HomeMy WebLinkAboutResolution - 2681 - Accept Paving Improvements - Kerr Construction - L556-579 Kingsgate Addition - 11/12/1987Resolution #2681
November 12, 1987
Agenda Item #10
JWF•js
RFSnl IITTnN
RESOLUTION ACCEPTING IMPROVEMENTS ON PORTIONS OF STREETS AS LISTED
BELOW:
WHEREAS, in conformance with the paving requirement provisions of City
Ordinance 1331, the subdivider of King's Gate Addition, Lots 556 thru 579
made arrangements with Kerr Construction Company for the construction of
paving improvements on certain streets dedicated in said subdivision under
the provisions of said Ordinance prior to the recording of the subdivision
plat of the above-mentioned Addition including the following streets:
Peoria Avenue from its intersection with the South lip line of 96th
Street to its intersection with the North lip line of 97th Street
known and designated as New Subdivision Sub -Unit Number 56 of Unit
Number 2033.
97th Street from Quaker Avenue to and including the cul-de-sac 600
feet East of Quaker Avenue known and designated as New Subdivision
Sub -Unit Number 57 of Unit Number 2033; and
WHEREAS, the construction of the above improvements on the above-
mentioned streets was performed under the supervision of the City Engineer,
and said improvements have been completed and have been inspected and found
to have been constructed in accordance with City specifications and in ac-
cordance with the provisions of City Ordinance -.1331; NOW"THEREFORE
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
SECTION 1. THAT the improvements on said portions of the above-
mentioned streets BE and the same are hereby accepted and the City Engineer
BE and he is hereby authorized to notify the Developer of acceptance by the
Lubbock City Council.
SECTION 2. THAT this Resolution shall take effect and be in force
from and after its passage.
Passed by the City Council on this 12th day of November 1987.
C. McMINN, MAYOR
Rane
ty Secretary
I APPR VE4'9S 0 C TNT:
Larry V. o fm n, for of
Transpo ation
APPROV AS TO ORM:
r
J. Vo7th Fullingim, Assistant Ci
Att ey
QUANTITIES
Unit &
Locat
CONSOLIDATED FINAL ESTIMATE
KING'S GATE ADDITION
Lots 556 thru 579
Accepted 11-12, 1987
S.Y. L.F. S.Y S.Y. L.F.
Paving Alley Valley C&G
6" Bas C&G Returns Gutter Remo
2033-56 Peoria Ave. from SLL of 1,040.8 619.58 62.82 52.54 120.00
96th. St. to NLL of
97th. St.
2033-57 97th. St. from Quaker Ave 2,623.20 1,297.31 49.76 45.00
to and including cul-de-sac
600' E of Quaker Ave.
TOTAL Quantities
COST ESTIMATE
3,663.58 S.Y. Paving-6"Base
1,916.89 L.F. Curb and Gutter
112.58 S.Y. Alley Returns & Dr. Ch.
52.54 S.Y. Valley Gutter
165.00 L.F. C&G Removal
COST DISTRIBUTION
Unit & Contract
Sub -Unit Cost
3,663.50 1,916.89 112.58 52.54 165.00
at $6.00
at $4.90
at $21,80
at $21.80
at $4.00
Developer
Cost
2033-56 $ 12,273.06 $ 12,273.06
2033-57 $ 23,360.79 $ 23,360.79
$ 35,633.85 $ 35,633.85
$,21,981.48
$ 9,392.76
$ 2,454.24
1,145.37
$ 660.00
$ 35,633.85