HomeMy WebLinkAboutResolution - 2012-R0240 - Contract - Minnix Commercial Partners Ltd.- Landfill Office Renovations - 06/07/2012Resolution No. 2012—RO240
June 7, 2012
Item No. 5.7
RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock is hereby authorized and directed to
execute for and on behalf of the City of Lubbock, Contract No. 12-10741-JOC for
renovations to the landfill office and building, by and between the City of Lubbock and
Minnix Commercial Partners, Ltd, and related documents. Said Contract is attached
hereto and incorporated in this resolution as if fully set forth herein and shall be included
in the minutes of the City Council.
Passed by the City Council on June 7, 2012
FFA
I_ M O.
TTEST:
ERebecdp Garza, City Secretary
APPROVED AS TO CO
Scott Snider, Assistant City Manager
Community Services
APPROVED AS TO FORM:
Chad Weaver, Assistant City Attorney
:ccdocs/RES.Contract-Minn ix Commerciai
,y 10, 2012
Resolution No. 2012—R0240
Contract No. 10741
Work Order Signature Document
BUYBOARD EQIQC Contract No.: Area I —1 MCP — Option 1
FINew Work Order O Modify and Existing Work Order
Work Order Number: 12294.00 Work Order Date: 03/07/2012
Work Order Title: Landfill Office and Building Remodel
Owner Name: City of Lubbock Contractor Name: Minnix Commercial Partners, LTD.
Contact: Scott Snider Contact: Keenan Davis
Phone: (8061775-2312 Phone: (8061798-7335
Work to be Performed
Work to be performed as per the Final Detailed Scope of Work Attached and as per the terms and conditions of
BuyBoard EZIQC Contract No Area I —1 MCP — Option 1.
Brief Work Order Description:
Renovate the Landfill Office and Building
Time of Performance See Schedule Section of the Detailed Scope of Work
Work Order Number
12294.00
CITY OF LUBB CK
Glenn, a or
Attest:
RebeccaGar, , City Secretary
APPROVED NTINT:
+' " 1
Scott Snider, Assistant City Manager
Location
North Avenue P Landfill
Amount of Contract
$28,580.28
Kee Davis, Project Manager
Minnix Commercial Partners, LTD
Owner's Repretative
Wesley Everett, Director of Facilities
APP D S O FORM:
Assistant City Attorney
r
Board'�
Caepe-fi- P.-haain®
Detailed Scope of Work
To: Keenan Davis
From: Wes Everett
Minnix Commercial
Partners, LTD
City of Lubbock
PO Box 64895
1625 13th St
Lubbock, TX 79464
Lubbock, TX 79401
(806)798-7335
806-775-2275
Date Printed:
May 16, 2012
Work order Number:
012294 00
Work Order Title:
City of Lubbock - Landfill Office Remodel
Brief Scope:
Landfill Office Remodel
i4m
Preliminary F-1 Revised O Final
The following items detail the scope of work as discussed at the site. All requirements necessary to accomplish the items
set forth below shall be considered part of this scope of work.
Repair sub floor and replace with VCT.
Float existing floor and put down new 112" overlay.
Install new VCT and cove base.
Cut down any doors necessary for installing new subf400r.
Install 5 new aluminum windows and reinstall existing metal grating over windows.
Install new 26 gauge R -Panel siding along with new trim, closures, gutter and downs pouts(North and South).
Caulk along building exterior to help prevent water damage.
Remove and reinstall all electrical currently mounted to structure as necessary for new siding.
Provide new 4" concrete pad on south side of building as discussed.
Provide new stair landing with step and handrail on one side.
Time of Performance
60 Working Days pending any material delays.
Scope of Work Page 1 of 1
EZ1QC - Buy Board 511 612 0 1 2
Contractor's Price Proposal CSI - Summary
Date: March 07, 2012
Re- QC Master Contract #:
Work Order #:
Owner PO #:
Title',
Contractor:
Proposal Value:
Area I - 1 MCP - Option 1
012294 00
City of Lubbock - Landfill Office Remodel
Minnix Commerciai Partners, LTD
$28,580 28
01 - General Requirements
$3,476.53
02 - Site Work
$122.00
03 - Concrete
$2,926.41
05 - Metals
$419.99
06 - Wood, Plastic, and Composites
$1,800.14
07 - Thermal & Moisture Protection
$12,322.99
08 - Openings
$3,184.38
09 - Finishes
$4,327.84
Proposal Total $28,580.28
Contractor's Price Proposal - Summary Page 1 of 1
EZ1QC - Buy Board 31712012
Contractor's Price Proposal CSI - Detail
Date: March 07, 2012
Re; IQC Master Contract #:
Area I - 1 MCR - Option 1
Work Order #:
012294.00
Owner PO #:
Title:
City of Lubbock - Landfill Office Remodel
Contractor:
Minnix Commercial Partners, LTD
Proposal Value:
$28,580.28
Sect Item Modifer
UOM Description
Line Total
Labor Equip. Material {Excluded if marked with an X)
01 - General Requirements
1 01352 0010
HR Electrician Note: Tasks in the CTC include appropriate costs to cover labor.
