HomeMy WebLinkAboutResolution - 2017-R0129 - Utility Contractors Of America - 04/13/2017Resolution No.2017-R0129
Item No.6.14
April 13,2017
RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock is hereby authorized and directed to execute for
and on behalf of the City of Lubbock, Change Order No. 1 to that certain Contract No. 12681 by
and between the City of Lubbock and Utility Contractors of America,Inc. for the NWWRP Raw
Sewage & Waste Activated Sludge Offsite Pipelines, and related documents. Said Change Order
No. 1 is attached hereto and incorporated in this resolution as if fully set forth herein and shall be
included in the minutes of the City Council.
Passed bythe City Council on April 13,2017
ATTEST:
?4_^*-*t^Rebecca Garza, City Secretar
APPROVED AS TO^CONTENT
DANIEL M.POPE,MAYOR
L.WoodTranklin,P.E.,DirectoTof'Public Works
APPROVED AS TO FORM:
Kelli Leisure,Assistant City Attorney
RES.ChgOrd#1.Contract 12681 -UtilityContractorsofAmerica
03.20.17
r
Contract No: 12681
Change Order No. 001
BID/RFP No. 16-12681-TF
City of Lubbock
Purchasing and Contract Management
Change Order
Contractor: Utility Contractors of America, Inc.
Contract Title: NWWRP Raw Sewage & Waste Activated Sludge Offsite Pipelines
Project Number: 92221.8242.30000
1. "Change Order" means a written order to a Contractor executed by the Owner in accordance with the contract authorizing an
addition to, deletion from, or adjustment or revision of the requirements of the contract documents, or an adjustment to the
compensation payable to Contractor, or to the time for performance of the contract and completion of the Project, or a
combination thereof, which does not alter the nature of the thing to be constructed and is an integral part of the project objective.
Adjustments to "Estimated Quantities" to a line item in a Unit Price contract do not require a Change Order. All work that alters
the nature of the thing to be constructed or that is not an integral part of the project objective must be let out for public bid.
Description of change (alteration, deviation, addition, or deletion) caused by conditions encountered during construction
not covered by the specifications and drawings of the project (attach additional pages ifnecessary):
PCM 001 (Add 60 Days): Add 1088 LF of 36" Hobas Pipe - Line 19 @ $210.00/LF ($228,480.00), Add 1088 LF of Trench Safety - Line 41 @$4.00/LF
($4,352.00). Add 2 EA Manholes - Line 31 @ $22,000.00/EA ($44,000.00), Add 2 EA 90 Degree Bends w/ Concrete per Quote ($30,300.00).
PCM 002 (Add 45 Days): Deduct 370 LF of Pipe, Casing & Bore (Quaker) - Line 11 @ $400/LF (-$148,000.00), Add 150 LF Pipe w/ Casing - Line 11
@$400/LF ($60,000.00), Add 220 LF Open Cut Pipe Line - 24 @$30/LF ($6,600.00), Add removal 225 SF Concrete Pvmt. Line - 46 @ $22/SY
($4,950.00), Add Repair Concrete 225 SY - Line 53 @ $96/SY ($21,600.00), Add Additional Traffic Control @ $3500/EA ($3,500.00).
(Add 150 Days): BNSF Railroad Surface Right of Entry Permit w/ BNSF & COL Contract; NO COST. Total Additional Days (CO 001): 255 days.
2. Where the Change Order is negotiated, the Change Order must be fully documented and itemized as to costs, including material
quantities, material costs, taxes, insurance, employee benefits, other related costs, profit and overhead. Where certain unit prices
are contained in the initial contract, no deviations are allowed in computing negotiated change order costs.
ITEMIZED COSTS MUST BE FULLY DOCUMENTED AND ATTACHED TO THIS FORM.
