Resolution #2241
February 13, 1986
Agenda Item #21
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock BE and is hereby authorized and
directed to execute for and on behalf of the City of Lubbock a Change Order
No. 2 extending the time limitations to the existing contract of the Quirt
Avenue Overpass Project, G.W.O. 11,684, for paving improvements between
said City and Heavy Highway Constructors, Inc., attached herewith, which
shall be spread upon the minutes of the Council and as spread upon the
minutes of this Council shall constitute and be a part of this Resolution
as fully copied herein in detail.
Passed by the City Council this 13th day of February , 1986.
AL AN, HENRY , MAYOR
ATTEST:
aneLu.e Moya, ulLy 5ecreLary
APPROVED AS TO CONTENT:
Larry Hof an, D r ct r of�
Transpor ation
APPROVED AS TO FORM:
arold Willard, Assistant City
Attorney
Resolution #2241
CHANGE ORDER NO. 2
Quirt Avenue Overpass
CDWO 38409
GWO 11684
Lubbock, Texas
February 3, 1986
To: HEAVY HIGHWAY CONSTRUCTORS, INC.
P.O. Box 1488
Amarillo, Texas 79105
General description of work included in original contract:
Improvements to Quirt Avenue from 31st Street to 37th Street including
the construction of a nine -span, 972`-6" prestressed concrete overpass
structure, retaining walls, concrete approach pavement, flexible at grade
approach pavement and frontage roads, water and sanitary sewer utility
modification and construction, storm drainage adjustments, and related
items of work.
Original Amount of Contract. . . . . . . . . . . $2,886,434.50
Change Order No. 1 . . . . . . . . . . . . . . . 12, 018.45
Change Order No. 2 . . . . . . . . . . . . . . . -0-
Adjusted Contract Amount. . . . . . . . . . $2,898,452.95
Adjustment in Construction Time . . . . . . 65 Calendar Days
WHEREAS, the Contractor has experienced certain delays in completion
of the construction work due to:
1. Unfavorable weather conditions at various stages
during construction of the project.
2. Delays in relocation of certain private utilities
within the project area.
3. Delays in relocation of certain railroad facilities
within the project area.
THIS AGREEMENT WITNESSETH: In consideration of the above listed
delays, the Owner and the Contractor agree to an extension of construction
time allowed for the project of sixty five (65) calendar days.
The aforementioned changes and work affected thereby, are subject to
all contract stipulations and convenants.
CHANGE ORDER NO. 2
Page 1 of 2
IN WITNESS THEREOF, the Owner and the Contractor have hereto set their
hand this the 13th day of February , 1986.
RECOMMENDED: PARKHILL, SMITH & COOPER, INC., Consulting Engineers
BYJ�%G�ZProj . Engineer, P2-7 ,1986
APPROVED: HEAVY HIGHWAY CONSTRUCTORS, INC., Contractor
By , ,1986
APPROVED: CITY OF LUBBOCK, TEXAS, Owner
ATTEST:
By Mayor February 13
C4t=y Secretary
�PPROVE2,73 AS 710
f
Approved as to form:
kw V�
AWidentM Attorney
CHANGE ORDER NO. 2
Page 2 of 2
,1986
February 7, 1986
Mr. Larry Hertel, P.E.
City of Lubbock
P.O. Box 2000
Lubbock, Texas 79457
Re: City of Lubbock
Quirt Avenue Overpass
CDWO 38409
GWO11684
Dear Larry:
Attached are five (5) copies of Change Order No. 2 signed by the
Contractor and the Engineer. After execution by the City please return
one copy to the Contractor and two copies to this office.
Sincerely,
PARKHILL, SMITH & COOPER, INC.
By �6
Ter G. Bilderback, P.E.
TGB/slo