HomeMy WebLinkAboutResolution - 2663 - Accept Paving Improvements-Heavy Highway Construction-Quirt Ave Overpass, E 34Th - 10/22/1987JWF:da
RESOLUTION
Resolution #2663
October 22, 1987
Agenda Item #18
WHEREAS, the City of Lubbock entered into a Contract with Heavy
Highway Constructors, Inc. for the construction of the Quirt Avenue
Overpass at East 34th Street (Project No. 9941); and
WHEREAS, said overpass has been completed including certain remedial
work as agreed to between the parties; and
WHEREAS, HDR Infrastructure, Inc., as consulting engineers for the
City of Lubbock, designed said overpass structure and observed the work in
progress to completion including the remedial work agreed to by the
parties, and the overpass is found to have been constructed in accordance
with terms of said contract with the exception that remedial work had to be
done as agreed to by the parties, which remedial work has been completed as
agreed; NOW THEREFORE:
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
SECTION 1. The following letters are attached to this resolution and
made a part hereof as follows:
EXHIBIT A: Letter from Heavy Highway Constructors, Inc. to City
Engineer Larry Hoffman dated July 21, 1987.
EXHIBIT B: Letter from HDR Infrastructure, Inc. to City Manager
Larry Cunningham dated July 31, 1987.
EXHIBIT C: Letter from City Manager Larry Cunningham to Heavy
Highway Constructors, Inc. dated August 17, 1987.
EXHIBIT D: Letter from Heavy Highway Constructors, Inc. to City
Manager Larry Cunningham dated August 24, 1987.
EXHIBIT E: Letter from City Engineer Larry Hoffman to Heavy Highway
Constructors, Inc. dated August 28, 1987.
Such letters constitute the contractual letter agreements between the City
of Lubbock and Heavy Highway Constructors, Inc. fot' the remedial work on
the overpass, final payment arrangements with respect to payment for
allowance for maintenance costs of $40,000.00 for the asphaltic concrete
overlay, and guarantee of the asphaltic overlay on the overpass by Heavy
Highway Constructors, Inc. to the City of Lubbock for an additional two
years beyond the one year of guarantee contained in the original contract,
in effect constituting a three year guarantee commencing on the date of
formal acceptance by the City Council.
SECTION 2. The City of Lubbock accepts the overpass improvements and
said remedial work as complete subject to the following agreements made by
the Contractor Heavy Highway Constructors, Inc.:
(A) Three year guarantee of the asphaltic overlay on the overpass
as hereinabove set forth and in said letters of agreement
attached hereto.
(B) Payment of $40,000.00 to the City of Lubbock by deduction from
retainage moneys due the Contractor Heavy Highway Constructors
Company, Inc. from the City of Lubbock to cover estimated
additional maintenance costs for twenty years.
SECTION 3. The City Engineer is hereby authorized to direct the
payment of $84,447.37 to Heavy Highway Constructors, Inc. as final payment
for said overpass improvements. The amount of $84,447.37 is arrived at by
taking the amount now held by the City of Lubbock in retainage under the
original contract of $124,447.37 and subtracting the $40,000.00 for
maintenance of the asphaltic concrete overlay on the overpass as
hereinabove described which leaves the amount of $84,447.37 as the sum due
the Contractor Heavy Highway Constructors, Inc. from the City of Lubbock,
payment for which is hereinabove authorized.
Passed this 22nd day of October , 1987.
ATTEST:
ty Secre'tar
APPROVED AS TO CONTENT:
Larry H furan, ctor of
Transp tation nd City Engineer
APPROVED AS TO FORM:
J. WIVrth Fullingim, Assistfint
City Attorney
-2-
sC/ • Z7 ,y�fcW
'B. C. McMINN, MAYOR
HEAVY HIGHWAY CONSTRUCTORS, INC.
P.O. BOX 1 488 - AMARILLO, TEXAS 791 05-606/374-0932
July 21, 1987
Mr. Larry Hoffman
City Engineer
City of Lubbock
P. O. Box 2000
Lubbock, TX 79457
RE: Quirt Avenue Overpass
Dear Mr. Hoffman:
We have spent approximately $63,000 in crack sealing on the Quirt Avenue
bridge deck. In response to HDR's request for another remedy, we propose
this remedial action:
We propose to overlay the entire bridge deck with two courses of surface
treatment and IV of asphaltic concrete with latex asphalt. Prior to the
overlaying operation, we also propose to have all the construction joints
sawed and sealed with joint sealing compound and raise existing sealed
expansion joints by 2". We will also guarantee the overlay over the bridge
deck for an additional two years. We believe this will be the best way
to protect the bridge deck from moisture. For a better appearance, we also
propose to overlay the concrete pavement area as well.
