HomeMy WebLinkAboutResolution - 2014-R0321 - Adopt LP&L Rate Schedule - 09/11/2014RESOLUTION
WHEREAS, Lubbock Power & Light is the municipally owned public
power utility of the City of Lubbock;
WHEREAS, the Electric Utility Board has approved an electric rate
schedule for Lubbock Power & Light pursuant to § 2.03.415(a) of the Code of
Ordinances of the City of Lubbock;
WHEREAS, § 2.03.415(a) of the Code of Ordinances of the City of
Lubbock requires that the electric rate schedule of Lubbock Power & Light be
approved by the City Council prior to its adoption; NOW THEREFORE:
BE IT RESOLVED BY THE ELECTRIC UTILITY BOARD OF THE CITY OF
LUBBOCK:
THAT Lubbock Power & Light's electric rate schedule, as attached
hereto, be approved and adopted with an effective date of October 1, 2014.
Passed by the City Council on the 11th day of September, 2014.
GL N C. ROBERTSON, MAYOR
ATTEST:
PA,O-�
Bec Garza, City Secret
APPROVED AS TO CONTENT:
David Mc Calla, Interim CEO,
Lubbock Power & Light
APPROVED AS TO FORM:
Todd Kimbrough, General Counsel,
Lubbock Power & Light
C1
Lubbock Power & Light
Aie aider is 9 -mm
Electric Rate/Tariff Schedule
Amended October 1, 2014
Page 12
Lubbock Power & Light Electric Rate/Tariff Schedule
Service Schedules
Type of Service Rate Class
General Terms and Conditions
Residential Standard Service
Rate 1
Residential Electric Space Heating Service
Rate 3
Residential Net Metering Service
Rate 5
Small General Service
Rate 10
Large School Service
Rate 15
Secondary General Service
Rate 16
Primary General Service
Rate 16P
Transmission General Service
Rate 16T
State University General Service
Rate 16U
Large Municipal Service
Rate 17
Street Lighting Service
Rate 18
General Religious Service
Rate 19
Small Municipal & School Service
Rate 21
Guard Light Service
Flood Light Service
Miscellaneous Service Charges
Discount Factor
Purchased Power Cost Recovery Factor
Rate/Tariff Schedule Rev: 12/01/2013
GENERAL TERMS AND CONDITIONS
Page 13
In order that all Customers may receive uniform, efficient, and adequate service, electric
service will be supplied to and accepted by all Customers receiving service from the City of
Lubbock's municipally owned electric utility, Lubbock Power & Light ("LP&L"), in accordance
with these Terms and Conditions including the attached Rate/Tariff Schedule ("Rate Schedule").
For purposes of this Rate Schedule, "Customer" shall mean any person, firm, corporation or
other legal entity receiving electric service from Lubbock Power & Light. All references herein
to either the City of Lubbock or Lubbock Power and Light shall be inclusive of the other.
1. Customer's Installation. Customer is responsible, at its own expense, for installing and
maintaining such protective devices as are recommended or required by the then current
edition of the National Electrical Code or as may be necessary to protect Customer's
equipment or process during abnormal service conditions or the failure of all or a part of
the electric service provided by LP&L. Such protective devices include, but are not
limited to, equipment necessary to limit voltage fluctuations, transients, or harmonics
such that neither LP&L nor LP&L's other customers are adversely affected. All wiring
and other electrical equipment furnished by the Customer will be installed, operated, and
maintained by the Customer at all times in conformity with good electrical practice and
with the requirements of the constituted authorities and these Terms and Conditions.
LP&L is not obligated to serve any equipment or any premises that has a detrimental
effect on LP&L equipment or the equipment of LP&L customers.
Customer is responsible for notifying LP&L of any change in the installation that might
impact the applicable rate to be charged. If the change results in the Customer qualifying
for a lower rate, the lower rate will be applied no earlier than the date notice is given to
LP&L. If the change results in a higher rate, the higher rate will be applied as of the date
of the change in installation. Back -billing shall not exceed a period of six months, if it is
found that a higher rate should have been applied to Customer or the back -billing would
result in additional charges or fees to Customer.
2. Continuous Service. Lubbock Power & Light shall use reasonable diligence to provide
continuous electric service but Lubbock Power & Light does not guarantee against
irregularities, interruptions, or fluctuating wave form or frequency, it being understood
that occasional irregularities, interruptions, and fluctuations are inevitable. Lubbock
Power & Light shall not be liable for damages or injury, including but not limited to
consequential or economic loss damages, occasioned by interruption, failure to
commence delivery voltage, wave form or frequency fluctuation caused by an act of God
or the public enemy, a breakdown of plant, lines or equipment, inevitable accidents, fire,
explosion, strikes, riots, war, delay in receiving shipments of required materials, order of
any court or judge granted in any bona fide adverse legal proceedings or action or any
order by any commission or tribunal having jurisdiction; OR, WITHOUT
LIMITATION BY THE PRECEDING ENUMERATION, ANY OTHER ACT OR
THING DUE TO CAUSES BEYOND LUBBOCK POWER & LIGHT'S
Terms & Conditions Rev: 10!012014
Page 14
CONTROL, TO THE NEGLIGENCE OF LUBBOCK POWER & LIGHT, ITS
EMPLOYEES, OR CONTRACTORS, except to the extent that the damages are
occasioned by the gross negligence or willful misconduct of Lubbock Power & Light.
3. Intentional Interruption of Service. Lubbock Power & Light may, without notice and
without liability to the Customer, interrupt service to the Customer when, in Lubbock
Power & Light's sole judgment, the interruption of service:
a. Will prevent or alleviate an emergency threatening to disrupt the operation
of Lubbock Power & Light's system; or
b. Will lessen or remove possible danger to life or property; or
C. Will aid in the restoration of electric service; or
d. Is required to make necessary repairs to or changes in Lubbock Power &
Light's facilities.
Lubbock Power & Light may, in the event of a national emergency or local disaster
resulting in disruption of normal service, in the public interest, interrupt service to the
Customer to provide necessary service to civil defense or other emergency service
agencies on a temporary basis until normal service to the agencies can be restored.
