HomeMy WebLinkAboutResolution - 2038 - CO#2 To Contract - Marecon Inc - Terminal Apron Expansion, LIA - 05/23/1985MH:js
RESOLUTION
Resolution #2038
May 23, 1985
Agenda Item #38
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock BE and is hereby authorized and
directed to execute for and on behalf of the City of Lubbock a Change Order
No. 2 by and between the City of Lubbock and Marecon, Inc. and to make
final payment for Lubbock International Airport Terminal Apron Expansion,
attached herewith, which shall be spread upon the minutes of the Council
and as spread upon the minutes of this Council shall constitute and be a
part of this Resolution as if fully copied herein in detail.
Passed by the City Council this 23rd
ATTEST:
11 Ranette yd, City Secretary
--f-APPROVED AS TO CONTENT:
rvin Coffee, Dire or of Aviation
APPROVED AS TO FORM:
Michele Hart;—Assistant City Attorney
To: Marecon, Inc.
2727 Kirby, Suite 205
Houston, Texas 77098
Resolution #2038
CHANGE ORDER NO. 2
Lubbock International Airport
Terminal Apron Expansion
AIP Project Nos. 3-48-0138-01 & 02
ADAP Project No. 6-48-0138-16
April, 1985
General description of work included in contract:
The construction of approximately 43,000 square yards of rigid pavement
on the terminal apron, removal. of existing pavement, construction of
drainage structures, excavation work, taxiway edge lighting, utilities and
other related items of work.
Original Amount of Contract . . . . . . . . . . . . . . $ _2,366,215.80
Change Order No. 1 . . . . . . . . . . . . . . . .(Add) 6,168.70
Adjusted Contract Price $2,372,284.50
Original Construction Time . . . . . . . . . . . . . .. 300 Calendar Days
Change Order No. 1 . . . . . . . • . . . . . . .(Add) 19 Calendar Days
Adjusted Construction Time 319 -Calendar Days
Change Order No. 2 . . . . . . . .. . . . . . . ..(Add) 114 Calendar Days
New Adjusted Construction Time 433 Calendar Days
WHEREAS, it is desirable to make certain changes in the work included under
this project:
AND WHEREAS, during the construction time provided by the contract for the
project, work was delayed due to weather conditions and other justified delays
during critical periods of construction the Owner and Contractor agree that the
time allowed for the completion of the project shall be extended 114 calendar
days, from 319 calendar days to 433 calendar days.
THIS AGREEMENT WITNESSETH: In consideration of the mutual advantage gained,
the Owner and the Contractor agree to the changes indicated above.
The aforementioned changes, and work affected thereby, are subject to all
contract stipulations and covenants.
CHANGE ORDER NO. 2
Page 1 of 2
IN WITNESS WHEREOF, the Owner and.the Contractor have hereto set their
hands this 23rd duty. of Mav , 1985.
RECOMMENDED: PARKHILL, SMITH & COOPER, INC., Consulting Engineers
Project
By. 4oa , Engineer, A my- Z`'1 , 1985
APPROVED: MARECON, INC., Contractor
By, /G• G • ,/KI, ,_ Z— 1985
APPROVED: CITY OF LUBBOCK, TEW, Owner
By
ATTEST:
-APPROVED AS TO CONTENT:
Ma&Cgr May 23 , 1985
City Secretary
wau,lr� pa4&---4
Ma vin Coffee
Director of Aviation
CHANGE ORDER NO. 2
Page 2 of 2