HomeMy WebLinkAboutResolution - 3836 - CO#1 To Contract- Williams & Peters Inc- Additional Paving, 21St & 25Th Streets - 03/26/1992JWF:js
RESOLUTION
Resolution No. 3836
March 26, 1992
Item X68
3E IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock BE and is hereby authorized and
directed to execute for and on behalf of the City of Lubbock a Change Order
No. 1 adding paving quantities to Project No. 591305-0001-3113 (En -Carlisle
Paving -- 21st & 25th Streets) to an existing Contract for paving improvements
between said City and Williams & Peters Construction Co., Inc., attached here-
with, which shall be spread upon the minutes of the Council and as spread upon
the minutes of this Council shall constitute and be a part of this Resolution
as if fully copied herein in detail.
Passed by the City Council this
ATTEST:
net�e boyo, Lity secretary
APPROVED AS TO CONTENT:
arry u. mertei, clty tngineer
26th day of March , 1992.
C
B. C. McMINK, MAYOR
APPROVED AS TO FORM:
c
L
U—.Wth Fullingim, Assistant City
At ney
WMS&PTRS.RES/D1-Agenda
Resolution No. 3836
March 26, 1992
Item #8
CHANGE ORDER NO. 1 TO PROJECT 591305-0001-3113
EN - Carlisle Paving -- 21st and 25th Streets
TO: Williams and Peters Construction Co., Inc.
P.O. Box 5215
Lubbock, TX 79417
Gentlemen:
WHEREAS, it is desirable to make changes in the plans and specifications
for this project, being namely the addition of the following:
Curb and Gutter and
Driveway Approaches on Avenue G
from 2nd Place to 3rd Place and
from 29th Street to 30th Street
WHEREAS, the Contractor herein agrees to the following change:
Original Amount of Contract $63,687.50
Increased by Change Order No. 1 9.617.50
Total Amount of Contract $73,305.00
15 Additional working days is allowed with this Change Order.
THIS AGREEMENT WITNESSETH: In consideration of the mutual advantages
gained, the Owner and the Contractor agree to the change shown herein and in
the revised plans, the Owner agrees to pay the Contractor the amount of
increase in cash. The Contractor agrees to proceed with construction and to
adhere to applicable specifications, under the direction of the Engineer.
Furthermore, the parties agree that the original contract between the Owner
and the Contractor shall be modified to the extent herein indicated, including
one (1) attachment.
IN WITNESS WHEREOF, the Owner and the Contractor have hereto set their
hands this 26th day of March , 1992.
WILLIAMS & PETERS CONSTRUCTION CO., INC.
(Contractor)
BY: TITLE: V10 - PR ES/OEIV T
BY: k . C • extz, 4 I0 �
B.C. McMinn
Mayor
RECOMMENDED FOR APPROVAL
arry He e
City Engineer
APPROVED AS TO FORM:
�7 gold _4 0
Worth Fullingim, Assistant
ty Attorney
CITY OF LUBBOCK
(Owner)
ATTES .
Rane o
City Se etary
CHANGE ORDER NO. 1
TO
PROJECT NO. 591305-0001-3113
(EN - Carlisle Paving -- 21st and 25th Streets)
Change Order No. 1 Consists of the Curb and Gutter
and Flatwork on Avenue G from 2nd Place to 3rd Place
and Curb and Gutter on Avenue G from 29th Street to
30th Street as Follows:
1. Add 1,565 LF to Item No. 2 for 24" concrete curb
and gutter at $5.75/LF = $ 8,998.75
2. Add 225 SY of 4" thick concrete driveway approaches
as Item No. 3 at $2.75/SY = $ 618.75
TOTAL CHANGE ORDER NO. 1 AMOUNT = $ 9,617.50
ORIGINAL CONTRACT AMOUNT =
$ 63.687.50
NEW CONTRACT AMOUNT = $ 73,305.00