Attached is a listing of proposed quantities and materials.
Yours very truly,
FCC:sv
cc: HDR Infrastructure
EXHIBIT 11A"
Equal Opportunity Employer
No Text
HDR Infrastru ra, Inc. Suite 125 Telephone (atr Resources
A Centerra Company 12700 Hillcrest Road 214 980-0001 Wastewater
Dallas, Texas Hazardous Waste
75230-2096 Bridges
Transportation
Industrial
July 31, 1987
Mr. Larry J. Cunningham
ffCity Manager
ww,�,,LL `
779457
Dear Mr. Cunningham:
We have reviewed the remedial action proposed by Heavy Highway
Constructors, Inc..(contractor) as described in their letter of
July 21, 1987 to the City of Lubbock. The proposed remedy -of
overlaying the entire bridge deck with a two -course surface
treatment, and 1 1/2 inches of asphaltic concrete is a deck
sealing practice not uncommon to the Texas State Department -Of
Highways and Public Transportation (SDHPT) for new bridge decks
constructed in the northern areas of the State. Further, the
✓ contractor has offered to extend the warranty of the deck overlay
✓✓✓ an additional two years beyond the one year warranty as stipulated
��✓ in.the construction contract, thus resulting in a total.warranty
period of three years after acceptance of the bridge by the City
of Lubbock.
Unlike the asphaltic concrete overlay system normally used by the
SDHPT, the contractor has proposed using latex modified asphalt
surface treatments in conjunction with a latex modified asphaltic
concrete overlay. The elastomeric properties of latex -modified
asphalt gives the overlay system additional toughness and
ductility. These properties give the overlay system additional
resistance to reflective cracking.
We are of the opinion that the contractor's proposed remedial
action of installing a latex modified asphaltic concrete overlay
system will protect the concrete deck from moisture. This will
reduce the potential for moisture, which may carry deicing salt,
to penetrate to the deck reinforcing steel, resulting in corrosion
of the steel and eventual spalling of the concrete.
The potential for water saturation of the bridge deck is also
generally due to poor deck drainage conditions. We feel this
potential is also minimized on the Quirt Avenue structure because
of the crest curve coupled with steep approach grades. This
conclusion assumes, however, that maintenance personnel keep the
deck drains clean, as well as accumulated debris removed, thus
permitting moisture to drain away freely and quickly.
EXHIBIT B��
M
Mr. Larry Cunningham
July 31, 1987
Page 2
The method the contractor has proposed for sealing the bridge deck
also provides an additional 1 1/2 inches of asphaltic concrete
wearing surface. This additional wearing surface effectively
becomes an additive to the concrete wearing surface which was -
originally required to be provided by the contractor. In addition
to the sealing effect gained by the additional 1 1/2 inches of
wearing surface, the integral wearing surface of the concrete deck
will also be preserved. This, in our opinion, would result in a
""As"�rou dote .n .ya�ra Jay...l *4 987 : i�et' "r} tt3 lilR "the.,: ettiod _sof
'repair';must not restilt `in -a ,bridge deck with maintenance
requirements in excess of those dictated by a new concrete deck
with no cracks." As we discussed in our meeting with you and.your
staff on j une. 18, 1987, both concrete and asphaltic concrete
:� pavemen#s <requi re maintenance. The asphaltic -concrete overlay,
however, may require more maintenance than the concrete pavement
due to the different characteristics of asphalt. The potential
for increased maintenance costs could be dealt with by extended
warranties, similar to those proposed by the contractor, or actual -
contractor maintenance responsibilities.
Based upon these conclusions and the above discussion, we
recommend that the City accept the contractor's proposal with the
following possible alternative modifications. Because of the
potential for increased maintenance costs associated with the
asphaltic concrete overlay, the City could pursue three (3)
options to mitigate the maintenance costs.
(1) Increase the warranty period proposed by the contractor
from an additional two (2) years to an additional ten
(10) years;
(2) Require the contractor to furnish and install the
initial maintenance seal coat approximately five (5) to
eight (8) years hence; or
(3) Accept a cash payment from the contractor to compensate
the City for the differential in maintenance costs.
It should be noted that the latter two options are assumed to be
considered in addition to the additional two (2) year deck overlay
warranty as proposed by the contractor. Specific details of the
repair procedures and warranty obligations would necessarily need
to be defined further and agreed upon by all parties prior to
final acceptance of the proposal.
13a
Mr. Larry Cunningham
July 31, 1987
Page 3
We sincerely hope the above information satisfactorily addresses
the advisability of the City accepting the contractor's proposed
course of.action. Should you desire additional information or
require clarification of any of the above discussion, please do
not hesitate to contact me at (214) 980-0001.
