HomeMy WebLinkAboutResolution - 1973 - Accept Water & Sewer Improvements -Panhandle Construction - Tracts A & B PR Add - 03/14/1985ck
RF.gnT.TTTTnN
Resolution #1973
Agenda Item #25
March 14, 1985
RESOLUTION ACCEPTING WATER AND SEWER SYSTEM IMPROVEMENTS FOR TRACTS
"A" and "B", PHEASANT RUN ADDITION.
WHEREAS, the developer of Tracts "A" and "B", Pheasant Run Addition
have complied with the provision of the City of Lubbock Code, Chapter 28,
Article 1V, by providing the water and sewer improvements for said addition
in accordance with paragraph 156 of said Chapter 28, and
WHEREAS, the total utility cost to the developer is $15,337.83 with
the improvements constructed by Panhandle Construction Company having a
value of $14,188.00 as determined by the unit prices established by said
Chapter 28, and $1,149.83 cash paid to the City, with FFS/CDHH Joint Venture,
the developer, to receive a refund of $15,337.83 in accordance with Chapter
28 of the Code of the .City .of Lubbock, and
WHEREAS, the construction of the said water and sewer improvements was
performed under the supervision of the Water Utilities�Engineer and completed
in accordance with the City of Lubbock's plans and specifications,
NOW THEREFORE BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
1. That the improvements be and the same are hereby accepted as an
integral part of the water and sewer pystem of the City of Lubbock.
2. That the refundable cost in the amount of $15,337.83 be made in
accordance with said Chapter 28.
3. This resolution shall take effect and be in force from and
after its passage:.
PASSED AND APPROVED THIS 14th DAY AF zl March �, 1985.
Henry,
Boyd, City Secretary
APPR VED AS CONTENT:
e
Wil?-olr,d D. Watson,''Chief Water
Utilities Engineer
APPROVED AS TO FORM:
,P— C. `F —
ty Attorney