HomeMy WebLinkAboutResolution - 6516 - Contract- Great Southwestern Construction Inc- LP&L,WS 230 Kv Transmission Line - 09/23/1999Resolution No. 6516
Sept. 23, 1999
Item No. 32
RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock BE and is hereby authorized and
directed to execute for and on behalf of the City of Lubbock a contract for Lubbock
Power & Light Wadsworth Substation 230 kV Transmission Line, by and between the
City of Lubbock and Great Southwestern Construction, Inc. of Castle Rock, Co. and
related documents. Said contract is attached hereto and incorporated in this resolution as
if fully set forth herein and shall be included in the minutes of the City Council.
Passed by the City Council this 23rd day of September , 19 99 ,
A/ -4
WINDY SITT , M YO
A
AS TO CONTENT:
0G�
Victor Kilman urchasing Manager
APPROVED AS TO FORM:
William de Haas
Competition and Contracts Manager/Attorney
gs:ccdocs/LP&L Wadsworth Substation -res
September 14, 1999
CONTRACT
STATE OF TEXAS
COUNTY OF LUBBOCK
THIS AGREEMENT, made and entered into this qday of September. 1999 by and between the City of
Lubbock, County of Lubbock, State of Texas, acting by and through the Mayor, City of Lubbock, thereunto authorized to
do so, hereinafter referred to as OWNER, and Great Southwestern Construction. Inc. of the City of Castle Rock.
County of Douglas and the State of Colorado hereinafter termed CONTRACTOR.
WITNESSETH: That for and in consideration of the payments and agreements hereinafter mentioned, to be made and
performed by the OWNER and under the conditions expressed in the bond bearing even date herewith (if any) the
CONTRACTOR hereby agrees with OWNER to commence and complete the construction of certain improvements
described as follows:
BID #99191 - LUBBOCK POWER & LIGHT WADSWORTH SUBSTATION 230 Kv TRANSMISSION LINE -
$179,450.00
and all extra work in connection therewith, under the terms as stated in the contract documents and at his (or their) own
proper cost and expense to furnish all materials, supplies, machinery, equipment, tools, superintendence, labor,
insurance and other accessories and services necessary to complete the said construction in accordance with the
contract documents as defined in the General Condition of Agreement.
The CONTRACTOR hereby agrees to commence work within ten days after the date written notice to do so shall have
been given to him and to substantially complete same within the time specified in the contract documents.
The OWNER agrees to pay the CONTRACTOR in current funds for the performance of the contract in accordance with
the bid submitted therefore, subject to additions and deductions, as provided in the contract documents and to make
payment on account thereof as provided therein.
IN WITNESS WHEREOF, the parties to these presents have executed this agreement in Lubbock, Lubbock County,
Texas in the year and day first above written.
owner's Representative
APPROVED AS TO FORM:
-- %ate
City Attorney
ATTEST:
Secretary
CONTRACTOR: GREAT SOUTHVVESTERN
CONSTRUCTION INC.
By.
PRINTED NAME: Qo bcr► A MogermIrr—
TITLE: PeE50Dc^ r
COMPLETE ADDRESS:
Great Southwestern Construction, Inc.
P.O. Box 849