HomeMy WebLinkAboutResolution - 2013-R0359 - Contract - Minnix Commercial Partners LTD - Fire Admin Complex Renovations - 10/24/2013Resolution No. 2013-RO359
October 24. 2013
Item No. 5.20
RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock is hereby authorized and directed to
execute for and on behalf of the City of Lubbock, Contract No. 11546 for various
renovations at the City of Lubbock Fire Administration Complex, by and between the
City of Lubbock and Minnix Commercial Partners, Ltd. and related documents. Said
Contract is attached hereto and incorporated in this resolution as if fully set forth herein
and shall be included in the minutes of the City Council.
Passed by the City Council on October 24, 2013
Gr,P(C.—ROB ERTSON, MAYOR
ATTEST:
Dho-AA-- e2�)c
Reb cca Garza, City SecretAZ_)
APPROVED AS TO CONTENT:
C -Y -n a--6 k ---d -
Mark wood,assistant-
tity Manager
Chief Information Officer
APPROVE AS TO FORM:
Chad Weaver, Assistant City Attorney
vw:ccdocs.' RES.Contract-Minnix
October 2, 2013
Resolution No. 2013-RO359
Work Order Signature Document
Contract No. 13-11546-JOC
BUYBOARD EQIQC Contract No.: 2012 Area J - MCP
FINew Work Order 1:1 Modify and Existing Work Order
Work Order Number: 011295.12 Work Order Date: 8/5/2013
Work Order Title: Lubbock Fire Training Flooring-Bomanite Options
Owner Name: City of Lubbock Contractor Name: Minnix Commercial Partners, Ltd.
Contact: Wesley Everett Contact: Keenan Davis
Phone: (806) 775-2665 Phone: (806) 798-7335
Work to be Performed
Work to be performed as per the Final Detailed Scope of Work Attached and as per the terms and conditions of
BuyBoard EZIQC Contract No. 2012 Area J - MCP.
Brief Work Order Description:
Lubbock Fire Training Flooring-Bomanite Options
Time of Performance
LIQUIDATED DAMAGES: If the performance period of a Job Order exceeds 30 days, partial payment is authorized,
based on a percentage of completion minus a 5% retainage of total sum of JO. Liquidated damages may be assessed if
project extends beyond JO agreed completion date
Work Order Number Location Amount of Contract
011295.02 Fire Training Complex 1515 E. $161, 264.24
Ursuline. Lubbock, Texas
CITY OF LUBBOCK
Glen C. ertson, Mayor Keenan Davis, Project Manager
Minnix Commercial Partners, Ltd.
Attest: 0epreAentative
Rebecca Gar -.-7, City Secretary jjj f1q�\YGr
Wesley Everett, Director of Facilities
APPROVED AS CONTENT: APP D A �10 FORM:
Mark Yearwo Chief Information Office Assistant City Attorney
Assistah City Manager
Work Order Signature Document
BUYBOARD EZIQC Contract No.: Area I -1 MCP - Option 1
❑ New Work Order X] Modify an Existing Work Order
Work Order Number: 011295.02 Work Order Date:
Work Order Title: Lubbock- Fire Training Flooring_ Bomanite
Owner Name: City of Lubbock Contractor Name: Minnix Commercial Partners, LTD
Contact: Wes Everett Contact: Keenan Davis
Phone: 806-775-2275 Phone: (806) 798-7335
Work to be Performed
Work to be performed as per the Final Detailed Scope of Work Attached and as per the terms and conditions of
BuyBoard EZIQC Contract No Area I - 1 MCP - Option 1.
Brief Work Order Description:
Fire Training Flooring - Bomanite Option.
Time of Performance See Schedule Section of the Detailed Scope of Work
Liquidated Damages Will apply: 191 Will not apply: El
Work Order Firm Fixed Price: $116,988.02
Owner Purchase Order Number:
AnIlrovalls
Owner - Date
Contractor Date
Work Order Signature Document Page 1 of 1
EZIQC - Buy Board 10/2/2013
P: Board®
V
aoperefire Puraheelnp
4IQC
Detailed Scope of Work THE GORDIAN GROUP
To: Keenan Davis From: Wes Everett
Minnix Commercial Partners, LTD City of Lubbock
PO Box 64895 1625 13th St
Lubbock, TX 79464 Lubbock, TX 79401
(806) 798-7335 806-775-2275
Date Printed: October 02, 2013
Work Order Number: 011295.02
Work Order Title: Lubbock- Fire Training Flooring_ Bomanite
Brief Scope: Fire Training Flooring - Bomanite Option.