Very truly yours,
,,,kftk'TNFRAMUCTURE ; "°ifi]C .
K s
William B. Hagood, P.E.
Vice President
cc.: Mr.J im-Bertram, Assistant City Manager
Mr. Larry Hoffman, Director of Transportation
Mr. John Ross, City Attorney
Mr. Bill Dowd, Assistant Vice President, HDR
Mr. Virgil Meedel, Senior Vice -President, HDR
$CITY OF LUBBOCK
®� \Office of
'3 The City Manager
5 P.O. Box 2000
Lubbock, Tx. 79457
(806) 762-6411
August 17, 1987
Mr. F.C. Chow
President
Heavy Highway Constructors, Inc.
P.O. Box 1488
Amarillo, Texas 79105
Re: Quirt Avenue Overpass
Dear Mr. Chow:
Your letter of July 21, 1987, regarding the proposed remedial
action to seal the deck on the Quirt Avenue Overpass was
referred to HDR Infrastructure, Inc., for their recommenda-
tion regarding the advisability of this approach. HDR condi-
tionally recommended that the City accept your proposal, and
because of the increased maintenance costs associated with
the asphaltic concrete overlay, suggested that the City pur-
sue an option to mitigate the maintenance costs.
The proposal contained in your letter of July 21, 1987, a
copy of which is attached, was presented to the City Council
during their meeting on August 13, 1987. Council accepted
your proposal with two additional qualifications:
1. Heavy Highway Constructors, Inc., must pay the
City of Lubbock a lump sum amount of $40,000 to
cover the costs of maintaining the asphaltic
concrete overlay for the next twenty years. This
amount is the estimated differential'in costs
between maintaining a portland cement concrete
surface and an asphaltic concrete surface during
the expected life of the concrete bridge deck.
2. The work needed to accomplish your proposal must
be completed by October 1, 1987.
E X H 161 T it
co
LO O�pl
slon. Please advise us of your response- tt is pr p sal
formulated by the City Council.
Sincerely,
Larry J. CunninggZaa
Citv ManaaAr
HEAVY HIGHWAY CONSTRUCTORS, INC.
P.O. BOX 1 488—AMARILLO.TEXAS79105-806/374-0932
August 24, 1987
VIA: CERTIFIED MAIL
Mr. Larry J. Cunningham
City Manager
City of Lubbock
P. O. Box 2000
Lubbock, TX 79457
RE: Quirt Avenue Overpass
Dear Mr. Cunningham:
Thank you for your August 17 letter about the Lubbock City Council's
acceptance of our proposed remedial action and two conditions to
that acceptance.
We agree to the two additional conditions set out in your August 17
letter.
When this remedial procedure is complete, we will expect the balance
owing to us to be paid at that time less the $40,000. We would like
written acceptance and release by the City of Lubbock of the remedial
work. I think your legal department could prepare that acceptance
and release more efficiently.
Yours very truly,
HEA V GHWAY ONSTRUCTORS, INC.
F. C. Chow, President
FCC:sv
cc: Mr. Larry V. Hoffman, P.E. - City Engineer
EXHIBIT "D"
Equal Opportunity Employer
Mr. F.C. Chow
President
Heavy Highway Constructors, Inc.
P.O. Box 1488
Amarillo, TX 79105
Re: Quirt Avenue Overpass
Dear Mr. Chow:
August 28, 1987
Please find attached copies of your letter dated July 21, 1987, containing
your proposed remedy for the cracked bridge deck; Mr. Cunningham's letter
of August 17, 1987, setting forth the City -Council's counter proposal; and,
your letter of August 24, 1987, accepting the City Council's counter proposal.
It is the City's understanding that your offer to guarantee the overlay for
an additional two years is.above and beyond the one year warranty contained
in the original contract and therefore, will result in a three year warranty
commencing on the date of formal acceptance of the project by the City Council.
HDR/PSC will serve as the City's project representative during the repair work.
Please notify Mr. Will Hagood of your proposed schedule and methodology for
completing the work. .The work must be completed by October 1, 1987, and traffic
must be maintained over the bridge during the construction of the repairs.
When the repairs are completed, HDR/PSC will recommend to the City that the
entire project including the repairs be accepted by the City. The City staff
will then place an item on the next available City Council Agenda for
acceptance of the project by the Council. Assuming that the City Council
accepts the project, the City will release to you the retainage minus $40,000.00
to be used by the City for future maintenance of the asphalt overlay.
The City certainly appreciates your willingness to work with us to remedy the
problem of the cracked deck on the bridge. A timely completion of the repairs
will certainly benefit all involved parties.