ITEM DESCRIPTION
A. ORIGINAL CONTRACT VALUE:
B. AMOUNT OF THIS CHANGE ORDER: Council approval required if over $25,000
COST CENTER: ACCOUNT:
C. PERCENT OF CONTRACT VALUE THIS CHANGE ORDER (B/A):
D. AMOUNT OF PREVIOUS CHANGE ORDERS:
E. TOTAL AMOUNT OF ALL CHANGE ORDERS (B+D):
F. PERCENT OF CONTRACT OF ALL CHANGE ORDERS (E/A): 25% increase
or decrease
G. NEW CONTRACT AMOUNT (A+E):
AMOUNT
$• 11,644,499.00
$ 255,782.00
2.2
$ 0.00
$ 255,782.00
2.2 %
,, 11,900,281.00
3. It is mutually agreed that the above dollar amount and the time extension, as applicable, as set forth in this Change Order constitutes
full compensation to the Contractor for all costs, expenses and damages to the Contractor, whether direct, consequential or otherwise,
in anyway incident to, or arising out of or resulting directly or indirectly, from the work performed or modified by the Contractor
under this Change Order.
This Ch_anee Order is not valid without the followine denatures (please sien in order and return 3 originals with Contract Cover Sheet to
Purchashng a d Contract Mana ement Department):
'42 �^' � Freese &Nichols 3/17/17
IL ILL /U,M CONTRACTOR b6 (2) PROJECT ARCHITECT/ENGINEER Date
as to Content:
PROJECTSa MANAGER
ApPITY
as to Forn
ate (4)ATTORNEY Date
Date (6) G AND CONTRAUr MANAGER Da e
Change Orders over $25,000 require a Contract Cover Sheet and the following sign res:
C OF LUB OC ATTEST:
4/1' 7 N4/13117
(7) MAYOR Date (8) CITY SECRET Y Date
Council Date: April 13, 2017 Agenda Item #: 6.14 — Resolution #:
PUR-45 (Rev 12/2012)
City of Lubbock
Purchasing and Contract Management
Change Order
PUR-45 (Rev 12/2012)
CHANGE ORDER (4.43)
PROJECT: NWWRP Raw Sewage & Waste Activated Sludge Offsite Pipelines
OWNER: City of Lubbock OWNER PROJ # 92221.8242.30000
CONTRACTOR: Utility Contractors of America, Inc. CONTRACT # 12681
ENGINEER: Alan Plummer, Inc. / Hugo Reed & Assoc. ENG. PROJ. # LUB16204
11CHANGE ORDER NO. 001 CHANGE ORDER DATE: 3/17/2017 11
Intake following additions/deletions or modifications to work described in the Contract Documents:
PCM 001,
Add 60
Days
PCM 002,
Add 45
Days
Add 150
Days
Description of Change
Add 1088 LF of 36" Hobas Pipe - Line 19 @ $210/1-F
Add 1088 LF of Trench Safety - Line 41 @ $4.00/1-F
Add 2 EA Manholes - Line 31 @ $22,000/EA
Add 2 EA 90 Degree Bends w/ Concrete per Quote
Deduct 370 LF of Pipe, Casing & Bore (Quaker) - Line 11 @ $400/1-F
Add 150 LF Pipe w/ Casing - Line 11 @ $400/1-F
Add 220 LF Open Cut Pipe - Line 24 @ $30/LF
Add Removal of 225 SF Concrete Pvmt. - Line 46 @ $22/SY
Add Repair Concrete 225 SY - Line 53@ $96/SY
Add Additional Traffic Control @ $3,500/EA
BNSF Railroad Surface Right of Entry Permit w/ BNSF & COL
Contract; NO COST
Cost
$228,480.00
$4,352.00
$44,000.00
$30,300.00
-$148,000.00
$60,000.00
$6,600.00
$4,950.00
$21,600.00
$3,500.00
$0.00
TOTAL COST OF THIS CHANGE ORDER:
$255,782.00
The compensation agreed to upon in this change order is full, complete and final payment for all costs the Contractor may incur as a result of or
related to this change whether said costs are known, unknown, foreseen or unforeseen at this time, including without limitation, any cost for delay,
extended overhead, ripple or impact cost, or any other affect on changed or unchanged work as a result of this Change Order.