F]Preliminary F� Revised FX Final
The following items detail the scope of work as discussed at the site. All requirements necessary to accomplish the
items set forth below shall be considered part of this scope of work.
Remove existing flooring and base, provide new in the following Rooms:
Bomanite Polished Concrete - B101, B102, B103, B104, B105, B106, B107, B108, B109, B120, B130, B131, B134,
B135, B136
Carpet- B111, 8121, B122, B123, B124, B125, B126, B138
Triumph Athletic Flooring - B 117, B137
No flooring in Room B132, B133
Paint all walls and jambs as discussed.
Wipe down all doors with Watco as discussed.
Modify existing cabinets/countertop in break room.
Provide new stainless steel top with integral sink in break room from wall to wall.
Install new garbage disposal and necessary electrical.
Install water line with in-line filter to coffee maker. Coffee maker provided and installed by others.
Provide new faucet, drain lines, and stops.
Joint filler in exposed concrete flooring control joints.
Bomanite Diamond polished concrete to be Level II finish (1500 Grit).
Excluded:
Staining, dyeing, decorative scoring, logo, or burnishing.
Deep grinding for a "terrazzo finish" is excluded as well.
Major unforeseen prep work of concrete.
Scope of Work Page 1 of 2
EZIQC - Buy Board 10/2/2013
Detailed Scope of Work Continues..
Work Order Number: 011295.02
Work Order Title: Lubbock- Fire Training Flooring_ Bomanite
Conti ctor 4 Date
J�� C
16) -VI
Owner Date
Scope of Work Page 2 of 2
EZIQC - Buy Board 10/2/2013
Contractor's Price Proposal CSI - Summary
Date: October 02, 2013
Re: IQC Master Contract #:
Work Order #:
Owner PO #:
Title:
Contractor:
Proposal Value:
Area I - 1 MCP - Option 1
011295.02
Lubbock- Fire Training Flooring_ Bomanite
Minnix Commercial Partners, LTD
3116,988.02
No Section Input
$66,341.15
01 - General Requirements
$15,165.13
03 - Concrete
$840.07
08 - Openings
$326.40
09 - Finishes
$33,867.30
11 - Equipment
$173.94
15 - Mechanical
$274.03
Proposal Total
The Percentage of NPP on this Proposal: 65.86%
$116,988.02
Contractor's Price Proposal - Summary Page 1 of 1
EZ/QC - Buy Board 10/2/2013
Contractor's Price Proposal CSI - Detail
Date: October 02, 2013
Re: IQC Master Contract #: Area I - 1 MCP - Option 1
Work Order #: 011295.02
Owner PO #:
Title: Lubbock- Fire Training Flooring_ Bomanite
Contractor: Minnix Commercial Partners, LTD
Proposal Value: $116,98802
Sect. Item Modifer UOM Descripflon Line Total
Labor Equip. Material (Excluded if marked with an X)
No Section Input
1 90 00 00 17 SF TdumpftRubber Athletic Flooring $25,639.90
Quantity Unit,Frice Factor Total
NPP Installation Quantity
x 17.93 x 1.0000 25,639.90 I
2 90 00 OQ 25 SF Sorganitw0lamond Polished Concrete with Level 11 Finish {1$00 t3lit)
Total
229.59
$34,144.00 i
Quan*
Unit Price Fact°
TOW
Quantity
Quantity Unit Price Factor
NPP Instaliatdaon
8,206.00
5.54 X 1.00W
34,144.00
Plumbing fopoof%a maker with In-line fHW.
3 90 00 40 26 LF Polyurea Joint Filler
8 01352 0006 HR CarpenterNote: Tasks in the CTC include appropriate costs to cover labor.
$334.73
$2,015:00 d
Quantity
UnitPrkw Factor
Total
Quantity Unit Price Factor
NPP lnataiiatiorr
500.00 x
4.03 x 1.Oo00
2,015.(10
Modifying existing countertop/Cabinet
4 90 00 00,27 l=A Stainless Stee4Coun6ertcp with
Integral Sink and 1 1/2" plywood Substrata
44,542.25
Quantity
Unit Price Factor
Total
NPP (netallaticrr
4.00 x
a
4,542.25 )r 1,0000
4,542.25
Subtotal for No Section Input $66,341.15
01 - General Requirements
5 01000 0012 SY Mohawk 26-30oz Nylon} Loop Carpaft $10,245.24' i
QuanUnit Price Factor Total
NPP InatalWibn Quantity Unit
x 34.38 x 1,0000 10,245.24
i
6 01 22 20 OG 0055 HR Maintenance ElecKdan, With Truck And ToolsThis laakw l be used g,gg
Speclficallyfor maintenance service calls.
