HomeMy WebLinkAboutResolution - 3266 - Accept Paving Improvements - Kerr Construction - Western Meadows Addition - 12/14/1989JWF:dw
RESOLUTION
Resolution # 3266
December 14, 1989
Item #11
RESOLUTION ACCEPTING IMPROVEMENTS ON A PORTION OF A STREET AS LISTED
BELOW:
WHEREAS, in conformance with the paving requirement provisions of City
Ordinance 1331, the subdivider of Western Meadows Addition, Lots 14-A, 15-A
& 19-A-1 made arrangements with Kerr Construction Company for the
construction of paving improvements on a certain street dedicated in said
subdivision under the provisions of said Ordinance prior to the recording of
the subdivision plat of the abovementioned addition including the following
street:
Alley stub removal on east side of Slide Road
between 54th and 55th streets and replace with
curb and gutter designated as N.S. 2034-18.
WHEREAS, the construction of the above improvements on the
abovementioned street was performed under the supervision of the City
Engineer, and said improvements have been completed and have been inspected
and found to have been constructed in accordance with City specifications
and in accordance with the provisions of City Ordinance 1331; NOW THEREFORE:
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
SECTION 1. THAT the improvements on said portions of the
abovementioned street be and the same are hereby accepted and the City
Engineer be and he is hereby authorized to release escrow money in the
amount of $695.00.
SECTION 2. THAT this Resolution shall take effect and be in force
from and after its passage.
Passed by the City Council this 14th day of December 1989.
B. C. McM- I`1N , MAYOR
_
ST,. /----�
Ranptte Boyd, City Secfetak-y
=`APPROV AS TO CONTENT:
A"o
Ctiarry Hertel, ity Engineer
APPROVE AVn�
STO FORM:
J. W&yth Fullingim, Assistan
Cit ttorney
WESTERN MEADOWS ADDITION
Lots 14-A, 15-A, & 19-A-1
December,. 14, 1989
QUANTITIES
Unit &
Sub -Unit Location
2034-18 Alley stub removal on east side of Slide Rd. between 54th.
and 55th. Streets and replace with curb and gutter
22.42 S.Y. Concrete alley stub removal and disposal
35.42 L.F. Curb and Gutter removal and disposal
34.001L.F. Curb and Gutter construction
COST DISTRIBUTION
Contract Developer City Escrow
Cost Cost _ Account
$ 695.00 $ 695.00
$ 695.00 *
* Placed in City escrow account by developer in lieu of bank letter and
to be returned to developer subsequent to acceptance .by City Council.
CONSTRUCTION IS LUMP SUM CONTRACT WITH KERR CONSTRUCTION COMPANY FOR
$ 695.00.