Resolution #2609
July 9, 1987
Agenda Item #16
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock BE and is hereby authorized and
directed to execute for and on behalf of the City of Lubbock a Change Order
No. 3 to a contract previously entered into by and between said City and
Kerr Construction Company for work on the Southwest General Aviation Area
Expansion at Lubbock International Airport, attached herewith, which shall
be spread upon the minutes of the Council and as spread upon the minutes of
this Council shall constitute and be a part of this Resolution as if fully
copied herein in detail.
Passed by the City Council this 9th day of July , 1987.
B.C. McMINN, MAYOR
ATTEST:
Ranette�Boyd, City Secretary
APPROVED AS TO CONTENT:
Marvin Coffee, Di for of Aviation
APPROVED AS TO FORM:
&-210 a old Willard, Assistant City Attorney
K
CHANGE ORDER NO. 3
Lubbock International Airport
City of Lubbock, Texas
Southwest General Aviation Area Expansion
AIP Project Nos. 3-48-0138-04 & 05
July 1985
To: Kerr Construction Company
P.O. Box 888
Lubbock, Texas 79408
General description of work included in contract:
The construction or strengthening of approximately 42,500 square yards
of flexible pavement on taxiways and construction of approximately 30,700
square yards of flexible pavement on roadways, reconstruction of existing
apron pavement, removal of existing pavement, construction of approximately
17,600 linear feet of curb and gutter, construction of drainage structures,
excavation work, installation of taxiway edge lighting, installation of
water and sewer lines, marking of taxiways and roads, installation of
security fencing, and other related items of work.
Original Amount of Contract .$3,157,000.48
Change Order No. 1 . . . . . . . . . . . .(Deduct) [113,370.82]
Change Order No. 2 . . . . . . . . . . . . (Add) 35,997.00
Change Order No. 3 . . . . . . . . . . . . 0.00
Adjusted Contract Price $3,079,626.66
Original Construction Time . . . . . . . . .
. 275
Calendar
Days
Change Order No. 1 . . . . . . . . . . . .
0
Calendar
Days
Change Order No. 2 . . . . . . . . . . . . .
. 31
Calendar
Days
Change Order No. 3 . . . . . . . . . . . . .
. 161
Calendar
Days
Adjusted Construction Time 467 Calendar Days
WHEREAS, it is desirable to make certain changes in the work included
under this project:
AND WHEREAS, during the construction time provided by the contract for
the project, work was delayed due to weather conditions, such as snow, rain
and subfreezing temperatures, during critical periods of construction, the
Owner and Contractor agree that the time allowed for the completion of the
project shall be extended 192 calendar days, from 275 calendar days to 467
calendar days. The revised completion date is January 30, 1987.
CHANGE ORDER 140. 3
Page 1 of 2
THIS AGREEMENT WITNESSETH: In consideration of the mutual advantage
gained, the Owner and the Contractor agree to the changes indicated above
and further agree that the contract shall be adjusted as shown above.
The aforementioned changes, and work affected thereby, are subject to
all contract stipulations and covenants.
IN WITNESS WHEREOF, the Owner and the Contractor have hereto set their
hands this 9th day of 11111y , 1987.
RECOMMENDED: PARKHILL, SMITH & COOPER, INC., Consulting Engineers
_ Project
ByManager 1r� zl .1987
APPROVED: KERR CONSTRUCTION COMPANY, Contractor
By. �. �1- ,1987
APPROVED: CITY OF LUBBOCK, TEXAS, Owner
a
By Zf Mayor , ,1987
ATTEST:
I C 4CiS=ecr�eta—ry
APPROVED AS TO CONTENT: ��
Marvin Coffee
' Director of Aviation
CHANGE ORDER NO. 3