HomeMy WebLinkAboutResolution - 2000-R0276 - Approve Paving Alley - Between Buddy Holly Ave And Texas Ave - 08/24/2000Resolution No. 2000-80276,
August 24, 2000
Item No. 28
RESOLUTION
WHEREAS, the City Council has heretofore determined that the City would
contribute the customary City portion of the cost of alley paving improvements, as
determined by City of Lubbock paving policy, to be constructed as approved by the
City Engineer, and the Owners of the property abutting the N -S alley between Buddy
Holly Avenue and Texas Avenue from 17`'' Street to 18th Street, have requested
permission to have pavement improvements constructed on the aforementioned alley
and the paving of said alley is needed to provide access to the area during its
construction period, and the City Engineer has approved the plans and specifications for
such improvements; and
WHEREAS, the Owners of the property abutting on the herein described alley
will contract separately with a competent contractor for the above alley improvements,
and said improvements will be constructed in accordance with the above-mentioned
plans and specifications under the supervision of the City Engineer, and the said
Owners desire that the City Contribute its customary share towards such paving; and
WHEREAS, the contract cost of the paving improvements will not exceed
$10,237.50 the total cost not over $10,851.75 and the City's share in connection
therewith would not exceed $1,085.18, leaving the property owner's portion not to
exceed $9,766.57, such costs being well within the current prices for paving obtained
by competitive bidding, and that such payment to be made by the City is reasonable,
fair, and just to the abutting property owners, the city and all other persons affected
thereby, and that the sum of $1,085.18 will be duly budgeted; NOW THEREFORE:
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
Section 1. - THAT, the City Engineer be and he is hereby authorized to
approve plans and specifications for paving on the alley herein described, provided that
such plans and specifications meet the usual requirements for paving on alleys within
the corporate limits of the city of Lubbock; said alley being as follows, to -wit:
The N -S alley between Buddy Holly Avenue and Texas Avenue from its intersection
with the South Lip Line of 17' Street to its intersection with the North Property Line of
18' Street known and designated as Sub -unit Number 96 of Unit Number A-461.
The City Engineer is further authorized and directed to duly inspect said paving
construction on said alley and to require strict compliance with the approved plans and
specifications, and upon completion of said paving, and upon final approval by the City
Engineer and acceptance of such improvements by the City Council, the City Engineer
is authorized to pay the Contractor in full and final payment of the City's share of the
cost of the above-mentioned improvements a sum not to exceed $1,023.75 which is the
City's share ($1,085.18 less $61.43 engineering) leaving the amount due the Contractor
from the property owners not to exceed $9,213.75.
17" — IS" Street Paving
Page 1 of 3
Section 2. This authority is conditioned that the Owners of abutting property
and the Contractor will pay for all materials and labor and costs incidental to such
construction, indemnify the City of Lubbock against any costs, claims or damages of
every nature pertaining thereto, and that the Contractor furnish the City Engineer with
acceptable evidence that the Contractor and his subcontractors, if any, are adequately
covered by public liability and property damage insurance policies, that the said
Owners of abutting property will cause such paving to continue to be done according to
the approved plans and specifications, and that upon completion thereof and final
approval of the City Engineer, all improvements designated herein shall be permanent
part of said alley and the property of the City of Lubbock, without any liability
whatsoever, except for the payment of a sum of $1,023.75 to the Contractor.
Passed by the City Council this 24th day of August 2000.
WINDY SITTONJ MAYOR
ATTEST:
Kaythi Darnell, City Secretary 11
The Owners of the abutting property on the above-mentioned alley, and ED
CURBO CONSTRUCTION, INC., Contractor, do hereby accept and agree to fully
abide by the foregoing provisions for the considerations therein stated.
ED
Un
CONTRACTOR
P/0",
PROPERTY OWNER ABUTTING FOOTAGE AMOUNT
Luther A. Avitts, Jr. 520.00' $9,766.57
Lots 1-20, Block 214
Original Town
17' — 196 Street Paving
Page 2 of 3
AS TO CONTENT:
Larry Hertel
City Engineer
APPROVED AS TO FORM:
M. Knight
Assistant City Attorney
JMK:cp Cityatt/John/AlleyPavingl7-18.res & ccdocs
August 8, 2000
171h — 1 e Street Paving
Page 3 of 3