$3,476.53
These tasks will be requested specifically by the owner for miscellaneous
work
not covered in the CTC.
Quantity Unit Price
Factor
Total
Installation 9000 x 30.90 x
1.2501
3,476.53
Disconnect and reinstall all electrical to building.
Subtotal for 01 - General Requirements
$3,476.53
02 - Site Work
2 02210 0003
CY Excavation For Building Foundations And Other Structures By Bobcat in Soil
$30.90
Quantity Unit Price
Factor
Total
Installation 800 x 3.09 x
1.2501
30.90
3 02MOD 0003 0086
For Quantities Up To 20 (Up To 15 M3), Add
$30.90
Quantity Unit Price
Factor
Total
Installation=
8,00 x 3.09 x
1.2501
30.90
4 02210 0021
CY Compaction Of Fill Or Subbase For Building Foundations and Other Structures
$30.10
by Vibratory Plate, Air Tamper, Etcetera
Quantity Unit Price
Factor
Total
Installation 8,00 x 3.01 x
1,2501
30.10
5 02MOD 0021 0094
For Quantities Up To 20 (Up To 15 M3), Add
$30.10
Quantity Unit Price
Factor
Total
Installation 8,00 x 3.01 x
1.2501
30.10
Subtotal for 02 - Site Work
$122.00
03 - Concrete
6 03110 0028
SF Cast On Grade Stairway Woad Formwork
$292.02
Quantity Unit Price
Factor
Total
Installation 40.00 x 5.84 x
1.2501
292.02
7 03210 0006
TON Grade 60 Reinforcing Steel, Footings And Slabs, #3-#8
$652.46
Quantity Unit Price
Factor
Total
Installation 0,33 x 1,581.60 x
1.2501
652.46
8 03311 0026
CY Up To 6", By Direct Chute, Place 3000 PSI Concrete Slab On Grade
$1,269.23
Quantity Unit Price
Factor
Total
Installation 11.00 x 92.30 x
1,2501
1,269.23
9 03MOD 0026 0046
For Quantities Up To 20, Add
$56,65
Quantity Unit Price
Factor
Total
Installation 11.00 x 4.12 x
1.2501
56.65
10 03311 0034
CY Direct Chute, Place 3000 PSI On Grade Concrete Stairs
$320.93
Quantity Unit Price
Factor
Total
Installation 2.00 x 128.36 x
1.2501
320.93
Contractor's Price Proposal - Detail
Page 1 of 4
EZlQC - Buy Board
3f712012
Contractor's Price Proposal - Detail Continues..
Work Order Number: 012294.00
Work Order Title: City of Lubbock - Landfill Office Remodel
Sect. Item
Modifer UOM Description
Line Total
Labor Equip.. Material
(Excluded If marked with an X)
03 - Concrete
11 03MOD 0034
0046 For Quantities Up To 20, Add
546.35
Quantity
Unit Price
Factor
Total
Installation 2.00 x
18.54 x
1.2501
46.35
12 03350 0004
SF Concrete Floor Finishes, Broom
$268.77
Quantity
Unit Price
Factor
Total
Installation 700.00 x
0.33 x
1,2501
288.77
Subtotal for 03 - Concrete
$2,926.41
05 - Metals
13 05521 0005
LF 2" Diameter (51 mm) Welded Pipe Handrail, 2 Rail, Up To 42" High (1.07 m)
$323.23
With Shop Paint
Quantity
Unit Price
Factor
Total
Installation 8.00 x
32.32 x
1.2501
323.23
14 05530 0004
SF 314"x 3116" Steel, Welded Grating
$96,76
Quantity
Unit Price
Factor
Total
X
Installation 60,00 x
0.88 x
1.2501
64.51
X
Demolition 60.00 x
0.43 x
1,2501 =
32.25
Subtotal for 05 - Metals
$419.99
06 - Wood, Plastic, and Composites
15 06160 0017
SF 1/2" (12mm) CD Grade Plywood Floor DeckingNote: Applied To Floor Or Joists
$1,800,14
Quantity
Unit Price
Factor
Total
Installation 1.170.00 x
1.22 x
1.2501 =
1,784.39
Demolition 60.00 x
0.21 x
1.2501 =
15.75
Subtotal for 06 -Wood, Plastic, and Composites
$1,800.14
07 - Thermal & Moisture Protection
16 07410 0008
SF 26 Gauge Galvanized Exposed Fastener Metal Root Panels
$3,985.07
Quantity
Unit Price
Factor
Total
Installation 1,265.00 x
2.24 x
1.2501 _
3,542,28
Demolition 1,265.00 x
0.28 x
1,2501 =
442.79
17 07620 0056
SF Aluminum Flashing, 0.013" Thick, Mill Finish
$21.83
Quantity
Unit Price
Factor
Total
Installation 6.00 x
2,91 x
12501 =
21.83
18 07620 0090
LF 4" Wide Facia
$3,829,81
Quantity
Unit Price
Factor
Total
Installation 460.00 x
5.77 x
1.2501
3,318.02
Demolition 460.00 x
0,89 x
1.2501
511.79
19 07631 0065
LF 3" x 4" Rectangular Corrugated Downspout Galvanized Steel,
28 Gauge
$188.02
Quantity
Unit Price
Factor
Total
Installation 40,00 x
3.76 x
1-2501
188.02
20 07631 0073
LF 6" Galvanized Steel Gutter, 28 Gauge
$400.03
Quantity
Unit Price
Factor
Total
Installation 10000 x
120 x
1.2501 =
400.03
Contractor's Price Proposal - Detail Page 2 of 4
EVOC - Buy Board 3(712012
Contractor's Price Proposal - Detail Continues..
Work Order Number: 012294.00
Work Order Title: City of Lubbock - Landfill Office Remodel
Sant.
Item Mlodifer
UOM Description
Line Total
Labor Equip.
Material (Excluded if marked with an X)
07 - Thermal & Moisture Protection
21 07920
0005
CLF 318" x 3f8" Joint, Silicone Sealant And Caui'king
$3,541.22
Quantity Unit Price
Factor
Total
Installation 1$00 x 188.85 x
1-2501
3,541.22
22 07920
0059
CLF 314" x 314" Joint, Polyurethane Sealant And Caulking
$357.01
Quantity Unit Price
Factor
Total
Installation 075 x 380.78 x
1,2501
357.01
Subtotal for 07 - Thermal & Moisture Protection
$12,322.99
08 - Openings
23 08520
0020
EA ?10 To 15 SF, 3-1/4" Frame Depth, HC 40, Side Loading Sash, Single Hung
$3,184.38
Aluminum Window (Traco TR -9700)
Quantity Unit Price
Factor
Total
Installation 500 x 472.64 x
1.2501 =
2,954.24
Demolition 5,00 x 3682 x
1.2501 =
230.14
Subtotal for 08 - Openings
$13,184.38
09 - Finishes
24 09305
0002
SF Thin -Set - Latex Portland Cement Mortar
$950.70
Quantity Unit Price
Factor
Total
Installation 1,170.00 x 0.65 x
1.2501 -
950.70
25 09MOD
0002 0062
For Quantities T 1000, Deduct
-$73.13
Quantity Unit Price
Factor
Total
Installation 1,170.00 x -0.05 x
1.2501
-73.13
26 09650
0024
SF Marbleized Pattern Vinyl Composition Tile 118" Thick
$2,632.71
Quantity Unit Price
Factor
Total
Installation 1,170.00 x 1.80 x
12501
2,832.71
27 09MOD
0024 0190
For Quantities > 1000 To 3000, Deduct
-$29.25
Quantity Unit Price
Factor
Total
Installation 1,170,00 x -0.02 x
1.2501
-29.25
28 09650
0033
LF 4" High 1/8" Vinyl Plastic Base, All Colors
$798.81
Quantity Unit Price
Factor
Total
Installation 300,00 x 1,75 x
12501
656.30
Demolition 300,00 x 0.38 x
1.2501
142.51
29 09910
0334
LF Paint Steel Pipes 4" Diameter, One Coat Primer
$16.50
Quantity Unit Price
Factor
Total
Installation 20.00 x 0.66 x
1.2501 2
16.50
30 09910
0344
LF Paint Steel Pipes 4" Diameter, Two Coats
$31,50
Quantity Unit Price
Factor
Total
Installation 20.00 x 1.26 x
1 2501 m
31.50
Subtotal for 09 - Finishes
$4,327.84
Contractor's Price Proposal - Detail Page 3 of 4
EZlQC - Buy Board 3!712012
Contractor's Price Proposal - Detail Continues.,
Work Order Number: 012294.00
Work Order Title: City of Lubbock - Landfill Office Remodel
Proposal Total $28,580.28
This total represents the correct total for the proposal. Any discrepancy between line totals,
sub-lctals and the proposal total is due to rounding.
Contractor's Pnce Proposal - Detail Page 4 of 4
EZIQC - Buy Board 3/7/2012