LVH: Ig
attachments-
xc: Jim Bertram, Assistant City Manager
John Ross, City Attorney
Will Hagood, HDR Infrastructure
Ver truly a
Larry V� Ho
City Engineer
EXH IBIT 11 E 11
CITY OF LUBBOCK, TEXAS
QUIRT AVENUE OVERPASS
ESTIMATE CERTIFICATE
Contractor: Heavy Highway Constructors, Inc.
P. 0. Box 1488
Amarillo, Texas 79105
Contract Date: October 25, 1984
Estimate No. 19 (FINAL)
Date: September 30, ,1987
Completion Date: May 1, 1986'
Time Used: 949 Days
y of Time Used: 100%
Complete: 100%
For Period: July 1, 1986 to September 29, 1987
ANALYSIS OF WORK PERFORMED TO DATE
Total Value of Work Performed to Date . . . . . . . . . . . . . . .
Add: Materials Stored at Close of Period . . . . . . . . . . . . .
Net Amount Earned on Contract to Date . . . . . . . . . . . . . . .
$ 2,976,504.80
S
$ 2,976,504.80
Less: Amount Retained $
Other . . . . . $ 40,000.00 (Future Maintenance)
Total Due to Date . . . . . . . . . . . . . $ 2,936,504.80
Less Previous Payments:
Estimate
No.
Estimate
No.
Estimate
No.
1 $
59,941.97
7
$
151,596.69
13
$_
15,448.86
2 $
147,903.53
8
$
284,639.04
14
$
236,207.41
3 $
133,397.45
9
$
62,541.58
15
$_217,485.25
4 $360,608.95
10
$
21,401.00
16
$
104,266.04
5 $325,172.31
11
$
259,004.14
17
$
12,028.12
6 $_314,796.23
12
$_121,240.99
18
$
24,377.87
AMOUNT DUE THIS PAYMENT . . . . . . . . . .
Original Contract Amount $ 2,886,434.50
Change Orders $ 90,070.30
Adjusted Contract Amount $ 2,976,504.80
Balance After This Payment $ -0-
$ 2,852,057.43
$ 84,447.37
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Prepared and Accepted By: HEAVY S RUCTORS, INC., Contractors
BY President , 45r 3 ,1987
Recommended for Payment: PARKHILL, SMITH & COOPER, INC., Consulting Engineers:
By ,Proj. Engineer, September 30 ,1987
HDR I RASTRUCTURE, IN ., Consulting Engineers
By 'Al,
r• ��� ,1987
Approved for Payment:
CITY OF LUBBOCK, 'TEXAS, Owner
By �. zo ,
�, __ 1987
0
� O
O
O
O
O p
e
.-r
coO
w
00
!C1 O
Go
�O
�
P"4
O
r\
0
0
0
> 'd
.-r
aur
.1
b G
N cd
w
waw
co
o
a cn
H
O
O
O
p
O
O
O
O
N
ra
O
omu
N
Q
H
O
n
Ln
O
LM
N
�T
to
M
co
u
41+4
11
O
O
v-4
O
M
t'n
cnv
w
v
4.4
e1S
oc
u
A
O>%
-=
W
p E+
- H
O4JC
O
O
a
O
11
y
00
U
U 3
N C
V1 ed
U
Go.-�
U y rl
H
aJ
0
1
bo
C�
C!
"4
d
C H
04
CLO
14
4-4
Li
00 `Jo
60
$4
L
M
,7
tii f
gn
1-4
ai >
-P4
>
HI
M
.t
u1
w od
4J00
r1
`�o
ig
-H
m
,-1 i+
W
vi
a
M
00
V4 W
Y1 O W
o
u1
p
WAj
W y
W C
X W
W .46
>C p
w +1
!C
W b
m
W b
iC U
U
O
c0
Ln
W �
m a
m tv
to
�
O
O
f\
f\
> C7
O
>
O
> FO
O
> 4+
>cd
O
o
44
O
as
.4
>
q
0 ,�L
y y
t/}
O Gl
O N
d
6
�-/
p
O
cu
<H
U
o4Q1' �
O
N
N 9
a 3
rOi
a a
r01
is r-4 tO C
M
u01
O
a°� a
c° 3 on
w3°
cn
aL ►�-�
v
i
�
�
6
0
m z U
N
H
41
Z
u1
�O
OHH
O
V4
W
w
[�4 o &4cn
�-c ce w
U
N
O
O
0
� O
O
O
O
O p
N N
w
.-r
coO
w
00
!C1 O
Go
�O
�
P"4
O
r\
w
N
> 'd
.-r
O
O
u1
O
O
N
p
P%
c0
�7
�O
�
P"4
O
r\
w
N
> 'd
.-r
aur
.1
b G
N cd
t+
co
V
a cn
H
O
O
O
O
O
O
O
O
N
C
O
omu
w
^
O
LM
N
�T
CO
M
co
u
41+4
M
M
t'n
cnv
w
v
4.4
e1S
oc
u
A
O>%
O
O
u1
O
O
O
p
Ln
^
O
ppp
N
P"4
en
r\
N
N
> 'd
.-r
aur
O
O
u1
.a
N
M
Ln
^
O
ppp
N
P"4
en
r\
N
N
> 'd
w
aur
A
b G
N cd
t+
co
.a
O C7
1'
u
sw
N
"A
e0
'0
—
i+
> 'd
aur
A
b G
N cd
t+
co
V
a cn
H
y
x
0
omu
w
d ctl
t'v
O u
n4)u
a
u
41+4
u 4)
cnv
w
v
4.4
e1S
oc
u
A
O>%
-=
8 x
p E+
- H
O4JC
O
O
O
11
y
00
U
U 3
N C
V1 ed
U
Go.-�
U y rl
H
aJ
0
1
bo
C�
C!