4. Disclaimer of Warranties. LUBBOCK POWER & LIGHT AND THE CITY MAKES
NO WARRANTIES WHATSOEVER WITH REGARD TO THE PROVISION OF
ANY SERVICE AND DISCLAIMS ANY AND ALL WARRANTIES, EXPRESSED
OR IMPLIED, INCLUDING BUT NOT LIMITED TO WARRANTIES OF
MERCHANTABILITY AND FITNESS FOR A PARTICULAR PURPOSE.
5. Discontinuance. Suspension and Refusal of Service. In addition to and in conjunction
with any other federal, state or local law regarding discontinuance, suspension or refusal
of utility service, Lubbock Power & Light may discontinue, suspend or refuse to supply
electric service to any customer for the following reasons:
a. Disconnection with notice. Lubbock Power & Light may disconnect electric
utility service after proper notice for any of the following reasons:
(i) failure to pay a bill for electric utility service or failure to comply with the
terms of any agreed payment plan;
(ii) failure to pay a deposit as required by the General Terms and Conditions
of the Rate Schedule; or
(iii) for any other reason whereby Lubbock Power & Light is legally entitled to
disconnect electric utility service with notice.
b. Disconnection without notice. Lubbock Power & Light may disconnect electric
utility service without prior notice for any of the following reasons:
(i) where a known dangerous condition exists for as long as the condition
exists;
(ii) where service is connected without authority by a person who has not
made application for service;
(iii) where service was reconnected without authority after termination for
nonpayment;
Terms & Conditions Rev: 10 012014
i5
(iv) failure to comply with the terms of any agreed payment plan where such
plan provides for disconnection without further notice;
(v) where there has been tampering with Lubbock Power & Light's equipment
or evidence of theft of service; or
(vi) for any other reason whereby Lubbock Power & Light is legally entitled to
disconnect electric utility service without notice.
6. Deposits. Lubbock Power & Light shall require a deposit from customers for electric
service, in accordance with the following terms and conditions:
a. Lubbock Power & Light shall require a deposit from a prospective residential
electric service customer in an amount equal to ONE HUNDRED THIRTY FIVE
AND NO/100 DOLLARS ($135.00), except as provided herein.
b. Lubbock Power & Light shall require a deposit from a prospective commercial
and/or industrial customer in an amount equal to ONE HUNDRED THIRTY
FIVE AND NO/100 DOLLARS ($135.00) or ONE-SIXTH (1/6) of the
reasonable and good -faith estimate of annual billings of the customer, whichever
is greater, except as provided herein. '
c. An applicant for residential electric service shall be exempt from the deposit
requirement if any of the following conditions are met by the applicant:
i. the applicant produces, to the satisfaction of Lubbock Power & Light, the
following information:
A. Proof that during the two years prior to applying for electric service
from Lubbock Power & Light, the applicant was a customer of a utility
providing electric service or one or more of the City of Lubbock utility
services for at least twelve (12) consecutive months; and
B. While a customer, the applicant was not delinquent in paying for any
utility service including City of Lubbock utility services on more than
one occasion; and
C. While a customer, the applicant never had any of the services
described in paragraphs A or B immediately above disconnected for
nonpayment;
ii. the applicant demonstrates adequate and available credit, to the
satisfaction of Lubbock Power & Light, by producing a letter of credit in
the primary applicant's name from a utility providing electric service of
whom the applicant was a customer; or
iii. the applicant is at least sixty-five (65) years of age and has no outstanding
account balance with a utility for utility service including City of Lubbock
utility services that accrued within the last two years.
iv. Subject to Section 6(c)(i)(B) and Section 6(c)(i)(C), an applicant has been
determined to be a victim of family violence as defined in the Texas
Terms & Conditions Rev: 10/01/2014
1' . _ 16
Family Code §71.004, by a family violence center as defined in Texas
Human Resources Code §51.002, by treating medical personnel, by law
enforcement personnel, by the Office of a Texas District Attorney or
County Attorney, by the Office of the Attorney General, or by a grantee of
the Texas Equal Access to Justice Foundation. This determination shall be
evidenced by submission of a certification letter developed by the Texas
Council on Family Violence. The certification letter may be submitted
directly to Lubbock Power & Light.
v. A customer who was exempted from the deposit requirement under this
Section 6(c) may have the exemption withdrawn and a deposit applied to
the account if the customer's service becomes disconnected for non-
payment.
d. An applicant for non-residential service shall be exempt from the deposit
requirement if the applicant produces, to the satisfaction of Lubbock Power &
Light, the following information:
i. Proof that during the two years prior to applying for electric service from
Lubbock Power & Light, the applicant was a customer of a utility
providing electric service for at least twelve (12) consecutive months and
is not currently delinquent in payment of any such utility service account;
and
11. While a customer, the applicant was not delinquent in paying for any
utility service on more than one occasion; and
iii. While a customer, the applicant never had service disconnected for
nonpayment.
iv. A customer who was exempted from the deposit requirement under this
Section 6(d) may have the exemption withdrawn and a deposit applied to
the account if the customer's service becomes disconnected for non-
payment.
e. Except as provided herein, a customer from whom a deposit has been collected, if
elected by the customer and the customer notifies Lubbock Power & Light, shall
be eligible for a refund of said deposit when the customer has paid bills for
service for twelve (12) consecutive residential billings or for twenty-four (24)
consecutive commercial or industrial billings without having service disconnected
for nonpayment of charges for such service, and without having more than one
occasion on which a bill was delinquent, and when the customer is not delinquent
in the payment of the current bill. Refunds to eligible customers shall be made
promptly either in the form of a check payable to the customer or as a credit to the
customer's bill, as determined by the sole discretion of Lubbock Power & Light.
