RESOLUTION
Resolution #2621
August 13, 1987
Agenda Item #17
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock BE and is hereby authorized and
directed to execute for and on behalf of the City of Lubbock a Change Order
No. 1 adding paving quantities to existing contract, Project Number
31115105, for paving improvements between said City and Kerr Construction
Company, attached herewith, which shall be spread upon the minutes of the
Council and as spread upon the minutes of this Council shall constitute and
be a part of this Resolution as if fully copied herein in detail.
Passed by the City Council this _ 13th day of August , 1987.
t
B.C. McM NN, MAYOR
ATTEST:
Ranette Wyd, City.Secretary
APPROVED AS TO CONTENT;
Larry 110TYFn,
Transport ion
APPROVED AS TO FORM:
Orth
Full ingim, Assist
i Attorney Pt
Res. #2621
TO: Kerr Construction Company
P.O. Box 888
Lubbock, Texas 79408
Gentlemen: CHANGE ORDER NO. 1 TO PROJECT NUMBER 31115105
WHEREAS, it is desirable to make changes in the plans and
specifications for this project, being namely Change Order No. 1.
Original Amount of Contract $286,858.50
Increased by Change Order No. 1 47,556.60
Total Amount of Contract $334,415.10
Construction completion date is extended to November 1,
1987.
THIS AGREEMENT WITNESSETH: In consideration of the mutual
advantages gained, the Owner and the Contractor agree to the
change shown herein and in the revised plans, the Owner agrees to
pay the Contractor the amount of increase in cash. The Con-
tractor agrees to proceed with construction and to adhere to
applicable specifications, under the direction of the Engineer.
Furthermore, the parties agree that the original contract between
the Owner and the Contractor shall be modified to the extent
herein indicated, including one (1) attachment.
IN WITNESS WHEREOF, the Owner and the Contractor have hereto
set their hands this 13th day of August, 1987.
KERR CONSTRUCTION COMPANY
(Contractor)
BY • � �_ A TITLE: ;955.
Ken Hancock
Kerr Construction Company
�y
a J�
BY : c , r/c-ers t�
.C. Mc INN
MAYOR
CITY OF LUBBOCK
(Owner)
ATTES .
Rane a Boyd
City Secretary
RECOMMENDED FOR APPROVAL
Jim B tanram
Ass' t City Manager
rry FWf finan
Direc of Transportation
zoX,
Bob Cass
Deputy City Manager
Sandy O tr
Community Development
Administrator
LAKE 6 & ATZLAN PARK
PAVING IMPROVEMENTS
PROJECT NUMBER 31115105
CHANGE ORDER NO. 1
To pave Colgate Street from Niter Avenue to Olive Avenue and Baylor
Street from Niter Avenue.to Mulberry Avenue.
Unit
Construction uantit Price Amount
1. Paving -6" of caliche base 5,370 S.Y. $ 6.30 $ 33,831.00
& 1 1/2" hot mix surface
2. Curb and Gutter 2,451 L.F. $ 5.60 $ 13,725.60
TOTAL OF CHANGE ORDER NO. 1
$ 47,556.60