"4
d
C H
04
CLO
14
4-4
Li
00 `Jo
60
$4
v
tii f
w
ru
ai >
-P4
>
HI
M
w od
4J00
r
`�o
ig
-H
m
,-1 i+
W
vi
a
M
00
V4 W
Y1 O W
A
WAj
W y
W C
X W
W .46
>C p
w +1
!C
W b
m
W b
iC U
U
W �
m a
m tv
to
�
z
O
> 13
O
> C7
O
>
O
> FO
O
> 4+
>cd
O
o
44
O
as
>
q
0 ,�L
y y
N
O Gl
O N
d
6
�-/
p
O
cu
ow
e>0
°a3 a
o4Q1' �
c,.rD
oa 8 3
G
od co
N 9
a 3
rOi
a a
r01
is r-4 tO C
M
a°� a
c° 3 on
w3°
cn
co
�
6
41
Z
u1
�O
f\
CD
Qti
p
W
r•+ Q
O
O
O
O
O
O
O
$4 w
ra w
aa)
o
0
0•
0
0
0
0
O
0
O
0
O
0
O
0
O
0
cti
en
c
d
i✓
ac�
a
d
e�
u
,
L ,°�
ai r"441
U
A
,,
b
►"r
fU
Ol fd
M
4
tti
L
Ncc
0
rA
a
0 O
c
A.
E
1v;
a3i
Ln
N
LFJ
n
0
O
N
Ln
cz
ar
A
4.JO
3
t -r
H
O
O
r�
co
O
Ln
00
a
Q
O
Ln
O
�
n
�
O
a
w
O
�D
x
w
O
Qq
A
IT
co
r w
.G
Ln
LM
N
ON
u •G
co
en
,-r
u
..f
m
.,1
b
44
crs
V4
tr cd cc
°�
cc a
..,-r
d
,�
41
02
eaa c�
> cc
-�
u
� 130
-4 ago 0)
�
u
'-,
ed
x
a
b
w r
d
'�
•'�
.�
u
ra
N A
Qi
u oD
u
u
u
y
Cf)
\�
N
f+
z
41
L
ani
cn
cc 4
uva
cti u
uVa
°`00
�
co
W
W $4
Cu
Li
n
O�
N
1n
N
ami
r,
.Oo
f�
1
N
-4%
f�
a
a
u
%0
u'1
.a
v
rdi0
vz
s
v
v
O
O
O
O
d
O
O
d
O
O
S
•
Ln
O
O
Ai
ul
ni
O
O
M
O
n
M
G
N
co
O
{M
•r
w
w
w
^
�'
•1
ra
14
t
cn En
z d
°Ln
°
Ln
rr"
voi
�
0
0
ul
%D
Ln
w H
►�
V
O
.�
N
N
to
Ln
^
O H
U
to
N
N
"��
N
r-4
owe
0.'
a
z
z
0-4
Aj
of
o
c
>:
>:
>:
rs
H
o
cn
rn
rn
cn
cn
w
rn
.a
cn
cn
rn
o�
►-r w
V4
O
�
0
0
L
41
�
coO
w
M
w
�C
w
vT
�
0
0
L
o
w
w
w
to
rl
r w
0
$4 w
ra w
d o
d
c�
cti
en
c
d
i✓
ac�
e�
u
,
L ,°�
ai r"441
U
,,
b
►"r
fU
Ol fd
4
tti
L
Ncc
rA
a
0 O
c
A.
