HOSPITAL ADDITION
Tract "A"
Accepted June 28, 1984
S. Y.
Unit & L.F. Drainage
Sub -Unit Location C & G Channel
2029-43 Erskine St. from ELL of N.
Salem Ave. to 235.02' E of
ELL of N. Salem Ave.
(C&G only) 247.29
2039-44 Concrete Darinage Channel
from E. back of curb at N.
Salem & Grinnell to E -W
Drainage Easement S of
Grinnell St. 40.36 260.17
Total Quantities 287.65 260.27
COST DISTRIBUTION
Unit &
Sub -Unit
Contract
Cost
2029-43
$1,409.55
2029-44
$6,994.47
Total
$8,404.02
Developer
Cost
$1,409.55
$6,994.47
$8,404.02