HomeMy WebLinkAboutResolution - 2976 - Accept Paving Improvements- Kerr Construction- L1346-1433, Meadows Addition - 12/15/1988HW:js
RESOLUTION
Resolution #2976
December 15, 1988
Item #?5
RESOLUTION ACCEPTING IMPROVEMENTS ON PORTIONS OF STREETS AS LISTED
BELOW:
WHEREAS, in conformance with the paving requirement provisions of City
Ordinance 1331, the subdivider of the Meadows Addition, Lots 1346-1433, made
arrangements with Kerr Construction Company for the construction of paving
improvements on certain streets dedicated in said subdivision under the pro-
visions of said Ordinance prior to the recording of the subdivision plat of
the above-mentioned Addition including the following streets:
The South 1/2 of 96th Street from its intersection with the East prop-
erty line of Lot 729 to its intersection with a line 13 feet West of
the West property line of Slide Road and designated as New Subdivision
Sub -Unit Number 6 of Unit Number 2031.
The North 16 feet of 98th Street from its intersection with a line 3
feet West of the East property line of the Alley East of Albany Avenue
to its intersection with a line 578 feet East of the East property
line of the Alley East of Albany Avenue and designated as New Subdivi-
sion Sub -Unit Number 7 of Unit Number 2031.
WHEREAS, the construction of the above improvements on the above-
mentioned streets was performed under the supervision of the City Engineer,
and said improvements have been completed and have been inspected and found
to have been constructed in accordance with City specifications and in ac-
cordance with the provisions of City Ordinance 1331; NOW THEREFORE:
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
SECTION 1. THAT the improvements on said portions of the above-
mentioned streets BE and the same are hereby accepted and the City Engineer
BE and he is hereby authorized to release prepaid money in the amount of
$14,215.18.
SECTION 2. THAT this Resolution shall take effect and be in force
from and after its passage.
Passed by the City Council this 15th day of DpeemhPr 1988.
B. C. McMINN, MAYOR
i ,AT FST-__
anett(e Boyd, City Secretary
APPROVE AS T/O� CONTE T:
J.
Larry D. Wertel, City Engineer
APPROVED AS TO FORM:
arold Will rd, Assistantleity
Attorney
CONSOLIDATED FINAL PAVING COST
THE MEADOWS ADDITION
Lots 1346-1433
November 30, 19
Unit and
S.Y, of 1 1/2"
A.C. Paving on
S.Y. of 1 1/2' L. F. of
A.C. Paving on Curb
Sub -Unit
Location 9' of Black
b Gutter
6' of Caliche
Alley Returns Drainage
Base
Base
Channel
2031-6
S 1/2 of 96th. St. from EPL
of lot 729 to 13T W of WPL
2,926.00 1,252.00
of Slide Rd.
624.35
2031-7
tt
N�16 ft. of 98th. St, from 1
,048.89
3 W of EPL of Alley E of
597.71
3.43
Albany Ave. to 587 ft. E
Of EPL of Alley E of
Albany Ave.
TOTAL QUANTITIES 1,048.89
2,926.00
FINAL COST OF CONSTRUCTION
1,849,71
3.43 624,35
11048.89
2,926.00
S.Y. of paving on black base at $ 18.65/S.Y.
S.Y. of paving
$ 19,561.80
on caliche base at $ 6.70/S.Y.
1,849.71 L. F. of curb and gutter $
$ 19,604.20
3.49 S.Y.
at 5.90/L.F.
of concrete alley returns at $ 22.00/S.Y.
$ 10,913.29
624.35 S.Y. of concrete drainage channel at $ 22.80/S.Y
$ 75.46
„
t_14 231_18
TOTAL
$ 64,389.93
CONTRACT COST DISTRIBUTION
Unit and
Contractor previously paid
Construction this amount from
City cost from
Sub -Unit
I— Le al Jud ement
prepaid account
number 467
2031-6
$ 41,226.18 $ 27,011.00
$ 14,215.18
2031-7
$ 23,163.75 $ 23,163.75
TOTALS
4 64,389.93 $ 50,174.75
$ 140215.18