A customer who received a refund of their deposit may have the deposit
Terms & Conditions Rev: 10/01/2014
Page 17
requirement reapplied if the customer's service becomes disconnected for non-
payment.
f. Lubbock Power & Light shall keep the following records for all deposits collected
by Lubbock Power & Light pursuant to this Section:
i. the name and address of each depositor;
ii. the amount and date of the deposit; and
iii. each transaction concerning the deposit.
g. Any deposit not previously refunded to Customer or credited to Customer's
account as provided herein shall be credited to Customer's final bill for service.
7. Right of Way. Customer shall provide, at no expense to Lubbock Power & Light, valid
easements and rights-of-way, as required by Lubbock Power & Light for installation of
an electric distribution system to provide electric utility service to Customer. Subject to
and in conjunction with all other applicable federal, state and local laws and regulations,
Lubbock Power & Light shall have the right to clear its distribution system and service
connection of any interfering tree, shrub, or other obstruction and shall have the right to
determine and maintain the amount of clearance it deems necessary in accordance with
good utility practices and applicable law.
Access to Premises. Lubbock Power & Light or its authorized agents shall have access at
all reasonable hours to the premises of Customer for the purpose of inspecting wiring and
apparatus, removing or replacing Lubbock Power & Light's property, reading of meters
and all other purposes incident to supplying of electric utility service.
9. Voltage Tolerances. Lubbock Power & Light may measure and record voltage levels at
Customer's billing meter. Voltages outside of the Acceptable Range, as defined below,
will be corrected as soon as possible by Lubbock Power & Light. For purposes of this
Rate Schedule, voltages within the Acceptable Range shall be deemed consistent with
proper electric utility service and good utility practice.
Nominal Voltage
(Volts)
Acceptable Range
(Volts)
120
110-127
208
191-220
240
220-254
277
254-293
Terms & Conditions Rev: 10,'01"2014
Page 18
480 440-508
10. Agreed Payment Plan. Lubbock Power & Light may allow a customer to pay an
outstanding bill in installments. Any such agreed payment plan shall be subject to the
following ten -ns and conditions:
a. The customer may establish a payment plan by contacting Lubbock Power &
Light in person, by telephone or by any other electronic communication approved
by Lubbock Power & Light;
b. The agreed payment plan must be in writing;
c. The Director of Electric Utilities may include additional terns and conditions
consistent with those outlined herein and with applicable policy and law.
The agreed payment plan may contain additional terms and conditions consistent with the
Rate Schedule and applicable federal, state, and local law and regulations. In the event of
a conflict between a written agreed payment plan and this Rate Schedule, the terms and
conditions of this Rate Schedule shall control.
11. Right to Amend. This Rate Schedule may be amended or modified by Lubbock Power &
Light through a written instrument duly executed by the City Council of the City of
Lubbock without further notice provided to Customer, except as otherwise required by
law.
12. Severability. If any portion of this Rate Schedule is held unenforceable by a court of
competent jurisdiction, the remainder of this Rate Schedule shall not be affected and shall
remain fully in force and enforceable.
13. Meter Aggre ag tion. Lubbock Power & Light will bill each electric meter as a single
meter. Customers with multiple meters that are rendered to a contiguous area, or that are
metered across a dedicated street or alley will be billed on a per meter basis with no
aggregation of those meters for billing purposes.
14. Applicable Law. The laws of the State of Texas shall govern the validity,
performance and enforcement of this Rate Schedule and the venue for any legal
proceedings shall be in Lubbock County, Texas.
Terms & Conditions Rev: 10/01/2014
(9
NJ
RESIDENTIAL STANDARD SERVICE
Rate 1
APPLICABLE: To residential customers for electric service used for domestic
purposes in private residences and separately metered individual
apartments when all service is supplied at one point of delivery and
measured through one meter, where facilities of adequate capacity
and suitable voltage are adjacent to the premises to be served.
Single-phase motors not to exceed 10 horsepower, individual
capacity, may be served under this rate.
ti 4914 I7�`P
RATE:
NON -SUMMER
MONTHS:
SUMMER MONTHS:
Lubbock, Texas
Service Availability Charge:
Summer Energy Charge:
Non -Summer Energy Charge:
$6.87 per month per meter
$0.03431 per kWh
$0.02373 per kWh
The billing months of October through May
The billing months of June through September
PURCHASED POWER The charge per kilowatt-hour of the above rate shall be increased by
COST RECOVERY the applicable recovery factor per kilowatt hour as provided in the
FACTOR: current Lubbock Power and Light "Purchased Power Cost Recovery
Factor".
FRANCHISE FEE The charge of the above rate may be increased (i) by an amount no
EQUIVALENT: greater than the equivalent franchise fee established by the City
Council of the City of Lubbock for any other electric utility; or (ii)
by an amount equal to any franchise fee obligation applicable to
Lubbock Power & Light as established by the City Council of the
City of Lubbock.
TAX: Billings under this schedule may be increased by an amount equal to
the sum of the applicable federal, state and local taxes, fees, or
charges levied, assessed and,. -or payable by Lubbock Power & Light
for utility services rendered, or on the right or privilege or rendering
the service, or on any object or event incidental to the rendition of
the service.
Residential Standard Service Rev: 10 012014
Page 1 10
BUDGET BILLING: Budget billing is available upon request. Budget billing is a
program that allows a customer to pay a specified amount each
month instead of paying the actual billed amount. Customers must
have a minimum of 12 months history at their current address to
qualify for budget billing. Customers must have a zero balance at
the time budget billing is implemented and must keep their accounts
current to remain on budget billing.
TERMS OF PAYMENT: Payment due on receipt. A late charge of 5% will be added to all
bills not paid within 21 days after bill date. If the 21" day falls on a
weekend or an official City of Lubbock recognized holiday, the late
charge will not be applied until the next business day.
CHARACTER OF AC. 60 hertz. Single-phase 120/240 volts. Three-phase 240 volts
SERVICE: where available on secondary.
TERMS & Service supplied under this rate is subject to the terms and
CONDITIONS: conditions set forth in LP&L's General Terms and Conditions of the
Rate Schedule as approved by the City Council of the City of
Lubbock and on file with the City Secretary of the City of Lubbock.