cn
°J
a3i
r�
a
awi G
cz
4.JO
3
t -r
H
0a d
8 a 8
d b
d
y
W
u
V4`6
a
w
ca
x
w
G�7
C�h
A
•v
rto
w
w
...
a i
v
d>
u •G
as
1
,-r
u
..f
m
.,1
b
44
crs
V4
tr cd cc
°�
cc a
..,-r
d
,�
41
02
eaa c�
> cc
-�
u
� 130
-4 ago 0)
�
u
'-,
ed
x
fu
b
w r
d
'�
•'�
.�
u
ra
N A
Qi
u oD
u
u
u
y
Cf)
\�
N
f+
U�
O
a
Z.
cc 4
uva
cti u
uVa
.-�w
U
�
C_
W
W $4
Cu
v
w
u
to
u
C.
w
-ry
a
a
u
%0
cncai
.a
v
rdi0
vz
s
v
v
w a
o
0
0
0
0
0
0
0
0
0
0
0
A
L
GOD
p
C
O
M
n
N
O
Ln O
O
O
Go
w
w
w
w
w
O
GD
O
.7
M
N
.Y
W
N
W
O
w
O
w
co
w
GO
w
M
w
w
w
N
�
N
M
a
u
+�
M
O
O
O
1�
M
CT1
Ln
.7
C11
Ln
.t
C N
N
X00
M
G0D
^
O
N
in
M
ra
O
O
O
O
p
O
O
O
u
7
O
O
O
M
O
O
O
O
O
GD
w
p
w
O
w
GO
w
O
w
�
GD
N
O
d
M
N
.Ot
GD
N
W
tf1
N
O
w
GD
w
GD
w
w
W
w
w
N
`*4
,Q
1,
N
W%
E'a
O
O
O
O
O
O
O
O
O
O
O
O
O
LM
u
N
O
O
O
O
L
O
O
O
O
O
U
fes+
'"r
•�-�
«�
O
M
M
M
z
H
cti
Ln
�
L
w
N
SOD
M
GD
uO1
^
Ln
O
N
IT
CT
W
RS
N
`l
Ln
.-r
�
N
GJ
y�
C:
41
w
41
w
w
u
N
6
ti
.�
x
41
G7
y
p
U
41
1.4
C
'�
'�
�
•cc
d
u
0
w
rdl
,4i
V
4!
'0
0
V
a,
r -I
u
u
G0i
w
w
4.4
0
a7
0
«�
0
�+
8
A
A
A
C
U
N
^
GS
-L i
w
>
to
f+
�,
U
,�-�
V]
�
H
A
..
44
C:
"4
ed
04
GJ
u
p
�
u
q
d
,�
�
Rte'
ami
q
Q,
a
13
9
8
U
W
W
D
v
W'
m
m
Waj
L
A
u
14
y
A
'd
A"0
A
b
M
to
u
N
w
y
47
V
49A
eg04
o
t
0
�
n
U
A
W
. 0 1
W
Ln
DW
(�j
(�j
cs
a
a
ii
U
04
G
a�q
H Z
N
N
N
N
N
N
N
M
M
M
M
tN^
to O
H � U
W N
owa
to 2 U
a w
wdE
H�tn
H cr w
U
a
z
N
w
v
CA
a
u
cc
41
w
94
I+
d
A
Q
&M
Ln
vQi
O
0
0
0
0
0
0
0
0
0
0
c
^
Q
(7%
n
w
O
en
O
co
"4
N
o+
O
�D
rX4
N
M
'4
14
ul
co
N
N
O
N
N
04
N
.--I
u1
N
OM1
i
Ln
IT
en
O
O
O
O
O
O
O
O
O
O
O
O
7
O
O
O
Ln
M
Ln
co
w
own
N
nO
�OGo
O
�OM
Dw
N1
M•
'O
O
w
u1
00
r
H
O
u�
O
In
n
C
O O
O
O
O
O
O
O
u
N
M
O
N
O
O
p
N
%CO
a
O
u
$4cn
ccn
Z
H
Q
c
r�
w
>+
u
rN
u
_
o
a
Co
to
w
w
w
a
w
w
w
w
.a
.a
.
w4
%0
0o
p
N
O
N
N
Qul
N
.1
u1
N
O
o
cc
Q
rl
a
w
W
Jd
cc
a
41
r -
O
a
W
u
oa
aCd
W
10
N
�
J
LJ
O
0
a
.0
lc
p
.-4
$4
gow
3
O
a
O
41
Ad
w
a
U
LW
N
to
t00
d N
Q
u
x
a
O
YI
W
p
is
a
O
N
pp
0
O
r -I
1 r
L
>
41
Cd
tv
a cc
0
`v
C
a
u
3
ooa�.+
cc
cc
�
w
u
a
«�
>
.->i
N
•.�
UAi
.-1 v
to
0
t�
>
u
W
w
_
H
Qj
41
a
r>i
cc
cmc
to
L
a
41
a
00
�
f4
rl
►-I
u
u
a
19
8
cc `
a
L
-r4
O
LJ
a
to
ctS
'C
G'
4-1
G'.