Contract Cost and/or Time Impacts:
Original Contract Amount
$11,644,499.00
Previously Approved Change Order Amount
$0.00
Adjusted Contract Amount
$11,644,499.00
Proposed Change Order Amount (this change order)
$255,782.00
Revised Contract Amount
$11,900,281.00
Previous Contract Time
270
Previous Substantial Completion Date
13-Jan-17
Previous Final Completion Date
12-Feb-17
Net Change in Contract Time
255
Revised Contract Time
525
Revised Substantial Completion Date
25-Sep-17
Revised Final Completion Date
25-Oct-17
Recommended by:
FREESE AND NICHOLS, INC.
By / /°�� 3/17/2017
Date
Approved by:
UCA, I c.
By /Z 7 /Z 1-7
Date
proved by:
City of Lubbock
By
CERTIFICATE OF INTERESTED PARTIES
FORM 1295
1 of 1
Complete Nos. 1- 4 and 6 if there are interested parties.
OFFICE USE ONLY
Complete Nos. 1, 2, 3, 5, and 6 if there are no interested parties.
CERTIFICATION OF FILING
Certificate Number:
1 Name of business entity filing form, and the city, state and country of the business entity's place
of business.
2017-188938
Utility Contractors of America, Inc.
Lubbock, TX United States
Date Filed:
04/06/2017
2 Name of governmental entity or state agency that is a party to the contract for which the form is
being filed.
City of Lubbock
Date Acknowledged:
04/07/2017
3 Provide the identification number used by the governmental entity or state agency to track or identify the contract, and provide a
description of the services, goods, or other property to be provided under the contract.
12681
Northwest Water Reclamation Plant
4
Name of Interested Party
City, State, Country (place of business)
Nature of interest
(check applicable)
Controlling
I Intermediary
Ziegner, Jonathan
Lubbock, TX United States
X
Lane, Ty
Lubbock, TX United States
X
5 Check only if there is NO Interested Party. ❑
6 AFFIDAVIT I swear, or affirm, under penalty of perjury, that the above disclosure is true and correct.
Signature of authorized agent of contracting business entity
AFFIX NOTARY STAMP / SEAL ABOVE
Sworn to and subscribed before me, by the said this the
day of
20 , to certify which, witness my hand and seal of office.
Signature of officer administering oath Printed name of officer administering oath l itle of officer administering oath
Forms provided by Texas Ethics Commission www.ethics.state.tx.us Version V1.0.883
CERTIFICATE OF INTERESTED PARTIES FORM 1295
10f 1
Complete Nos. 1- 4 and 6 if there are interested parties.
OFFICE USE ONLY
Complete Nos.1, 2, 3, 5, and 6 if there are no interested parties.
CERTIFICATION OF FILING
Certificate Number:
2017-188938
1 Name of business entity filing form, and the city, state and country of the business entity's place
of business.
Utility Contractors of America, Inc.
Lubbock, TX United States
Date Filed-
04/06/2017
2 Name of governmental entity or state agency that is a party to the contract for which the form is
being filed.
City of Lubbock
Date Acknowledged:
g Provide the identification number used by the governmental entity or state agency to track or identify the contract, and provide a
description of the services, goods, or other property to be provided under the contract.
12681
Northwest Water Reclamation Plant
4
Name of Interested Party
City, State, Country (place of business)
Nature of Interest
(check applicable)
Controlling
I Intermediary
Ziegner, Jonathan
Lubbock, TX United States
X
Lane, Ty
Lubbock, TX United States
X
5 Check only if there is NO Interested Party. ❑
6 AFFIDAVIT 1 swear, or affirm, under penalty of perjury, that the above disclosure is true and correct.
�r;�R�'%1;;n- Tammy VanBuren
Notary Public. State of Texas j
My Comrr.ission Expires (�
September 27. 2020 i S . ` r f ar�thorized agent of contracting business enfiry
AFFIX NOTARY STAMP 7 SEAL ABOVE
Swom to crit�ed before me, by th d Ty Lane this the 6th day of April
20 1 certify\ ich, witness my han and seal of office.
Tammy VanBuren
Signature officer administerinal9allh Printed name of officer administering oath Title of officer administering oath
rorms proviaea lay 1 exas ttnics commission www.ethics.state.tx.us Version V1.0.883