EFFECTIVE DATE: For all electric meters read by LP&L on or after October 1, 2014
Residential Standard Service Rev: 10.:0 1 2014
RESIDENTIAL
ELECTRIC SPACE HEATING SERVICE
Rate 3
X11
APPLICABLE: To residential customers for electric service with predominant
electric space heating used for domestic purposes in private
residences and separately metered individual apartments when all
service is supplied at one point of delivery and measured through
one meter, where facilities of adequate capacity and suitable voltage
are adjacent to the premises to be served. Single-phase motors not
to exceed 10 horsepower, individual capacity, may be served under
this rate. Electric space heating includes permanently installed
whole house space heating equipment in regular use, including heat
pumps and electric resistance heating and excluding bathroom
heaters.
TERRITORY:
V.7V"
NON -SUMMER
MONTHS:
SUMMER MONTHS:
Lubbock, Texas
Service Availability Charge:
Summer Energy Charge:
Non -Summer Energy Charge:
$6.87 per month per meter
$0.04473 per kWh
$0.01301 per kWh
The billing months of October through May
The billing months of June through September
PURCHASED POWER The charge per kilowatt-hour of the above rate shall be increased by
COST RECOVERY the applicable recovery factor per kilowatt hour as provided in the
FACTOR: current Lubbock Power and Light "Purchased Power Cost Recovery
Factor".
FRANCHISE FEE The charge of the above rate may be increased (i) by an amount no
EQUIVALENT: greater than the equivalent franchise fee established by the City
Council of the City of Lubbock for any other electric utility; or (ii)
by an amount equal to any franchise fee obligation applicable to
Lubbock Power & Light as established by the City Council of the
City of Lubbock.
Residential Electric Space Heating Service Rev: 10/01 2014
12
TAX: Billings under this schedule may be increased by an amount equal to
the sum of the applicable federal, state and local taxes, fees, or
charges levied, assessed and/or payable by Lubbock Power & Light
for utility services rendered, or on the right or privilege or rendering
the service, or on any object or event incidental to the rendition of
the service.
BUDGET BILLING: Budget billing is available upon request. Budget billing is a
program that allows a customer to pay a specified amount each
month instead of paying the actual billed amount. Customers must
have a minimum of 12 months history at their current address to
qualify for budget billing. Customers must have a zero balance at
the time budget billing is implemented and must keep their accounts
current to remain on budget billing.
TERMS OF PAYMENT: Payment due on receipt. A late charge of 5% will be added to all
bills not paid within 21 days after bill date. If the 21St day falls on a
weekend or an official City of Lubbock recognized holiday, the late
charge will not be applied until the next business day.
CHARACTER OF AC. 60 hertz. Single-phase 120/240 volts. Three-phase 240 volts
SERVICE: where available on secondary.
TERMS & Service supplied under this rate is subject to the terns and
CONDITIONS: conditions set forth in LP&L's General Terns and Conditions of the
Rate Schedule as approved by the City Council of the City of
Lubbock and on file with the City Secretary of the City of Lubbock.
EFFECTIVE DATE: For all electric meters read by LP&L on or after October 1, 2014
Residential Electric Space Heating Service Rev: 10/01/2014
X13
RESIDENTIAL
NET METERING SERVICE
Rate 5
APPLICABLE: To residential customers for electric service used for domestic
purposes in private residences and separately metered individual
apartments when all service is supplied at one point of delivery and
measured through one meter, where facilities of adequate capacity
and suitable voltage are adjacent to the premises to be served.
Single-phase motors not to exceed 10 horsepower, individual
capacity, may be served under this rate.
This rate is available to net metering customers only. Net metering
customer are defined as customers who have installed distributed
generation on the customer side of the Lubbock Power and Light
meter. All customers desiring to be placed on this rate must sign an
agreement for interconnection and parallel operation with Lubbock
Power and Light. Customers that qualify for this rate will receive
credit in kWh generated against kWh consumed in one billing
period. KWh credits will only offset up to the amount of kWh
consumed in each billing period.
TERRITORY: Lubbock, Texas
RATE: Service Availability Charge: $25.91 per month per meter
Summer Energy Charge: $0.01100 per kWh
Non -Summer Energy Charge: $0.00338 per kWh
NON -SUMMER The billing months of October through May
MONTHS:
SUMMER MONTHS: The billing months of June through September
PURCHASED POWER The charge per kilowatt-hour of the above rate shall be increased by
COST RECOVERY the applicable recovery factor per kilowatt hour as provided in the
FACTOR: current Lubbock Power and Light "Purchased Power Cost Recovery
Factor".
Residential Net Metering Service Rev: 10/0 1/2014
14
FRANCHISE FEE The charge of the above rate may be increased (i) by an amount no
EQUIVALENT: greater than the equivalent franchise fee established by the City
Council of the City of Lubbock for any other electric utility; or (ii)
by an amount equal to any franchise fee obligation applicable to
Lubbock Power & Light as established by the City Council of the
City of Lubbock.
TAX: Billings under this schedule may be increased by an amount equal to
the sum of the applicable federal, state and local taxes, fees, or
charges levied, assessed and/or payable by Lubbock Power & Light
for utility services rendered, or on the right or privilege or rendering
the service, or on any object or event incidental to the rendition of
the service.
BUDGET BILLING: Budget billing is available upon request. Budget billing is a
program that allows a customer to pay a specified amount each
month instead of paying the actual billed amount. Customers must
have a minimum of 12 months history at their current address to
qualify for budget billing. Customers must have a zero balance at
the time budget billing is implemented and must keep their accounts
current to remain on budget billing.
TERMS OF PAYMENT: Payment due on receipt. A late charge of 5% will be added to all
bills not paid within 21 days after bill date. If the 21 st day falls on a
weekend or an official City of Lubbock recognized holiday, the late
charge will not be applied until the next business day.
CHARACTER OF AC. 60 hertz. Single-phase 120/240 volts. Three-phase 240 volts
SERVICE: where available on secondary.
TERMS & Service supplied under this rate is subject to the terms and
CONDITIONS: conditions set forth in LP&L's General Terms and Conditions of the
Rate Schedule as approved by the City Council of the City of
Lubbock and on file with the City Secretary of the City of Lubbock.
EFFECTIVE DATE: For all electric meters read by LP&L on or after October 1, 2014.
Residential Net Metering Service Rev: 1001 2014
SMALL GENERAL SERVICE
Rate 10
115
APPLICABLE: To commercial customers for electric service supplied at secondary
voltage for commercial purposes when all service is supplied at one
point of delivery and measured through one meter, where facilities
of adequate capacity and suitable voltage are adjacent to the
premises to be served, and whose load does not exceed 10 kW of
demand in any month. Single-phase motors not to exceed 10
horsepower, individual capacity, may be served under this rate.
Youth -oriented (18 years of age and younger) non-profit sports
leagues utilizing electric service for sports field lighting at
municipally owned outdoor facilities may be served under this rate
regardless of demand. Meters in which the load exceeds 10 kW of
demand in any month will be assigned to Rate 16 (Secondary
General Service) and will not be eligible to be reassigned to Rate 10
until there have been 12 consecutive months where loads have not
exceeded 10 kW of demand.
Not applicable to temporary, breakdown, standby, supplementary,
resale or shared service.
TERRITORY: Lubbock, Texas
RATE: Service Availability Charge: $11.54 per month per meter
Energy Charge: $0.01692 per kWh
PURCHASED POWER The charge per kilowatt-hour of the above rate shall be increased by
COST RECOVERY the applicable recovery factor per kilowatt hour as provided in the
FACTOR: current Lubbock Power and Light "Purchased Power Cost Recovery
Factor".
FRANCHISE FEE The charge of the above rate may be increased (i) by an amount no
EQUIVALENT: greater than the equivalent franchise fee established by the City
Council of the City of Lubbock for any other electric utility; or (ii)
by an amount equal to any franchise fee obligation applicable to
Lubbock Power & Light as established by the City Council of the
City of Lubbock.
Small General Service Rev: 10/01/2014
X16
TAX: Billings under this schedule may be increased by an amount equal to
the sum of the applicable federal, state and local taxes, fees, or
charges levied, assessed and/or payable by Lubbock Power & Light
for utility services rendered, or on the right or privilege or rendering
the service, or on any object or event incidental to the rendition of
the service.
TERMS OF PAYMENT: Payment due on receipt. A late charge of 5% will be added to all
bills not paid within 21 days after bill date. If the 21" day falls on a
weekend or an official City of Lubbock recognized holiday, the late
charge will not be applied until the next business day.
CHARACTER OF AC. 60 hertz. Single-phase 120/240 volts. Three-phase 240 volts
SERVICE: where available on secondary.
TERMS & Service supplied under this rate is subject to the terms and
CONDITIONS: conditions set forth in LP&L's General Terms and Conditions of the
Rate Schedule as approved by the City Council of the City of '
Lubbock and on file with the City Secretary of the City of Lubbock.
EFFECTIVE DATE: For all electric meters read by LP&L on or after October 1, 2014
Small General Service Rev: 10..,01 2014
LARGE SCHOOL SERVICE
Rate 15
i 17
APPLICABLE: To all public and private school facilities supplied at secondary
voltage for school purposes when all service is supplied at one point
of delivery and measured through one meter, where facilities of
adequate capacity and suitable voltage are adjacent to the premises
to be served and whose load exceeds 10 kW of demand in any
month. Meters on this rate with loads that drop to 10 kW of demand
or below will be eligible to be reassigned to Rate 21 (Small
Municipal and School Service) only after 12 consecutive months
where loads have not exceeded 10 kW of demand.
TERRITORY:
RATE:
Not applicable to temporary, breakdown, standby, supplementary,
resale or shared service, or to service for which a specific rate
schedule is provided.
Lubbock, Texas
Service Availability Charge:
Energy Charge:
Demand Charge:
:533.84 per month per meter
$0.00042 per kWh
$4.91738 per kW
DEMAND: Lubbock Power and Light will furnish at its expense the necessary
inetering equipment to measure the customer's kW demand for the
30 -minute period of greatest use during the month. In the absence
of a demand meter, the customer's demand will be billed using the
monthly kilowatt-hours and an average load factor of 41.30 percent.
In no month, shall the billing demand be greater than the kW value
determined by dividing the kWh sales for the billing period by 80
hours.
PURCHASED POWER The charge per kilowatt-hour of the above rate shall be increased by
COST RECOVERY the applicable recovery factor per kilowatt hour as provided in the
FACTOR: current Lubbock Power and Light "Purchased Power Cost Recovery
Factor".
Large School Service Rev: 10•''01!2014
18
FRANCHISE FEE The charge of the above rate may be increased (i) by an amount no
EQUIVALENT: greater than the equivalent franchise fee established by the City
Council of the City of Lubbock for any other electric utility; or (ii)
by an amount equal to any franchise fee obligation applicable to
Lubbock Power & Light as established by the City Council of the
City of Lubbock.
TAX: Billings under this schedule may be increased by an amount equal to
the sum of the applicable federal, state and local taxes, fees, or
charges levied, assessed and/or payable by Lubbock Power & Light
for utility services rendered, or on the right or privilege or rendering
the service, or on any object or event incidental to the rendition of
the service.
POWER FACTOR: Applicable to customers on this rate schedule with a peak demand of
200 kW or greater. At all times, Customer will maintain at Lubbock
Power & Light's point of delivery, a power factor of not less than
85% lagging.
Where Customer fails to maintain a power factor of at least 85%
lagging at LP&L's point of delivery„ Customer shall install suitable
capacitors or other equipment necessary to raise the overall power
factor at the point of delivery to a satisfactory value. Where such
power factor correction equipment is used, Customer shall install a
relay, switch or other regulating equipment for purposes of
disconnecting or controlling the power factor correction equipment
in order to prevent excessive voltage conditions on Lubbock Power
& Light's system.
Effective October 1, 2015, LP&L may disconnect Customer's
service, following proper notice, if Customer fails to maintain a
power factor of at least 85% lagging. In cases where service is
provided and the customer fails to maintain a power factor of at least
85% lagging, actual KVA shall be used as the billing demand.
TERMS OF PAYMENT: Payment due on receipt. A late charge of 5% will be added to all
bills not paid within 21 days after bill date. If the 215` day falls on a
weekend or an official City of Lubbock recognized holiday, the late
charge will not be applied until the next business day.
CHARACTER OF AC. 60 hertz. Single-phase or three-phase, at one available
SERVICE: standard voltage.
Large School Service Rev: 10!0V2014
Page 119
TERMS & Service supplied under this rate is subject to the teens and
CONDITIONS: conditions set forth in LP&L's General Terms and Conditions of the
Rate Schedule as approved by the City Council of the City of
Lubbock and on file with the City Secretary of the City of Lubbock.
EFFECTIVE DATE: For all electric meters read by LP&L on or after October 1, 2014
Large School Service Rev: 10/01/2014
SECONDARY GENERAL SERVICE
Rate 16
120
APPLICABLE: To all commercial and industrial customers for electric service
supplied at secondary voltage for commercial purposes when all
service is supplied at one point of delivery and measured through
one meter, where facilities of adequate capacity and suitable voltage
are adjacent to the premises to be served and whose load exceeds 10
kW of demand in any month. Meters on this rate with loads that
drop to 10 kW of demand or below will be eligible to be reassigned
to Rate 10 (Small General Service) only after 12 consecutive months
where loads have not exceeded 10 kW of demand.
TERRITORY:
RATE:
NON -SUMMER
MONTHS:
SUMMER MONTHS:
t
Not applicable to temporary, breakdown, standby, supplementary,
resale or shared service.
Lubbock, Texas
Service Availability Charge:
Energy Charge:
Summer Demand Charge:
Non -Summer Demand Charge:
$24.32 per month per meter
$0.00068 per kWh
$6.82088 per kW
$3.64838 per kW
The billing months of October through May
The billing months of June through September
DEMAND: Lubbock Power and Light will furnish at its expense the necessary
metering equipment to measure Customer's kW demand for the 30 -
minute period of greatest use during the month. In the absence of a
demand meter, the customer's demand will be billed using the
monthly kilowatt-hours and an average load factor of 57.01 percent.
In no month, shall the billing demand be greater than the kW value
determined by dividing the kWh sales for the billing period by 80
hours.
PURCHASED POWER The charge per kilowatt-hour of the above rate shall be increased by
COST RECOVERY the applicable recovery factor per kilowatt hour as provided in the
FACTOR: current Lubbock Power and Light "Purchased Power Cost Recovery
Factor".
Secondary General Service Rev: 12 01 '1013
Page 121
FRANCHISE FEE The charge of the above rate may be increased (i) by an amount no
EQUIVALENT: greater than the equivalent franchise fee established by the City
Council of the City of Lubbock for any other electric utility; or (ii)
by an amount equal to any franchise fee obligation applicable to
Lubbock Power & Light as established by the City Council of the
City of Lubbock.
TAX: Billings under this schedule may be increased by an amount equal to
the sum of the applicable federal, state and local taxes, fees, or
charges levied, assessed and/or payable by Lubbock Power & Light
for utility services rendered, or on the right or privilege or rendering
the service, or on any object or event incidental to the rendition of
the service.
POWER FACTOR: Applicable to customers on this rate schedule with a peak demand of
200 kW or greater. At all times, Customer will maintain at Lubbock
Power & Light's point of delivery, a power factor of not less than
85% lagging.
Where Customer fails to maintain a power factor of at least 85%
lagging at LP&L's point of delivery, Customer shall install suitable
capacitors or other equipment necessary to raise the overall power
factor at the point of delivery to a satisfactory value. Where such
power factor correction equipment is used, Customer shall install a
relay, switch or other regulating equipment for purposes of
disconnecting or controlling the power factor correction equipment
in order to prevent excessive voltage conditions on Lubbock Power
& Light's system.
Effective October 1, 2015, LP&L may disconnect Customer's
service, following proper notice, if Customer fails to maintain a
power factor of at least 85% lagging. In cases where service is
provided and the customer fails to maintain a power factor of at least
85% lagging, actual KVA shall be used as the billing demand.
TERMS OF PAYMENT: Payment due on receipt. A late charge of 5% will be added to all
bills not paid within 21 days after bill date. If the 21` day falls on a
weekend or an official City of Lubbock recognized holiday, the late
charge will not be applied until the next business day.
CHARACTER OF AC. 60 hertz. Single-phase or three-phase, at one available
SERVICE: standard voltage.
TERMS & Service supplied under this rate is subject to the terms and
CONDITIONS: conditions set forth in LP&L's General Terms and Conditions of the
Rate Schedule as approved by the City Council of the City of
Lubbock and on file with the City Secretary of the City of Lubbock.
Secondary General Service Rev: 12/01/2013
22
EFFECTIVE DATE: For all electric meters read by LP&L on or after October 1, 2014
Secondary General Service Rev: 12,`01+2013
23
PRIMARY GENERAL SERVICE
Rate 16P
APPLICABLE: To all commercial and industrial customers for electric service
supplied at primary voltage for commercial purposes when all
service is supplied at one point of delivery and measured through
one meter, where facilities of adequate capacity and suitable voltage
are adjacent to the premises to be served.
TERRITORY:
RATE:
Not applicable to temporary, breakdown, standby, supplementary,
resale or shared service.
Lubbock, Texas
Service Availability Charge
Energy Charge:
Demand Charge:
$264.38 per month per meter
$0.00048 per kWh
$4.38863 per kW
DEMAND: Lubbock Power and Light will furnish at its expense the necessary
metering equipment to measure the customer's kW demand for the
30 -minute period of greatest use during the month. In the absence
of a demand meter, the customer's demand will be billed using the
monthly kilowatt-hours and an average load factor of 69.71 percent.
In no month, shall the billing demand be greater than the kW value
determined by dividing the kWh sales for the billing period by 80
hours.
LOSS ADJUSTMENT: When metering is installed on the secondary (customer's) side of
any voltage transformation made at less than available primary
voltage at the point of service, the meter readings for billing
purposes shall be increased to include all transformation losses.
PURCHASED POWER The charge per kilowatt-hour of the above rate shall be increased by
COST RECOVERY the applicable recovery factor per kilowatt hour as provided in the
FACTOR: current Lubbock Power and Light "Purchased Power Cost Recovery
Factor".
Primary General Service Rev: 10/01!2014
24
FRANCHISE FEE The charge of the above rate may be increased (i) by an amount no
EQUIVALENT: greater than the equivalent franchise fee established by the City
Council of the City of Lubbock for any other electric utility; or (ii)
by an amount equal to any franchise fee obligation applicable to
Lubbock Power & Light as established by the City Council of the
City of Lubbock.
TAX: Billings under this schedule may be increased by an amount equal to
the sum of the applicable federal, state and local taxes, fees, or
charges levied, assessed and/or payable by Lubbock Power & Light
for utility services rendered, or on the right or privilege or rendering
the service, or on any object or event incidental to the rendition of
the service.
POWER FACTOR: Applicable to customers on this rate schedule with a peak demand of
200 kW or greater. At all times, Customer will maintain at Lubbock
Power & Light's point of delivery, a power factor of not less than
85% lagging.
Where Customer fails to maintain a power factor of at least 85%
lagging at LP&L's point of delivery„ Customer shall install suitable
capacitors or other equipment necessary to raise the overall power
factor at the point of delivery to a satisfactory value. Where such
power factor correction equipment is used, Customer shall install a
relay, switch or other regulating equipment for purposes of
disconnecting or controlling the power factor correction equipment
in order to prevent excessive voltage conditions on Lubbock Power
& Light's system.
Effective October 1, 2015, LP&L may disconnect Customer's
service, following proper notice, if Customer fails to maintain a
power factor of at least 85% lagging. In cases where service is
provided and the customer fails to maintain a power factor of at least
85% lagging, actual KVA shall be used as the billing demand.
TERMS OF PAYMENT: Payment due on receipt. A late charge of 5% will be added to all
bills not paid within 21 days after bill date. If the 21" day falls on a
weekend or an official City of Lubbock recognized holiday, the late
charge will not be applied until the next business day.
CHARACTER OF AC. 60 hertz. Single-phase or three-phase at Lubbock Power &
SERVICE: Light's available primary voltage.
TERMS & Service supplied under this rate is subject to the terms and
CONDITIONS: conditions set forth in LP&L's General Terms and Conditions of the
Rate Schedule as approved by the City Council of the City of
Lubbock and on file with the City Secretary of the City of Lubbock.
Primary General Service Rev: 10;'01:2014
25
EFFECTIVE DATE: For all electric meters read by LP&L on or after October 1, 2014
Primary General Service Rev: 10/0V2014
NJ
STATE UNIVERSITY GENERAL SERVICE
Rate 16U
126
APPLICABLE: To all State of Texas universities using more than 100,000,000 kWh
per year where facilities of adequate capacity and suitable voltage
are adjacent to the premises to be served.
TERRITORY:
RATE:
Not applicable to temporary, breakdown, standby, supplementary,
resale or shared service.
Lubbock, Texas
Service Availability Charge:
Demand Charge:
Energy Charge:
$0.00 per month per meter
$0.00
$0.014000 per kWh
WHOLESALE POWER The charge per kilowatt-hour of the above rate shall be increased by
CHARGE: an amount equal to LP&L's average cost of Wholesale Power for the
month immediately preceding the current billing month for the
customer as delivered to all LP&L customers including assumed
system losses of 2%. The Wholesale Power Charge shall be
calculated monthly by dividing (i) the amount of the Total Bill for
Wholesale Power for the month immediately preceding the current
billing month for the customer including any prior month
adjustments by (ii) the kWh delivered to all LP&L customers in the
month immediately preceding the current billing month for the
customer. The kWh delivered to all LP&L customers shall be
calculated by reducing by 2% the kWh delivered to LP&L's
delivery points by SPS as shown on the Wholesale Power bill of the
month immediately preceding the current billing month for the
customer. This reduction is an adjustment to account for line losses
occurring between LP&L's point(s) of interconnection with SPS and
the delivery points of the customer.
State University General Service Rev: 1001 `2014
127
TERMS OF PAYMENT: Payment due 30 days after bill date or as otherwise required by state
law. If the 30`I' day falls on a weekend or an official City of
Lubbock recognized holiday, the due date will be extended until the
next business day. A late charge of I% or as authorized by state
law, whichever is greater, will be added to all bills not paid by the
due date.
CHARACTER OF AC. 60 hertz. Single-phase or three-phase at Lubbock Power &
SERVICE: Light's available secondary voltage.
TERMS & Service supplied under this rate is subject to the terms and
CONDITIONS: conditions set forth in LP&L's General Terms and Conditions of the
Rate Schedule as approved by the City Council of the City of
Lubbock and on file with the City Secretary of the City of Lubbock.
EFFECTIVE DATE: For all electric meters read by LP&L on or after October 1, 2014
State University General Service Rev: 10 01 2014
LARGE MUNICIPAL
Rate 17
128
APPLICABLE: To all municipal facilities supplied at secondary voltage for
municipal purposes when all service is supplied at one point of
delivery and measured through one meter, where facilities of
adequate capacity and suitable voltage are adjacent to the premises
to be served and whose load exceeds 10 kW of demand in any
month. Meters on this rate with loads that drop to 10 kW of demand
or below will be eligible to be reassigned to Rate 21 (Small
Municipal and School Service) only after 12 consecutive months
where loads have not exceeded 10 kW of demand.
TERRITORY:
RATE:
Not applicable to temporary, breakdown, standby, supplementary,
resale or shared service, or to service for which a specific rate
schedule is provided.