b "J
N
A
a
a
a
m
ai
u
41
a
i.+
0
`v
u E3
a
to
to
{+
u
►+
u
M1
A
a
A
m
u
cc
C7
oq
0
cc
A
a
O
a
cc W E-4
- ec
r -4°r+°
p
0
q
-
�,
�°
-
c°�
a
ccn
to
t7 E°'+ d
ci
ci
�o
a
N
M
e i
rOi
r�1
.OT
. 7
7
s
.MT
.fit
y O
En
H
� V
�GO►�i
O w
= w U
44 6 E-
o o
E- M) to
U
z
W
v
d\
z°
d
L
tv
Is
tii
41
W
w
oeenn
Ln
►+
a
o
0
0
0
0
0
0
0
—
o
w
r1
O�
w
Oti
w
N
N
tNl�
N
c
Q
0
0
0
0
0
0
0
o
O
H
o
co
Q
O
^O
Ln
Ln\1
N
N
O
Ln
.Q7
VO1
.moi
en
e70
M
O
C'
M
0
CJ
w
w
G%
W
i3+
N
3
1
C
eft
N
"i
ONco
•-I
M
�1
�7
L
w�l
N
N
is
w
c
O
O
O
O
O
O
O
O
1f1
vOi
Lf
O
O
tf1
O
N
M
.t
efQ1
.moi
NT
�O
�O
co
w
N
H
O
O
O
O
O
O
O
L
41
O
M
O
A
,-+
�
0
+4
M
N
000
N
N
V
�
2
H
U
u
V
VW
V
V
V
O
a
w
w
y
�.
cn
w
w
w
v,
+j
m
"4
M
Aj
r.►
to
tf1
4)
c
u
C
y
W
�O
to
W
�
O
oAj
to
x
Nrl
1J
'd
CC
�
U
ca
µ+
O
en
y
�
U
w
H
H
`�
V4
?C
00
cn
U
0
E,
�
Aa
a�
f
M
41
w
N
rl
O
x
w
W
(j
W
W
Cs7 a
�
IJ
~-Li
(~
tv
�'
w
w
0
H U
d
d
C
C
O
H
m
H
H
N
U
P4
L
U
47
"a
'O
00
6-4
)-4Q
u
u
v
ani
"4
0
u
q
u
Ai
us
w
u
0
,4
+H
-444
PC
d
u
Q
U
Pi
F
00
00
O
.0
U
M
kn
Ln
M
eft
Ln
Ln
rl
d
�O
oeenn
Ln
1
aoo
coer
U4
.T
.4
�T Ln
O
'�
M .4
Le)
w
r1
O�
w
Oti
w
N
N
tNl�
N
HDR Infrastructure, Inc. Suite 125 Telephone Water Resources
A Centerra Company 12700 Hillcrest Road 214 980-0001 Wastewater
Dallas, Texas Hazardous Waste
75230-2096 Bridges
Transportation
Industrial
October 8, 1987
Mr. Larry J. Cunningham
City Managgr-*'-
City ofLubbock
P.O. ox 2000
"lubbock, Texas 79457
Re: Quirt Avenue Overpass
Final Project Review and Acceptance
Dear Mr. Cunningham:
A final on-site review of the asphaltic concrete overlay protec-
V✓100 tion system, recently applied to the Quirt Avenue bridge deck and
✓/ roadway approaches, was conducted on September 29, 1987. Members
of the final review team included representatives as follows:
City of Lubbock (City)
Mr. Larry Hoffman
Mr. Don Jennings
Mr. Larry Hertel
Mr. Percy Boren
HDR Infrastructure, Inc. (HDR)
Mr. Will Hagood
Parkhill, Smith & Cooper, Inc. (PSC)
Mr. Terry Bilderback
Mr. Royce Gooch
Heavy Highway Constructors, Inc. (Contractor)
Mr. F.C. Chow
Kerr Construction Company
Mr. Ken Hancock
I'riur In this rc-view tv.-em walkl.nl; ;tcrrrta Ule bridt;t: L(i r)h:svrvv Iliv
completed work, Mr. Royce Gooch briefed the team and answered
questions with regard to the latex asphalt overlay system uti-
lized and the contractor's installation methods observed by
representatives of PSC. PSC's on-site observatiogs are outlined
as follows:
Mr. Larry J. Cunningham
October 8, 1987
Page 2
(1) All bridge deck construction joints (nine locations)
were sawed and sealed with a nitrile rubber base
permanent highway joint sealing compound.
(2) The existing bridge deck expansion joints were modified
to receive the overlay. All joints were extended above
the concrete wearing surface approximately two (2)
inches by welding 2" x 2" x 1/4" steel angle to the
in-place metal armor joint extrusions.
(3) One-half of the deck width and concrete approach road-
way width was broom cleaned, followed by an application
of latex modified AC -5 asphalt, applied at at rate of
0.25 gallons per square yard of deck area.
(4) The first surface course, consisting of Grade 4 aggre-
gate suppled by R.E. Janes Gravel Co., was then applied
at a rate of approximately one (1) cubic yard per 100
square yards of deck area and rolled with a pneumatic
roller.
(5) A second application of latex modified AC -5 asphalt was
then applied to the first surface.course at a rate of
0.30 gallons per square yard of deck area.
(6) A second surface course of aggregate, Grade 4 supplied
by R.E. Janes Gravel Co., was applied at a rate of one
(1) cubic yard per 100 square yards of deck arga and
rolled with a pneumatic roller.
(7) Steps 3 through 6 were repeated for the remaining half
of the bridge deck and approach roadways.
(8) A tack coat of RC -250 asphalt was applied to the armor
joint extensions and the side curbs of the roadway.
(9) .A one and one-half inch (1-1/211) compacted thickness hot
mix asphaltic concrete (HMAC) overlay was then applied
over the second surface course. Note: HMAC comprised
of course and intermediate aggregates, supplied from.,the
Brownwood-Whites Mines. Five (5) percent AC -10 asphalt
with latex additive used as binder.
Mr. Larry J. Cunningham
October 8, 1987
Page 3
(10) After placement of the 1-1/2 inch HMAC wearing surface,
a coat of emulsified asphalt was applied to the
completed surfacing.
Based upon on-site observations made by representatives of PSC,
all work performed by Heavy Highway Constructors, Inc. and Kerr
Construction Company, as related to the overlay installation,
conformed with generally accepted construction practices for
application of double surface treatments and hot mix asphaltic
concrete overlays. In accordance with your letter of August 17,
1987 to Mr. F.C. Chow, all overlay operations were completed
prior to the City's deadline of October 1, 1987.
Based upon PSC's observations during installation of the overlay
system and our final review of'the completed work, we recommend
that the City of Lubbock accept the total Quirt Avenue Overpass
project, incluing the asphaltic overlay system now in place.
This acceptance is contingent upon Heavy Highway Constructors,
Inc. extending the warranty of the HMAC overlay system an addi-
tional two (2) years beyond the one year total project warranty
stipulated in the construction agreement between the City of
Lubbock and Heavy Highway Constructors, Inc. A three (3) year
warranty of the overlay system and a one (1) year warranty of all
other construction associated with this project would commence on
the date of final acceptance of the project by the City of
Lubbock.
In accordance with your agreement with the Contractor, we have
prepared Pay Estimate No. 19 (Final), as attached, noting the net
amount of $2,976,504.80 earned to date by the Contractor, less
$40,000 to cover the future costs of maintaining the asphaltic
concrete overlay system. The final amount due Heavy Highway
Constructors, Inc. is $84,447.37.
We sincerely consider it an honor to have the privilege of
serving as your engineering consultant over the past five years
and look forward to continuing to provide our services in the
future.
Mr. Larry J. Cunningham
October 8, 1987
Page 4
Should you have any questions with regard to the above infor—
mation, our recommendations, or the enclosed final construction
pay estimate, please do not hesitate to contact us.
Very truly yours,
HDR INFRASTRUCTURE, INC.
William B. Hagood, P.E.
Vice President
cc: Mr. Jim Bertram, Assistant City Manager
Mr. Larry Hoffman, Director of Transportation
Mr. John Ross, City Attorney
Mr. Clayton Yeager, President, PSC
Mr. Terry Bilderback, Project Manager, PSC
Mr. Bill Dowd, Assistant Vice President, HDR
Mr. Virgil Meedel, Senior Vice President, HDR
e 6OUTN
f -, wi
a. arm 1T.
Ir—Ml Pant
-IjD
s
' t. pTN —, r___� I
WELL
O I IL OL
R.
R.
I
� I t IITN
000 9a rDD tmD
I
I J
� t O
r ..
I
Jj�17TN '
1 RJ
9M
1
!MD l,_ R•
tatTLArN
MEMORIAL
GARD908
RUEL
MARTIN
ELEM.
i
alrr etrersn•
i 71,
R. IITN
—N�
Fes.