March 13, 2008
Item No, 4.19
RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the City Council of the City of Lubbock hereby authorizes and directs the
Mayor of the City of Lubbock to execute an Amendment 91 to a Professional Engineering
Services Contract entered into August 23, 2007, by and between the City of Lubbock and
HDR Engineering, Inc., of Austin, Texas, for engineering services related to storm water
drainage issues in Mose Hood and Stumpy Hamilton parks, which Contract and any
associated documents, are attached hereto and made a part of this Resolution for all
intents and purposes.
Passed by the City Council this 13th day of
ATTEST:
Reb cca Garza, City Secretary
APPROVED AS TO CONTENT:
Michael G. Keenum, P.E.
Storm Water Engineer
APPROVED AS TO FORM:
Don Vandiver, Attorney of Counsel
DDres/H DR-FngSvesCon08AmendRes
February 29, 2009
March , 2007.
DAVID A. MILLER, MAYOR
Resolution No. 2008-R0090
AMENDMENT 41 TO AGREEMENT
BETWEEN THE CITY OF LUBBOCK, TEXAS
AND HDR ENGINEERING, INC.
FOR
PROFESSIONAL ENGINEERING SERVICES
THIS IS AN AMENDMENT TO THE AGREEMENT dated and effective as of August
23, 2007 between The City of Lubbock, Texas and HDR Engineering, Inc. OWNER and
ENGINEER in consideration of their mutual covenants as set forth herein agree to
modify the Agreement as follows:
Revise Exhibit A, Paragraph A1.03 to read as follows:
A1.03 Final Design Phase
A. After acceptance by Owner of the Report and any other deliverables,
selection by Owner of a recommended solution and indication of any specific
modifications or changes in the scope, extent, character, or design requirements of
the Project desired by Owner, and upon written authorization from Owner,
Engineer shall:
1. Prepare Construction Plans: ENGINEER will prepare detailed construction
drawings in accordance with City of Lubbock standards. Both Park site
drainage improvements will be included in one plan set and bid as one project.
Provide 50%, 90%, and "Issued for Bid" set of complete FDF copies of
construction drawings for review and comment by OWNER. Upon final
approval, provide electronic PDF set of "Issued for Bid" construction plan sets.
Based on the current scope of the Project, the construction plans are anticipated
to include the drawings listed below.
(1) Cover Sheet
(2) General Construction Notes
Site Layout Sheets - Mose Hood & Stumpy Hamilton Parks (MHP &
(3-4) SHP) - 2 Sheets
(5-6) Grading, Erosion & Sedimentation Control Plan MHP & SHP - 2 Sheets
(7) Erosion and Sediment Control Details - I Sheet
(8-9) Storm Sewer Plan & Profile MHP - 2 Sheets
(10) Storm Sewer Plan & Profile SHP - 1 Sheet
(11-12) Grading and Drainage Standard Details - 2 Sheets
(13-15) Special Structures/Trash Rack Details - 3 Sheets
(16-17) Temporary Irrigation Plan & Details SHP - 2 Sheets
(18-19) Permanent Irrigation Plan & Details MHP - 2 Sheets (prepared by City)
OWNER's Responsibilities: Review 50%, 90%, and Issued for Bid set of
construction plans and provide comments to ENGINEER in a timely manner.
Provide permanent irrigation plan and details for Mose Hood Park to be
included in construction plan set.
2. Perform "No Rise" Floodplain Analysis: ENGINEER will obtain the current
effective FEMA hydrologic and hydraulic models and develop post-project
models based on the final design. ENGINEER will compare the post-project
base flood elevations with the current effective base flood elevations for
compliance with minimum FEMA NFIP requirements and OWNER°s
floodplain regulations. ENGINEER will prepare a brief technical memorandum
summarizing the results of the analysis.
OWNER's Responsibilities. OWNER's Floodplain Administrator will
determine if a FEMA Letter of Map Change (LOMC) is required based on the
results of the No Rise Floodplain Analysis. If required, ENGINEER will
perform the LOMC work upon written authorization to proceed from OWNER.
OWNER will be responsible for payment of associated regulatory fees.
3. Prepare and Process FEMA CLOMRILOMR: Upon OWNER's review of the
No Rise Floodplain Analysis, and if deemed necessary by OWNER,
ENGINEER will, upon written authorization to proceed from OWNER, prepare
and process a FEMA CLOMR application based on the final design. Upon
completion of construction of the project improvements, ENGINEER will
prepare and process a FEMA LOMR application based on the final record
drawings. ENGINEER will process the CLOMR/LOMR applications through
final approval by FEMA. ENGINEER will assist the OWNER in providing
standard notifications to affected property owners by determining and providing
the OWNER with the affected parcels.
