RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock is hereby authorized and directed to
execute for and on behalf of the City of Lubbock, Amendment No. 1 to that certain
Contract No. 10513 dated July 12, 2012 for professional services related to the
construction of Fire Station 19, by and between the City of Lubbock and Wiginton
Hooker Jeffry, P.C. - Architects of Plano, Texas, and related documents. Said
Amendment is attached hereto and incorporated in this resolution as if fully set forth
herein and shall be included in the minutes of the City Council.
Passed by the City Council on January 31, 2013
GL CRR SON, MAYOR
ATTEST-
kebe Garza, City Secretar
APPROVED AS TO CONTENT:
1� JI) 61
Wesley D. Everett, Director of Facilities
APPROVED AS TO FORM:
Chad Weav r, Assistant City Attorney
vwxcdocsiRES,Amend t:l Contract-Wiginton Hooker
January 15, 2013
Resolution No. 2013—R0043
Amendment 1
To Agreement Between
The City of Lubbock, TX
and
Wiginton Hooker Jeffry, P.C. Architects
THIS IS AN AMENDMENT TO THE AGREEMENT dated and entered into the 31St day of January
2013 by and between the City of Lubbock ("City") and Wiginton Hooker Jeffry, P.C. Architects
("WHJA") 500 North Central Expressway, Suite 300, Plano, Texas 75074.
WHJA has entered into the agreement with the City for providing professional services relating to the
design, plans, specifications, and estimates of the construction of Fire Station 19, located at 5826 98`h
Street, Lubbock, Texas. The original Agreement was approved by City Council on July 12, 2012,
Resolution No. 2012-RO274.
This amendment includes work associated with the additional professional services associated with the
project scope and an additional alternative storage/CPAT Building, as stated in Attachments A and B,
attached hereto.
This amendment increases the original amount by $45,000. The amendment also includes an additional
seventy-five (75) days from the expiration date of the original Agreement.
All other portions of the original Agreement and previous Amendments shall remain in place and are not
altered by this amendment.
IN WITNESS HEREOF, the parties have executed this Agreement as of this 3151 day of January.
2013.
CI:Zw�_
Gle. Robe o
Ma or
Wiginto ooker Je C. -Architects
Lance Melton, A14, L ED AP
Vice President
ATTEST:
_ APPROV D AS KO :T:
Rebecica. Garza, City Secretary Wes Everett, Director Facilities Management
AP D AS -XO FORM:
City Attorney's Office
ATTACHMENT A
WIGINTON HOOKER 1EFFRY,PC ARCHITECTS
500 N. Central Expressway Suite 300 Plano, Texas 75074 ph 972.665.0657 fx 972.665.0656 www.whiarch.com
January 2, 2013
Wesley Everett
Director of Facilities Management
City of Lubbock
1625 13th Street
Lubbock, TX 79401
via email
weverett@mail.ci.lubbock.tx.us
Re: Fire Station #19 - A/E Additional Services for Increased Project Scope
Mr. Everett:
We have enjoyed working with you, George Lisenbe, Chief Kemp and the rest of the Fire
Administration through the schematic design process. The time spent to date has proven critical for you
and the fire department leadership to properly determine your needs. Though the requested, submitted,
and approved schematic design exceeded the original contract agreement, it became evident that it was
needed to meet the department function at this new facility for now and many years to come.
The following outlines the additional services delivered to date for the Lubbock Fire Station #19. Per
articles 1.1 and 4.3.1.1 of the prime agreement executed on July 12, 2012, the following adjustments to
the agreed upon scope have been requested by fire administration with support from you and George.
1. Increase building gross square footage from 10,000 (ref. article 1.1) to 12,130. This increase
includes an added training room, adjustments to accommodate the dive team functions, and
facility space adjustments for compliance with the new accessibility code (ADA). After many
site -adapt station designs were reviewed and considered, the resultant effort created a new
unique station design (ref. article 1.1) in plan and exterior aesthetic specific to the Lubbock Fire
Department needs.
2. Due to the adjustments of scope, the project delivery per Part II, shall be adjusted by 75 days.
The additional service negotiated with you and Chief Kemp for this increased scope is $25,000.
Please sign below and we continue with the design as requested. Again, thank you very much for the
opportunity to serve you.
Sincerely,
Wiginton Hooker Jeffry, P.C. — Architects
Lance Melton, AIA, LEED AP
Vice President
ATTACHMENT B
WIGINTON HOOKER JEFFRY,PC A R C H IT E CTS
500 N Central Expressway Suite 300 Plano. Texas 75074 ph 972.665.0657 1x 972.665.0656 www.whjarch.com
January 4, 2013
Wesley Everett
Director of Facilities Management
City of Lubbock
1625 13th Street
Lubbock, TX 79401
via email
weverett@mail.ci.lubbock.tx.us
Re: Fire Station #19 - A/E Additional Services for Add Alternate Storage / CPAT Building
Mr. Everett:
Per the collective request of Chief Kemp, George Lisenbe, and yourself, please accept and approve the
following additional A/E services per article 4.3.1.6 of the contract.
The requested add alternate for the A/E team to include in our design and construction documents to be
part of the bid packaged along with the original scope of the project.
1. New 40'x80' Storage / CPAT Building
2. Located on the Fire Station 19 site as indicated on the approved schematic design submission.
3. Match construction type (including foundation design), roof and fenestration of fire station
4. 14 feet tall eve walls
5. 3 — 12 feet tall and wide standard overheard doors (no high speed necessary) on 80' side of
building.
6. 1 — 3'-6"x7' man door located on south wall closer to west side.
7. No interior partitions / rooms
8. No Air Conditioning
9. Radiant Heat
10. Additional site paving as needed for vehicular access to overhead doors on east side of building
and walking access to south end man door.
11. The geotechnical investigation report results and recommendations for the main fire station
building will be used for this storage building.
12. Provide mechanically assisted natural ventilation (either large ceiling fans or exhaust fans with
manual controls).
The construction budget for the project will need to be increased accordingly.
The additional service negotiated with you and Chief Kemp for this increased scope is $20,000.
Please sign below and we continue with the design as requested.
Sincerely,
Wiginton Hooker Jeffry, P.C. — Architects
Lance Melton, AIA, LEED AP