Quan* Unit Prlcs Factor
IuPP
3.00 x' 61.22 x 1.280 a
Elec kkxd for Break room sink
Total
229.59
—Installatkm
7 01 22, 20 00 0058 HR Maintenance Plumber With Truck And TodsThlz task wN be used spedlkx;ilyr
5230.49
for maintenance service calfs.
Quantity
Quantity Unit Price Factor
Total
NPP installationx 63.06 x 1.2.501 a
236.49
Plumbing fopoof%a maker with In-line fHW.
8 01352 0006 HR CarpenterNote: Tasks in the CTC include appropriate costs to cover labor.
$334.73
These tasks will be requested specifically by the owner for miscellaneous work
not covered in the CTC.
Quantity Unit Price Factor
Total
Installation 800 x 33.47 x 1.2501
334.73
Modifying existing countertop/Cabinet
Contractor's Price Proposal - Detail Page 1 of 4
EZ/QC - Buy Board 10/2/2013
Contractor's Price Proposal - Detail Continues..
Work Order Number: 011295.02
Work Order Title: Lubbock- Fire Training Flooring_ Bomanite
12 01560 0003
Sect
Item Modifer
UOM Description
$2,875.23
SF Travertine Pattern Vinyl Composition Tile 1/8" Thick
Quantity Unit Price
Line Total
Labor
Equip.
Material (Excluded if marked with an X)
Installation 10,000.00 x 0.23 x
1.2501
2,875.23
1,180.51
01 - General Requirements
Demolition 8,180.00 x 0.45 x 1.2501 =
$15,165.13
03 - Concrete
17 09850 0037
9
01510
0010
EA Any Size Dumpster
SF 3/4" Thick Self Leveling Underlayment For Concrete Floors Including Surface
Total
$840.07
$312.53
Preparation
5682
Quantity
Unit Price
Factor
Total
Total
carpet placement. Not to be used in conjunction with demolition tasks
Installation 175.00 x 3.84 x
Installation 5.00 x
50.00 x
1.2501
312.53
10
01510
0011
EA Dumpster In/Out Fee
Installation 10,790.00 x 0.38 x 1.2501
5,125.86
$781.31
14 08210 0215
EA Remove And Reinstall Wood Door
Quantity
Unit Price
Factor
Total
Factor
Total
10/2/2013
Installation 5.00 x
125.00 x
1.2501
781.31
Subtotal for 08 - Openings
11
01510
0012
EA Dumpster Daily Fee
09 - Finishes
$150.01
15 09250 0048
SF Tape, Spackle And Finish Drywall Walls Up To 10' Height
Quantity
Unit Price
Factor
Total
Quantity Unit Price
Factor
Total
Installation 60.00 x
2.00 x
1.2501 -
150.01
12 01560 0003
SF 6 Mil Plastic Sheeting, Applied To Walls Or Ceilings
$2,875.23
SF Travertine Pattern Vinyl Composition Tile 1/8" Thick
Quantity Unit Price
Factor
Total
Quantity Unit Price Factor
Total
Installation 10,000.00 x 0.23 x
1.2501
2,875.23
1,180.51
Subtotal for 01 - General Requirements
Demolition 8,180.00 x 0.45 x 1.2501 =
$15,165.13
03 - Concrete
17 09850 0037
LF Vinyl Floor Tile Reducer Strip, Black Or Brown
$5682
13 03540 0005
SF 3/4" Thick Self Leveling Underlayment For Concrete Floors Including Surface
Total
$840.07
Preparation
5682
18 09650 0040
SF Remove Glue From Concrete FloorNote: For removal of glue from VCT or
Quantity Unit Price
Factor
Total
carpet placement. Not to be used in conjunction with demolition tasks
Installation 175.00 x 3.84 x
1.2501
840.07
Subtotal for 03 - Concrete
Quantity Unit Price Factor
Total
$840.07
08 - Openings
Installation 10,790.00 x 0.38 x 1.2501
5,125.86
14 08210 0215
EA Remove And Reinstall Wood Door
Contractor's Price Proposal - Detail
$328.40
Quantity Unit Price
Factor
Total
10/2/2013
Installation 7.00 x 37.30 x
1.2501
326.40
Subtotal for 08 - Openings
$326.40
09 - Finishes
15 09250 0048
SF Tape, Spackle And Finish Drywall Walls Up To 10' Height
$508.29
Quantity Unit Price
Factor
Total
Installation 1,500.00 x 0.27 x
1.2501
506.29
For holes in all areas.