OWNER's Responsibilities: OWNER will be responsible for payment of
associated regulatory fees. OWNER's Floodplain Administrator will review
and approve CLOMR and LOMR applications prepared by ENGINEER.
OWNER will prepare and deliver standard notifications to property owners
affected by the CLOMR/LOMR per FEMA requirements.
4. Prepare Technical Specifications: ENGINEER will prepare complete Technical
Specifications for construction in accordance with TxDOT standards and
applicable City of Lubbock standards, as well as Special Provisions to
Technical Specifications and Special Specifications as required. Provide 90%
and "Issued for Bid" PDF copy of Specifications for review and comment by
the OWNER. Upon final approval, provide electronic set of Issued for Bid
Specifications.
OWNER's Responsibilities. Review 90% and Issued for Bid Technical
Specifications and provide comments to ENGINEER in a timely manner.
OWNER will prepare "Front End" bidding documents including, but not
limited to, Bidding Requirements, Contract Forms, and Conditions of the
Contract. OWNER will provide Technical Specifications for the permanent
irrigation design for Mose Hood Park.
5. Opinion of Probable Construction Cost: ENGINEER will prepare opinion of
probable Construction Cost for the Work. The opinion will be based on recent
bid tabulations for similar work available to ENGINEER and/or provided by the
OWNER. ENGINEER will furnish a PDF copy of cost estimate to OWNER.
OWNER's Responsibilities: Furnish bid tabulations available to the OWNER
(if any) for similar projects in the Lubbock area within the previous 36 months.
Review the opinion and provide review comments to ENGINEER in a timely
manner. OWNER will provide their cost estimate for their permanent irrigation
plan design for Mose Hood Park.
B. ENGINEER's services under the Final Design Phase will be considered
complete on the date when the deliverables required by paragraphs A1.03.A.1-4
have been delivered to OWNER.
Revise Exhibit A, Paragraph Al. 04 to read as follows:
A1.04 Bidding or Negotiating Phase
A. After acceptance by Owner of the Bidding Documents and the most recent
opinion of probable Construction Cost as determined in the Final Design Phase, and
upon written authorization by Owner to proceed, Engineer shall:
1. Assist in Advertising for Bids: Assist Owner in advertising for and obtaining
bids or proposals for the Work.
OWNER's Responsibilities: Maintain a record of prospective bidders to
whom Bidding Documents have been issued and receive and process
contractor deposits or charges for the Bidding Documents.
2. Pre -Bid Conference: ENGINEER will prepare and conduct a Pre -Bid
Conference to present the project to prospective bidders, provide clarifications,
and answer questions.
OWNER's Responsibilities: Attend Pre -Bid Conference and provide meeting
facilities.
3. Prepare Responses to RFI's: ENGINEER will prepare and issue addenda
required to clarify Contractor requests for information.
4. Review Bids: ENGINEER will attend the Bid opening, prepare Bid
tabulations, assist OWNER in evaluating Bids or proposals, and make
recommendations to the OWNER within five (5) days of bid opening.
B. The Bidding or Negotiating Phase will be considered complete upon
commencement of the Construction Phase or upon cessation of negotiations with
prospective contractors.
Revise Exhibit C, Paragraph C4.01A to read as follows:
A. OWNER shall pay ENGINEER for Basic Services set forth in Exhibit A as
follows:
1. A Lump Sum amount of $111,807.00 based on the following
assumed distribution of compensation:
a. Field Survey $21,735.00
b. Preliminaa Design Phase $10,485.00
Original Contract Subtotal: $32,220.00
C. Final Design Phase $61,519.00
d. Bidding and Negotiating Phase $10,068.00
e. FEMA CLOMR/LOMR $8,000.00**
£ Construction Phase $ TBD*
Amendment #1 Subtotal: $79,587.00
*To be negotiated upon completion of the Bidding & Negotiating Phase.
**Dependent on results of"No Rise" floodplain analysis, requires written
authorization to proceed by OWNER.
2.4. (no change)
5. The Lump Sum is conditioned on Contract Times to complete the
Work not exceeding fifteen (15) months. Should the Contract Times to
complete the Work be extended beyond this period at no fault of the
ENGINEER, the total compensation to ENGINEER shall be appropriately
adjusted.
IN WITNESS WHEREOF, the parties hereto have executed this Amendment.
OWNER-: City of Lubbock, Texas ENGINEER: R Engineering Inc.
Title: David A. Miller, Mayor Title:
Date Signed: March 13, 2008 Date Signed: Z'4?0'G`df
ATTEST.CQo.�� C:��
C4 Secretary
Approved:
As to Content: "
Title
As to
Title: