HomeMy WebLinkAboutResolution - 2625 - CO #2 To Contract - Lee Lewis General Contractor - Maintenance Building, LIA - 08/13/1987HW:js
RFSnI IITTnN
Resolytion #2625
August 13, 1987
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock BE and is hereby authorized and
directed to execute for and on behalf of the City of Lubbock Change Order
No. 2 to a Contract previously entered into by and between said City and Lee
Lewis General Contractor, for the construction of a Maintenance Building for
snow and ice removal equipment at Lubbock International Airport, attached
herewith, which shall be spread upon the minutes of the Council and as
spread upon the minutes of this Council shall constitute and be a part of
this Resolution as if fully copied herein in detail.
Passed by the City Council this l_lt.h day of Augimt , 1987.
-B. C. MCMINN, MAYOR
ATTEST:
nette Boyd, City Secretary
APPROVED AS TO CONTENT:
Mar1vin Coffee, Di for of Aviation
APPROVED AS TO FORM:
arold Wil rd, Assistant City
Attorney
CHANGE
...
Distribution to:
ORDER
OWNER
❑
ARCHITECT
AIA DOCUMENT G701
CONTRACTOR
FIELD
❑
OTHER
❑
PROJECT: Maintenance Building for Snow and
CHANGE ORDER NUMBER: 2
(name, address)Ice Removal Equipment; Lubbock
International Airport, Lubbock,
TexasINITIATION DATE: April 15, 1987
TO (Contractor):
��----
ILee
ARCHITECT'S PROJECT NO: 8750
Lewis
3eneral Contractor, Inc.
1
CONTRACT FOR:The construction of the Main -
P.O. Box
Lubbock,
65197
Texas 79464
tenance Building for Snow and Ice Removal
Equipment, Lubbock International Ai ppor
AIP Project No.3-�8-0138-
CONTRACT DATE:
.J
June 3, 1987
You are directed to make the following changes in this Contract:
See Attached List, Items.l through 8
TOTAL CHANGE IN CONTRACT SUM (ADD) ..................$ 259706.00
TOTAL CHANGE IN CONTRACT TIME
DUE ITEMS 1 THROUGH 8 ............................. NONE
TOTAL CHANGE IN CONTRACT TIME
DUETO WEATHER DELAYS..... ....................... 109 DAYS
Approved as to Content: Approved as to Form:
JL
Marvin Coff , Director of Aviation Harold Willard, Asst. City Attorney
Not valid until signed by both the Owner and Architect.
Signature of the• Contractor indicates his agreement herewith, including any adjustment in the Contract Surn or Contracl Time.
The original (Contract Sum) (Gd0wcXXo&kkxkXxX:)fxatcQkwas ........................... $ 2,341,150.00
Net change by previously authorized Change Orders ...................... • ............ $ 4,387.00
The (Contract Sum) (0Cxaaxtlt=ot%Aa0mmxX3mX prior to this Change Order was ......... $ 2,345,537.00
The (Contract Sum) will be (increased) ( N* (XP1QdXX:KQ p
by this Change Order......................................................... $ 25,706.00
The new (Contract Sum) including this Change Order will.be ... $ 2, 371, 243.00
The Contract Time will be (increased) (&xxa.xm* (Lmzx t=ab by ( 109 ) Days.
The Date of Substantial Completion as of the dace of this Change Order therefore is September 20, 1987
Parkhill, Smith & Cooper, Inc. Lee Lewis General Contractor
ARCHITECT) TRAi'TUR
4ai n Avenue R. .�. Sox 65197
Address Address
, Texas 79412
13Y
DATE
DATE
AIA DOCUMENT G701 ' • CHANGE ORDER • APRIL 19711 EDITION AIA110 1 n
THE AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE., N.W., WASHINGTON, D.C.
Authorized:
Citv of Lubbock
OR
P.O. Box 2000
Address
Lubbock, Texas 79457
a-
Rv�►
-Mayor, b. C. McMinn"
DATE rIR-1R-R7_ -
Boyd, City Secretary
f
CHANGE ORDER NO. 2
Maintenance Buildine for Snow and Ice Removal Equipment
LUBBOCK INTERNATIONAL AIRPORT
AIP Proiect No. 3-48-0138-06
I.
Additional earthwork at west apron approach due to conflict with
existing water line (ADD) ....................................... ...,.$
CHANGE ORDER NO. 2
Maintenance Buildine for Snow and Ice Removal Equipment
LUBBOCK INTERNATIONAL AIRPORT
AIP Proiect No. 3-48-0138-06
I.
Additional earthwork at west apron approach due to conflict with
existing water line (ADD) ....................................... ...,.$
3,777.00
2.
Relocate underground fuel tanks to east edge of apron (ADD) ............
$
101100.00
3.
Add electrical for power change to fuel pumps (ADD) ....................$
3,220.00
4.
Extended 2-4" telephone conduits from building to west property
dine (ADD) ... .........................................................$
29875.00
5.
Add -V thick roof insulation on north portion of roof to cover
boltconnections (ADD) ..................................................$
7,676.00
6.
Add floor drain at air washer and extend water line to hot water
washer (ADD)............................................................$
1,262.00
7.
Add twelve (12) overflow scuppers in west building fascia for
roof drainage (ADD) .....................................................$
4,301.00
8.
Delete overhead secondary power service and provide underground
primary and pad mounted transfdrmer service (by LP&L) (DELETE) .........
$ (79505.00)
TOTAL (ADD) ................$