16 09650 0025
SF Travertine Pattern Vinyl Composition Tile 1/8" Thick
$5,762.12
Quantity Unit Price Factor
Total
Installation 481.00 x 1.93 x 1.2501
1,180.51
Demolition 8,180.00 x 0.45 x 1.2501 =
4,801.82
17 09850 0037
LF Vinyl Floor Tile Reducer Strip, Black Or Brown
$5682
Quantity Unit Price Factor
Total
Installation 45.00 x 1.01 x 1.2501 =
5682
18 09650 0040
SF Remove Glue From Concrete FloorNote: For removal of glue from VCT or
$5,12566
carpet placement. Not to be used in conjunction with demolition tasks
associated with floor file installation.
Quantity Unit Price Factor
Total
Installation 10,790.00 x 0.38 x 1.2501
5,125.86
Contractor's Price Proposal - Detail
Page 2 of 4
EZ/QC - Buy Board
10/2/2013
Contractor's Price Proposal - Detail Continues..
Work Order Number: 011295.02
Work Order Title: Lubbock- Fire Training Flooring_ Bomanite
Sect Item Modifer UOM Description Line Total
Labor Equip. Material (Excluded If marked with an X)
09 - Finishes
19
09650
0049
LF 4" High 1/8" Rubber Base, Group 2 All (Except White)
Installation 100 x 2519 x 12501 =
$8,094.24
EA 1/2 HP Insulated Garbage Disposal (GE GFC520F)
$27.85
Replacement
Quantity Unit Price Factor
Total
Quantity Unit Price
Factor
Total
Installation 2,500.00 x 1.50 x 1.2501
4,687.88
1.2501
173.94
Subtotal for 11 - Equipment
Demolition 2,500.00 x 0.45 x 1.2501 =
1,406.36
20
09880
0027
SY 28 Ounce, Medium Traffic, Non-Pattemed, Nylon Broadloom Carpet
$924.45
27 15451 0212
EA 3/8" To 1/2" Compression Shut -of Valve Replacement With 15" Polybutylene
Quantity Unit Price Factor
Total
Supply Tube
Installation 0.00 x 24.85 x 1.2501 =
0.00
Factor
Total
Demolition 290.00 x 2.55 x 1.2501 =
924.45
55.18
21
09920
0084
SF Paint Interior Plaster/Drywall, 2 Coats Paint, Brush/Roller Work
$15,572.18
Quantity Unit Price Factor
Total
Installation 24,425.00 x 0.51 x 1.2501
15,572.18
22
09MOD
0084 0321
For Quantities > 10000 To 20000, Deduct
-$2,442.70
Quantity Unit Price Factor
Total
Installation 24,425.00 x -0.08 x 1.2501 =
-2,442.70
23
09920
0248
LF Paint Interior Metal Frame And Trim, 2 Coats Paint, Brush/Roller Work
$888.82
Quantity Unit Price Factor
Total
Installation 900.00 x 0.79 x 1.2501 =
888.82
24
09930
0011
EA One Coat Shellac, Varnish Or Polyurethane Wood Door (Per Face)
$814.44
Quantity Unit Price Factor
Total
Installation 50.00 x 13.03 x 1.2501
814.44
25
09945
0022
SF Hand Scraping And Sanding Of Metal
$564.98
Quantity Unit Price Factor
Total
Installation 1,965.00 x 0.23 x 1,2501 -
564.98
Subtotal for 09 - Finishes
$33,867.30
11 - Equipment
$31.49
Quantity Unit Price Factor
Total
Installation 100 x 2519 x 12501 =
26 11910 0082
EA 1/2 HP Insulated Garbage Disposal (GE GFC520F)
$27.85
Replacement
$173.94
Quantity Unit Price Factor
Quantity Unit Price
Factor
Total
Installation 1.00 x 139.14 x
1.2501
173.94
Subtotal for 11 - Equipment
$173.94
15 - Mechanical
27 15451 0212
EA 3/8" To 1/2" Compression Shut -of Valve Replacement With 15" Polybutylene
$55.18
Supply Tube
Quantity Unit Price
Factor
Total
Installation 2.00 x 22.07 x
1.2501 =
55.18
28 15451 0215 EA Double Bowl Sink/Lavatory Drain Line Replacement
$31.49
Quantity Unit Price Factor
Total
Installation 100 x 2519 x 12501 =
3149
29 15451 0216 EA Braided Stainless Steel, Compression x FIP, Supply Lines To Sink/Lavatory
$27.85
Replacement
Quantity Unit Price Factor
Total
Installation 2.00 x 11.14 x 12501 =
2785
Contractor's Price Proposal - Detail Page 3 of 4
EZ/QC - Buy Board 10/2/2013
Contractor's Price Proposal - Detail Continues..
