RESOLUTION
Resolution #2163
October 10, 1985
Agenda Item #22
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock BE and is hereby authorized and
directed to execute for and on behalf of the City of Lubbock Change Order
#7 to Terminal Expansion Contract between the City of Lubbock and Lee Lewis
for the relocation of the airport security office, attached herewith, which
shall be spread upon the minutes of the Council and as spread upon the
minutes of this Council shall constitute and be a part of this Resolution
as if fully copied herein in detail.
Passed by the City Council this 10th day of
ATTEST:
, ulty 5ecretar
APPROVED AS TO CONTENT:
Marvin Coffee,
4r)9oro Aviation
APPROVED AS TO FORM:
ichel art, Assf-s an City Attorney
October , 1985.
"ANNY0R
W
W
Resolution #2163
CHANGE Distribution to:
ORDER OWNER ❑
ARCHITECT ❑
AIA DOCUMENT G701 CONTRACTOR ❑
FIELD ❑
OTHER ❑
PROJECT: Lubbock International Airport CHANGE ORDER NUMBER: seven (7)
(name, address) Terminal Building - Phase II
Lubbock, Texas INITIATION DATE: September 30, 1985
TO (Contractor)
--j ARCHITECT'S PROJECT NO: 82-07-01
F Lee Lewis General Contractor 1 CONTRACT FOR: General Construction
2521 74th Street
Lubbock, Texas 79423
L I CONTRACT DATE: June 14, 1984
You are directed to make the following changes in this Contract:
Include in the work revisions to the Security Office area as indicated on sheets
5.7, M-24, E-37.
$44,697.00*
Note: This amount shall be deducted from the Contract Contingency Allowance.
The balance of the Contingency Allowance following this Change Order i s :
Original Contingency Allowance $410,000.00
Less Previous Change Orders -228,164.00
Less this Change Order 44,697.00
Contingency Allowance Balance $137,139.00
Not valid until signed by both the Owner and Architect.
Signature of the Contractor indicates his agreement herewith, including any adjustment in the Contract Sum or Contract Time.
The original (Contract Sum) XtXIX.*XrXtXXaXXA ("X6&4 was ........................... $ 6,976,775.00
Net change by previously authorized Change Orders ................................... $ 228,164.00
The (Contract Sum) ( XtkX)MAX%X0XiDhXq")'prior to this Change Order was .......... $ 6,976,775.00
The (Contract Sum) 0WX*X*X1kXX GXrX)CkXtX will be %U*X"X(XX(XXy6AXX(unchanged)
by this Change Order ..............
The new (Contract Sum)XUXP)iX*4"N0AKX(X0Q including this Change Order will be ... $ 6,976,775.00
The Contract Time will be ( X%X"X0X(XX,*X$)X(unchanged) by ( 0 ) Days.
The Date of Substantial Completion as of the date of this Change Order therefore is Jude 10 , 1986
Authorized:
Whitaker McQueen Jones & Assoc. Lee Lewis Ge�ntractor ICiity of Lubbock,Texas
ARCHITECT _ CQN�f ACT Tn��c OWI fji)hnck . Texas