Resolution #2475
December 11, 1986
Item #16
RESOLUTION ACCEPTING DRAINAGE IMPROVEMENTS AS LISTED BELOW:
WHEREAS, in conformance with the paving requirement provisions of
City Ordinance No. 1331, the subdivider of King's Gate Addition, Tract
"G" made arrangements with Lee Lewis General Contractor, Inc., for the
construction of drainage improvements and Kerr Construction Company for
the construction of paving improvements in said subdivision under the
provisions of said Ordinance prior to the recording of the subdivision
plat of the above-mentioned addition including the following
construction:
84th Street from its intersection with a line 13.00 feet east
of the east property line of Quaker Avenue to its
intersection with a line 16.00 feet west of the west property
line of Orlando Avenue including drainage slab on north side
of Tract "G" known and designated as New Subdivision Sub -Unit
Number 73 of Unit Number 2031; and
WHEREAS, the construction of the above improvements was performed
under the supervision of the City Engineer, and said improvements have
been completed and have been inspected and found to have been constructed
in accordance with City specifications and in accordance with the
provisions of City Ordinance No. 1331; NOW THEREFORE:
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
SECTION 1. THAT the improvements be and the same are hereby
accepted and the City Engineer be and he is hereby authorized to notify
the developer of acceptance by the Lubbock City Council.
SECTION 2. THAT this Resolution shall take effect and be in force
from and after its passage.
Passed by the City Council this 11th day of December , 1986.
B. C. McMINN, MAYOR
Boyd, City
APP AS C AS FO
i
t
Larry V. f , C' Engineer Fullingim, Assi t
QUANTITIES
Unit &
Sub -Unit
2031-73
CONSOLIDATED FINAL ESTIMATE
King's Gate Addition
Tract "G"
Accepted 12-11-86
S.Y. Paving S.Y. Drainage
Location 6" Base L.F. C&G Channel
84th St, from 13' East of EPL of 3,966.14 1,880.16 922.45
Quaker Ave. to 16 ft. W of WPL
of Orlando Avenue including drain-
age slab on N. side of Tract "G"
This work was constructed under two contracts:
Kerr Construction - Paving & C&G
Lee Lewis Construction - Drainage Channel
COST ESTIMATE
3966.14 S.Y. Paving 6" Base @$6.65 $26,374.83
1880.16 L.F. Curb & Gutter @$5.90 $11,092.94
922.45 S.Y. Drainage Channel @Lump Sum $14,000.00
CONTRACT COST $51,467.77
COST DISTRIBUTION
Unit & Contract Developer
Sub -Unit Cost Cost
2031-73 $51,467.77 $51,467.77