Work Order Number: 011295.02
Work Order Title: Lubbock- Fire Training Flooring_ Bomanite
Sect. Item Modifer UOM Description Line Total
Labor Equip. Material (Excluded if marked with an X)
15 - Mechanical
30 15451 0280 EA Top Cast Kitchen Faucet With Spray, Single Handle, Chrome Finish, Delta $159.51
440 -WF
Quantity Unit Price Factor Total
Installation 100 x 127.60 x 1.2501 159.51
Subtotal for 15 - Mechanical
$274.03
Proposal Total $116,988.02
This total represents the correct total for the proposal. Any discrepancy between line totals,
sub -totals and the proposal total is due to rounding.
The Percentage of NPP on this Proposal: 65.86%
Contractor's Price Proposal - Detail Page 4 of 4
EZIQC - Buy Board 10/2/2013
Work Order Signature Document
BUYBOARD EZIQC Contract No.; Area I -1 MCP - Option 1
❑ New Work Order FX I Modify an Existing Work Order
Work Order Number: 011292.01 Work Order Date:
Work Order Title: Lubbock- FS#2 - Bomanite Option
Owner Name: City of Lubbock Contractor Name: Minnix Commercial Partners, LTD
Contact: Rodney Unrein Contact: Keenan Davis
Phone: 806 775-2726 Phone: (806) 798-7335
Work to be Performed
Work to be performed as per the Final Detailed Scope of Work Attached and as per the terms and conditions of
BuyBoard EZIQC Contract No Area I - 1 MCP - Option 1.
Brief Work Order Description:
FS#2 Bomanite Option.
Time of Performance See Schedule Section of the Detailed Scope of Work
Liquidated Damages Will apply: 191 Will not apply:
Work Order Firm Fixed Price: $44,276.22
Owner Purchase Order Number:
Owner I\ -
Contractor Date
Work Order Signature Document Page 1 of 1
EZIQC - Buy Board 10/2/2013
WBoard®
oapn►nf/re Purchssinp
Detailed Scope of Work
To: Keenan Davis
From: Rodney Unrein
Minnix Commercial
Partners, LTD
City of Lubbock
PO Box 64895
1625 13th St
Lubbock, TX 79464
Lubbock, TX 79401
(806) 798-7335
806 775-2726
Date Printed:
October 02, 2013
Work Order Number:
011292.01
Work Order Title:
Lubbock- FS#2 - Bomanite Option
Brief Scope:
FS#2 Bomanite Option.
ti
THE GORDIA-C
N GROUP
F]Preliminary FIRevised FX Final
The following items detail the scope of work as discussed at the site. All requirements necessary to accomplish the
items set forth below shall be considered part of this scope of work.
Minnix Commercial Partners proposes the following work to be performed at FS #2:
Removal existing flooring and base.
Bomanite Diamond Polished flooring in all areas except restrooms,bay, and dorm rooms.
Install new carpet tiles in dorm rooms with transition strips.
Demo laminate countertop and replace with stainless steel with integral double bowl sink.
Paint all walls, frames, and wipe down wood doors. Excluding Bay area.
Install disposal.
Install new stops, drain lines, and supply lines.
