HomeMy WebLinkAboutResolution - 2291 - CO#1 To Contract - Caprock Highway Construction - Park Drainage - 04/09/1986Resolution #2291
April 9, 1986
Agenda Item #12
T2'P QOT TT T T OOT
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock BE and is hereby authorized and
directed to execute for and on behalf of the City of Lubbock a Change Order
No. 1 adding quantities to G.W.O. 011675 Park Drainage Channel Improvements
to existing contract for drainage improvements between said City and Caprock
Highway Construction Co., attached herewith, which shall be spread upon the
minutes of the Council and as spread upon the minutes of this Council shall
constitute and be a part of this Resolution as if fully copied herein in
detail.
Passed by the City Council this
ATTEST:
9th day of April
1986.
Ranettt Boyd, City Secretary
APPROVED AS TO CO TENT: \
c
Larry V. fman, D' ctor of Transportation
AS TO FORM:
— d" V64 ��+Vwl
J.;'+T rth Fullingim, Ass'stant City Attorney
TO:
Gentlemen:
CHANGE ORDER NO. 1 TO G.W.O. 011675
PARK DRAINAGE CHANNEL IMPROVEMENTS
Caprock Highway Construction Co.
5185 - 69th Street
Lubbock, Texas 79424
WHEREAS, it is desirable to make changes in the plans
this project, being namely the addition of the quantities
the Special Conditions of the Contract documents, and;
Resolution #2291
& specifications for
as is specified in
WHEREAS, the Contractor herein agrees to the following change:
Original Contract Amount = $142,842.90
Increased By Change Order No. 1 = $27,170.50
Total Amount of Contract = $170,013.40
Completion date of this Change Order is December 5, 1986
THIS AGREEMENT WITNESSETH: In consideration of the mutual advantages
gained, the Owner and the Contractor agree to the change shown herein and in
the revised plans, the Owner agrees to pay the Contractor the amount of increase
in cash. The Contractor agrees to proceed with construction and to adhere to
applicable specifications, under the direction of the Engineer. Furthermore,
the parties agree that the original contract between the Owner and the Contractor
shall be modified to the extent herein indicated, including one (1) attachment.
IN WITNESS WHEREOF, the Owner and the Contractor have hereto set their hands
this 9th day of April 1986.
C hway Construction Co.
eside t
OF LUBBOCK
(OWNER)
ATT
Ranette oyd, City Secretary
RECOMMENDED
Larry V offman,//rector of
Transpo ation
APP 0VED AS TO FORM:
J
�nC. Ross,Jr., City ttorney
FOR APPROV
LarrCtidiingham, CitM nager
CHANGE ORDER NO. 1
G.W.O. 011675
Park Drainage Channel Improvements
Location - Lake #19, #26, #31, #88 & #25
Original Contract Amount
Estimated Quantities & Prices Added by this Change Order:
(In Lake #25)
Bid Item
Number Description
Resolution #2291
$142,842.90
1.
7660
S.F.
Drainage
Slab 4"
R.C. (3000 #/7 Day)
@
$1.89
= $14,477.40
2.
900
L.F.
Drainage
Channel
40' wide graded
@
$3.60
= $3,240.00
3.
1000
C.Y.
Unclassified Excavation
C.Y.
@
$2.50
= $2,500.00
4.
2010
S.F.
Errosion
Structure
4" R.C. (3000 #/7
Day) @
$1.79
= $3,597.90
5.
312
L.F.
Curb and
Gutter
(12")
@
$5.85
= $1,825.20
6.
600
S.F.
Spillway
Slab 6"
R.C.
@
$2.55
= $1,530.00
Sub -Total C.O. #1 - $27,170.50
NEW CONTRACT AMOUNT $170,013.40