HomeMy WebLinkAboutResolution - 3341 - Accept Improvements - Kerr Construction - Project #9486, Kingsgate Park - 04/12/1990IJWF: js
Resolution # 3341
April 1.2, 1990
Item #16
RESOLUTION
A RESOLUTION ACCEPTING DRAINAGE AND STREET IMPROVEMENTS AS LISTED BELOW:
WHEREAS, the City of Lubbock heretofore entered into a Contract with
Kerr Construction Company for the making of drainage and street improvements
in said City including among others the following:
Kingsgate Drainage and Street improvements.
WHEREAS, the construction of the above improvements was performed
under the supervision of the City Engineer, and said improvements have been
completed and have been inspected and found to have been constructed in accor-
dance with the terms of said Contract, Project No. 9486; NOW THEREFORE:
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
SECTION 1. THAT the improvements above-mentioned BE and the same are
hereby accepted and the City Engineer BE and he is hereby authorized to direct
the final payment to the Contractor in the amount of $5,923.02.
SECTION 2. THAT this Resolution shall take effect and be in force from
and after its passage.
Passed by the City Council this
ATTEST:
e uoya, city 5ecrina
APPROVED AS TO CONTENT:
arry herTei, city tngineer
APPROVED AS TO FORM:
J./Wqtth Fullingim, Assistantficity
At o ney
12th day of
April , 1990.
B. C. McMIN , MAYOR
MONTHLY ESTIMATE
CITY OFLUBBOCK
Project: Kingsgate Drainage & Street Improvements_ _ _ Project No. 9486
Contractor: Kerr Construction Company Estimate No. 4 & FINAL
Address: P. 0. Box 888 Contract $ 114, 084.00
Lubbock, Texas 79408
Estimate Period From March 26, . 19 90 to April 12, '1990
on First estimate and final estimate use actual work dates
ITEM UNIT OF PROJECT WORK DONE CONTRACT
MEASURE EST. QUANTITIES ON CONTRACT PRICE AMOUNT
1 Concrete Draina e -'Slab and S.Y. 245 215.70 5.00
APPROVED: Fo, Fn ,,'s C', , E' I r 118 460.32
Tots �=,tiiount of Work Done ....... � ,
(dIC II Ll11 nils hy: . . . . . . . . . . .. S 0
3 ?� Q !�d Less 5 %Retained
Engineer Date C;��� Difference ... e 118,460.32
-' Less Special Deduction . .. -----
2Ct,ecwe(jt)y:
Dept. Head Date Less Liquidated Damage .. $ -----
Less PrpOous PaVm.ents I ........ $ 112, 537 .30
Director Date Amount Due this Estimate......... $ 5,923.02
V.G. removal and disposal
2.
Curb and Gutter removal and
L.F.398.66
$ 5.00
disposal
3.
5" thick concrete drainage
S
511
17.909,146.90
slabs 3000 psi/28 da
4.
Curb and Gutter
L.F.
300
368.66
$ 6.65
$
2,451.59
5.
Ten foot storm sewer inlet box
Each
5
5
1.400.00
$
7,000.00
6.
Concrete erosion control slabs
S:Y
107.26
$ 33.90
3,636.11
3000psi/28 day concrete
7.
18" RCP Class 2 pipe installed
L.F.
1,000,000
$ 19.50
$
19,500.00
8.
6" thick concrete paving, w
S.Y.
2315
$ 22.90
52,768.93
5% entrained air Class "C"
3600 psi concrete
9.
Contraction and longitudinal
L.F.
3950
4,246
$ 1.25
5 307.50
concrete joint sawing and
sea
-ling
10.
1-1/2"THD Type "C" Asphalt
S.Y.
560
727.92
21.70
$
15,577.49
Concrete Paving with 6" of
Asphalt Stabilized Base.
APPROVED: Fo, Fn ,,'s C', , E' I r 118 460.32
Tots �=,tiiount of Work Done ....... � ,
(dIC II Ll11 nils hy: . . . . . . . . . . .. S 0
3 ?� Q !�d Less 5 %Retained
Engineer Date C;��� Difference ... e 118,460.32
-' Less Special Deduction . .. -----
2Ct,ecwe(jt)y:
Dept. Head Date Less Liquidated Damage .. $ -----
Less PrpOous PaVm.ents I ........ $ 112, 537 .30
Director Date Amount Due this Estimate......... $ 5,923.02