,d- 7-%
Date
MI -4(3
ate
Scope of Work Page 1 of 1
EZ10C - Buy Board 10/2/2013
Contractor's Price Proposal CSI - Summary
Date: October 02, 2013
Re: IQC Master Contract M
Area I - 1 MCP - Option 1
Work Order*
011292.01
Owner PO M
Title:
Lubbock- FS#2 - Bomanite Option
Contractor:
Minnix Commercial Partners, LTD
Proposal Value:
$44,276.22
No Section Input
$20,301.05
01 - General Requirements
$550.05
06 - Wood, Plastic, and Composites $480.04
08 - Openings $373.03
09 - Finishes $22,046.85
11 - Equipment $292.59
15 - Mechanical $232.61
Proposal Total $44,276.22
The Percentage of NPP on this Proposal: 45.86%
Contractor's Price Proposal - Summary Page 1 of 1
EZ/QC - Buy Board 10/2/2013
Contractor's Price Proposal CSI - Detail
Date: October 02, 2013
LF Patyurea Joint Fitler
Re: IQC Master Contract #:
Area I -1 MCP - Option 1
Work Order*
011292.01
Owner PO #:
Title:
Lubbock- FS#2 - Bomanite Option
Contractor:
Minnix Commercial Partners, LTD
Proposal Value:
$44,27e.22
Sect. Item Modlfer UOM Description Line Total
Labor Equip. Material (Excluded if marked with an X)
No Section Input
1 W W 00 25 SF SomanRsDiamond Polished Concrete wkh Level 11 Fini'�{1s (1500 ariCj $11,086.00
Quay" Unit Prion Factor TOW
NPP" Insltallgtion 2,01200 x 5.50 x 1~.01)00 11,Oea,00
2 9000 0026
LF Patyurea Joint Fitler
Quantity
Quantity
UOR Prkxr.
Factor
Totat
Nf'P
Installation x
4.03
x
1.0000 a
848.311
3 90: 00 00 28.
EA Stainless Steel Coimlartopa wffh Intergrai Double Bowl Sink and 1 i/2"'
$8,386.75
-.__.__ _
Pfywoaci SObstrafa -
Quantity
Quantity
UM4 Price.
Fact t
TOW
NPP
installation
x'
83881;'75
x
1.0m
a�3tta7a
Subtotal for No Section Input
$20,301.05
01 - General Requirements
4 01510 0010
EA Any Size Dumpster
$125.01
Quantity
Unit Price
Factor
Total
Installation 2.00 x
50.00
x
1.2501
125.01
5 01510 0011
EA Dumpster In/Out Fee
$312.53
Quantity
Unit Price
Factor
Total
Installation 2.00 x
125.00
x
1.2501
312.53
8 01510 0012
EA Dumpster Daily Fee
$112.51
Quantity
Unit Price
Factor
Total
Installation 45.00 x
2.00
x
1.2501
112.51
Subtotal for 01 - General Requirements
$550.05
06 - Wood, Plastic, and Composites
7 06415 0005
LF Plastic Laminated Counter Top Custom Made With BacksplashNote: Up to 26"
$480.04
deep
Quantity
Unit Price
Factor
Total
Installation 0.00 x
26.08
x
1.2501
0.00
Demolition 75.00 x
5.12
x
1.2501 =
480.04
Subtotal for 06 - Wood, Plastic, and Composites
$480.04
08 - Openings
8 08210 0215
EA Remove And Reinstall Wood Door
$37303
Quantity
Unit Price
Factor
Total
Installation 8.00 x
37.30
x
1.2501
373.03
Contractor's Price Proposal - Detail
Page 1 of 3
EZIQC - Buy Boatd
10/2/2013
Contractor's Price Proposal - Detail Continues..
Work Order Number: 011292.01
Work Order Title: Lubbock- FS#2 - Bomanite Option
Sect Item Modifer
UOM Description
Line Total
Labor Equip. Material (Excluded if marked with an X)
Subtotal for 08 - Openings
$373.03
09 - Finishes
9 09650 0017
SF 0.085" Thick, Commercial Grade Sheet Vinyl Flooring, Assorted Colors
$966.95
Quantity Unit Price
Factor
Total
Installation 0.00 x 1.44 x
1.2501 =
0.00
Demolition 2,975.00 x 0.26 x
1.2501 =
96695
10 09650 0037
LF Vinyl Floor Tile Reducer Strip, Black Or Brown
$45.45
Quantity Unit Price
Factor
Total
Installation 36.00 x 1.01 x
1.2501 =
45.45
11 09650 0040
SF Remove Glue From Concrete FloorNote: For removal of glue from VCT or
$1,413.24
carpet placement Not to be used in conjunction with demolition
tasks
associated with floor tie installation.
