RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock BE and is hereby authorized and
directed to execute for and on behalf of the City of Lubbock a Change Order
No. 1 to a contract previously entered into by and between said City of
Lubbock and Rhode Construction Company, Inc. concerning I-27 Utility Adjust-
ments, Phase V construction and/or reconstruction in connection therewith,
attached herewith, which shall be spread upon the minutes of the Council and
as spread upon the minutes of this Council shall constitute and be a part of
this Resolution as if fully copied herein in detail.
Passed by the City Council this 10th day of August 1989.
B. C. McMINN, MAYOR
ATTEST:
, City Secret%ry
APPR01fED 0 CONTENT:
'lfo d Wats n, Chie ngineer
for ter Utilities
APPROVED AS TO FORM:
Atto
CHANGE ORDER NO. 1
City of Lubbock
I-27 Utility Adjustments
Phase V
Lubbock, Texas
July 31, 1989
TO: RHODE CONSTRUCTION COMPANY, INC.
P. 0. Box 53370
Lubbock, Texas 79453
Adjustment to Contract Amount:
Original Amount of Contract . . . . . . . . . . . . . . . . . . .$2,256,362.34
Change Order No. 1 . . . . . . . . . . . . . . . . . . . . (Add) 19.125.53
Adjusted Contract Amount . . . . . . . . . . . . . . . . . . . . .$2,275,487.87
Adjustment to Contract Time: . . . . . . . . . . . . . . . . . . . . . . None
WHEREAS, it is desirable to make certain change in the work in this project:
THIS AGREEMENT WITNESSETH: In consideration of the mutual advantage gained,
the Owner and the Contractor agree to the changes indicated below and further
agree that the amount of the contract shall be adjusted by the amount shown
above.
Add the following items:
Item Quantity
No. & Unit Descrivtion of Item and Unit Price Total Amount
1. 3 Concrete valve vaults on Line 11-W
Each located at 34th Street & East of
Ave. J, and 34th Street & Ave. G,
Furnish and install, complete in
place, each: Three thousand two
hundred six Dollars
and two Cents ($ 3.206.02 )
$ 9.618.06
2. 2 Concrete valve vaults on Lines 3-W
Each & 16-W, located at 30th Street &
Ave. G, and 24th Street & Ave. H,
Furnish and install, complete in
place, each: Two thousand seven
_hundred seventy-four Dollars
and seventy-seven Cents ($2.774.77)
$ 5.549.54
Change Order No. 1
Page 1 of 2
•
3. 1 Concrete valve vault on Lines 3-W,
Each 14-W & 16-W located at 34th Street
& Ave. G, furnish and install, com-
plete in place, each: Three thousand
nine hundred fifty seven Dollars
and ninety-three Cents ($3.957.93 )
$ 3.957.93
Total Change Order No. 1 $19,125.53
IN WITNESS THEREOF, the Owner and the Contractor have hereto set their
hand this 10th day of _ August , 1989.
RECOMMEND: PARKHILL, SMITH AND COOPER, INC., Consulting Engineers
BY-44LProject Engineer, ,� 1989
APPROVED: RHODE CONSTRUCTy,ION COMPANY,, INC., Contractor
By(�a+//o!� _f�esic�etif" , 7-3/ 1989
APPROVED: CITY
O''F/ILUBBOCK, TEXAS, Owner
By,X<• L.. At Mayor 1989
B. C. McMINN
Change Order No. 1
Page 2 of 2
UTILITY
MEMORANDUM
TO: Right of Way Section - District 5 DATE July 31, 1989
FROM: Utility Section - D-15
[XI UTILITY ADJUSTMENT U -7519
[] UTILITY JOINT USE AGREEMENT U
COMPANY City of Lubbock
COUNTY Lubbock
HIGHWAY IH 27
CSJ N0. 067-11-016 ROW NO. 9005-27-14 FEDERAL NO. 127-7(34)303
In reference to your letter dated July 24, 1989, the proposed field
change for the additional work on the above captioned project
is approved.
RRM:bfd
cc: External Audit