RESOLUTION
RESOLUTION ACCEPTING IMPROVEMENTS ON PORTIONS OF STREETS AND AVENUES
AS LISTED BELOW:
WHEREAS, in conformance with the paving requirement provisions of
City Ordinance 1331, the subdivider of King's Gate Addition, Tract "F"
made arrangements with Kerr Construction Company for the construction of
paving improvements on certain streets dedicated in said subdivision under
the provisions of said Ordinance prior to the recording of the subdivision
plat of the above mentioned addition including the following streets:
84th Street from its intersection with the east lip line of
Orlando Avenue to its intersection with a line 16 feet west
of west property line of Nashville Avenue known and design-
ated as New Subdivision Sub -Unit Number 40 of Unit Number
2030.
Orlando Avenue from its intersection with aline 13 feet
south of south property line of 82nd Street to its inter-
section with a line 16 feet south of south property line of
84th Street and designated as New Subdivision Sub -Unit
Number 41 of Unit Number 2030.
AND WHEREAS, the construction of the above improvements on the above
mentioned streets was performed under the supervision of the City Engineer,
and said improvements have been completed and have been inspected and found
to have been constructed in accordance with City Specifications and in accor-
dance with the provisions of City Ordinance 1331.
THEREFORE, BE IT RESOLVED BY THE CITY OF LUBBOCK, TEXAS.
I.
That the improvements on said portions of the above mentioned streets
be and the same are hereby accepted and the City Engineer be and he is
hereby authorized to notify the Developer of acceptance by the Lubbock City
Council.
II.
This resolution shall take effect and be in force from and after its
passage.
PASSED AND APPROVED THIS 13TH DAY OF SEPTEMBER, 1.984.
ATTEST._
, City secretary
APPROVED AS TO FORM:
ID�
Don nning ity Engineer
APPROVED AS TO FORM:
n G. KOSS, Jr.,
CONSOLIDATED FINAL ESTIMATE
KING'S GATE ADDITION
TRACT "F"
Accepted 9/13/1984
QUANTITIES
Resolution 1810
2030-41 Orlando Ave. from 13'
S of SPL of 82nd St.
to 16'S of SPL of 84th
Street. 246.58 2,900.53 1,387.54 190.64
TOTAL QUANTITIES 246.58 7,867.45 3,612.77 283.36
122.31 263.76
318.27 513.76
COST ESTIMATE
7,867.45 S.Y. Paving 6" Base @$ 6.65 $52,318.54
3,612.77
S.Y.
S.Y.
L.F. S.Y. Alley
S.Y.
L.F.
Unit &
6" Rein.
Paving
6" Ret. & Drg.
Valley
12"
Sub -Unit Location
Concrete
6" Base
C.&_G. Channel
Gutter
C & G
@$ 8.90
Paving
246.58
S.Y. 6" Reinforced Concrete Paving
@$23.50
$ 5,794.63
2030-40 84th St. from ELL of
CONTRACT COST
$96,996.02
Orlando Ave. to 16'
W of WPL of Nashville
Avenue.
4,966.92
2,225.23 92.72
195.96
250.00
2030-41 Orlando Ave. from 13'
S of SPL of 82nd St.
to 16'S of SPL of 84th
Street. 246.58 2,900.53 1,387.54 190.64
TOTAL QUANTITIES 246.58 7,867.45 3,612.77 283.36
122.31 263.76
318.27 513.76
COST ESTIMATE
7,867.45 S.Y. Paving 6" Base @$ 6.65 $52,318.54
3,612.77
L.F. Curb & Gutter
@$ 5.85
$21,134.70
283.36
S.Y. Alley Return & Drainage
Channels
@$21.90
$ 6,205.58
318.27
S.Y. Valley Gutter
@$21.90
$ 6,970.11
513.76
L.F. 12" Curb & Gutter
@$ 8.90
$ 4,572.46
246.58
S.Y. 6" Reinforced Concrete Paving
@$23.50
$ 5,794.63
CONTRACT COST
$96,996.02
COST DISTRIBUTION
Unit & Construction Developer
Sub -Unit Cost Cost
2030-40 $54,594.70
$54,594.70
3030-41 $42,401.32
$42,401.32
TOTAL $96,996.02