Quantity Unit Price
Factor
Total
Installation 2,975.00 x 0.38 x
1.2501
1,413.24
12 09650 0049
LF 4" High 1/8" Rubber Base, Group 2 All (Except White)
$1,706.39
Quantity Unit Price
Factor
Total
Installation 700.00 x 1.50 x
1.2501 =
1,312.61
Demolition 700.00 x 0.45 x
1.2501 =
393.78
13 09680 0061
SY 24 Ounce, Patterned, Nylon Carpet Tile
$4,947.81
Quantity Unit Price
Factor
Total
Installation 107.00 x 36.99 x
1.2501 =
4,947.61
14 09910 0225
LF Paint Metal Door Frame And Trim, 2 Coats Paint, Brush/Roller
Work
$167.89
Quantity Unit Price
Factor
Total
Installation 170.00 x 0.79 x
1.2501 =
167.89
15 09920 0060
SF Paint Interior Plaster/Drywall, 2 Coats Paint, Brush
$12,538.50
Quantity Unit Price
Factor
Total
Installation 17,000.00 x 0.59 x
1.2501 =
12,538.50
16 09930 0011
EA One Coat Shellac, Varnish Or Polyurethane Wood Door (Per Face)
$260.62
Quantity Unit Price
Factor
Total
Installation 18.00 x 13.03 x
1.2501
260.62
Subtotal for 09 - Finishes
$22,046.85
11 - Equipment
17 11910 0063
EA 3/4 HP Insulated Garbage Disposal (GE GFC720F)
$213.38
Quantity Unit Price
Factor
Total
Installation 1.00 x 170.69 x
1.2501 =
213.38
18 11910 0087
EA Remove And Reinstall Stove/Range
$79.21
Quantity Unit Price
Factor
Total
Installation 1.00 x 6338 x
1.2501
79.21
Subtotal for 11 -Equipment
$292.59
15 - Mechanical
Contractor's Price Proposal - Detail
Page 2 of 3
EZ/QC - Buy Board
10/2/2013
Contractor's Price Proposal - Detail Continues..
Work Order Number: 011292.01
Work Order Title:
Lubbock- FS#2 - Bomanite Option
Sect
Item
Modifer UOM Description
Line Total
Labor Equip.
Material
(Excluded if marked with an X)
15 - Mechanical
19 15451
0182
EA 33"x22"x8" Stainless Steel Kitchen Sink, Double Bowl, 18 Gauge (Elkay
$39.84
LR3322)
Quantity Unit Price
Factor
Total
Installation 0.00 x 952.41 x
1.2501
0.00
Demolition 1.00 x 31.87 x
1.2501 =
39.84
20 15451
0212
EA 3/8" To 1/2" Compression Shut-off Valve Replacement With 15" Polybutylene
$55.18
Supply Tube
Quantity Unit Price
Factor
Total
Installation 2.00 x 22.07 x
1.2501
55.18
21 15451
0215
EA Double Bowl Sink/Lavatory Drain Line Replacement
$31.49
Quantity Unit Price
Factor
Total
Installation 100 x 2519 x
1.2501
31.49
22 15451
0218
EA Braided Stainless Steel, Compression x FIP, Supply Lines To Sink/Lavatory
$27.85
Replacement
Quantity Unit Price
Factor
Total
Installation 2.00 x 11.14 x
1.2501
27.85
23 15451
0222
EA Sink Basket Strainer Replacement
$31.70
Quantity
Quantity Unit Price
Factor
Total
Installation
00 x 12,88 x
1.2501
31.70
24 15451
0282
EA Top Cast Kitchen Faucet With Spray, Single Handle, Stainless Steel Flnish,
$48.55
Delta Brilliance 440 -SSWF
Quantity Unit Price
Factor
Total
X
Installation 1.00 x 22.35 x
1.2501 =
27.94
X
Demolition 1.00 x 14.89 x
1.2501 =
18.81
Subtotal for 15 - Mechanical
$232.61
Proposal Total $44,276.22
This total represents the correct total for the proposal. Any discrepancy between line totals,
sub -totals and the proposal total is due to rounding.
The Percentage of NPP on this Proposal: 45.85%
Contractors Price Proposal - Detail Page 3 of 3
EZ/QC - Buy Board 10/2/2013