Lubbock, Texas
Service Availability Charge:
Energy Charge:
Demand Charge:
$42.30 per month per meter
$0.00057 per kWh
$4.46265 per kW
DEMAND: Lubbock Power and Light will furnish at its expense the necessary
metering equipment to measure the customer's kW demand for the
30 -minute period of greatest use during the month. In the absence
of a demand meter, Customer's demand will be billed using the
monthly kilowatt-hours and an average load factor of 41.30 percent.
In no month, shall the billing demand be greater than the kW value
determined by dividing the kWh sales for the billing period by 80
hours.
PURCHASED POWER The charge per kilowatt-hour of the above rate shall be increased by
COST RECOVERY the applicable recovery factor per kilowatt hour as provided in the
FACTOR: current Lubbock Power and Light "Purchased Power Cost Recovery
Factor".
Large Municipal Service Rev: 10101/2014
7 f
29
FRANCHISE FEE The charge of the above rate may be increased (i) by an amount no
EQUIVALENT: greater than the equivalent franchise fee established by the City
Council of the City of Lubbock for any other electric utility; or (ii)
by an amount equal to any franchise fee obligation applicable to
Lubbock Power & Light as established by the City Council of the
City of Lubbock.
TAX: Billings under this schedule may be increased by an amount equal to
the sum of the applicable federal, state and local taxes, fees, or
charges levied, assessed and/or payable by Lubbock Power & Light
for utility services rendered, or on the right or privilege or rendering
the service, or on any object or event incidental to the rendition of
the service.
POWER FACTOR: Applicable to customers on this rate schedule with a peak demand of
200 kW or greater. At all times, Customer will maintain at Lubbock
Power & Light's point of delivery, a power factor of not less than
85% lagging.
Where Customer fails to maintain a power factor of at least 85%
lagging at LP&L's point of delivery„ Customer shall install suitable
capacitors or other equipment necessary to raise the overall power
factor at the point of delivery to a satisfactory value. Where such
power factor correction equipment is used, Customer shall install a
relay, switch or other regulating equipment for purposes of
disconnecting or controlling the power factor correction equipment
in order to prevent excessive voltage conditions on Lubbock Power
& Light's system.
Effective October 1, 2015, LP&L may disconnect Customer's
service, following proper notice, if Customer fails to maintain a
power factor of at least 85% lagging. In cases where service is
provided and the customer fails to maintain a power factor of at least
85% lagging, actual KVA shall be used as the billing demand.
TERMS OF PAYMENT: Payment due on receipt. A late charge of 5% will be added to all
bills not paid within 21 days after bill date. If the 21" day falls on a
weekend or an official City of Lubbock recognized holiday, the late
charge will not be applied until the next business day.
CHARACTER OF AC. 60 hertz. Single-phase or three-phase, at one available
SERVICE: standard voltage.
TERMS & Service supplied under this rate is subject to the terms and
CONDITIONS: conditions set forth in LP&L's General Terms and Conditions of the
Rate Schedule as approved by the City Council of the City of
Lubbock and on file with the City Secretary of the City of Lubbock.
Large Municipal Service Rev: 10/01/2014
EFFECTIVE DATE: For all electric meters read by LP&L on or after October 1, 2014
Large Municipal Service Rev: 10 01 2014
131
STREET LIGHTING SERVICE
Rate 18
APPLICABLE: To municipal and State of Texas facilities for street lighting service
where facilities of adequate capacity and suitable voltage are
adjacent to the point of service.
TERRITORY: Lubbock, Texas
RATE: Service Availability Charge: 50.00 per month per meter
Energy Charge: $0.04071 per kWh
DETERMINATION OF Energy use will be determined by applying the total rated wattage of
ENERGY USE: each fixture, including the ballast, to the number of hours of
operation in each month. Street light burning time will be from one-
half after sunset to one-half hour before sunrise using National
Weather Service official sunrise & sunset times for Lubbock, Texas.
PURCHASED POWER The charge per kilowatt-hour of the above rate shall be increased by
COST RECOVERY the applicable recovery factor per kilowatt hour as provided in the
FACTOR: current Lubbock Power and Light "Purchased Power Cost Recovery
Factor".
FRANCHISE FEE The charge of the above rate may be increased (i) by an amount no
EQUIVALENT: greater than the equivalent franchise fee established by the City
Council of the City of Lubbock for any other electric utility; or (ii)
by an amount equal to any franchise fee obligation applicable to
Lubbock Power & Light as established by the City Council of the
City of Lubbock.
TAX: Billings under this schedule may be increased by an amount equal to
the sum of the applicable federal, state and local taxes, fees, or
charges levied, assessed and/or payable by Lubbock Power & Light
for utility services rendered, or on the right or privilege or rendering
the service, or on any object or event incidental to the rendition of
the service.
TERMS OF PAYMENT: Payment due on receipt. A late charge of 5% will be added to all
bills not paid within 21 days after bill date. If the 21St day falls on a
weekend or an official City of Lubbock recognized holiday, the late
charge will not be applied until the next business day.
Street Lighting Service Rev: 10/01:2014
Page 132
CHARACTER OF AC. 60 hertz. Single-phase at available standard voltage at the
SERVICE: point of service.
CONDITIONS OF Customer will install, own, operate and maintain the street lighting
SERVICE: system.
TERMS & Service supplied under this rate is subject to the terms and
CONDITIONS: conditions set forth in LP&L's General Terms and Conditions of the
Rate Schedule as approved by the City Council of the City of
Lubbock and on file with the City Secretary of the City of Lubbock.
EFFECTIVE DATE:
October 1, 2014
Street Lighting Service Rev: 10.01 2014
C�
GENERAL RELIGIOUS SERVICE
Rate 19
Page 133
APPLICABLE: To service provided exclusively to the primary structure used for
worship services of any church or religious association. This rate is
not available for any other structure owned and operated by a church
or religious association that is not primarily used for worship
services. This rate is not applicable to temporary breakdown,
standby, supplementary, or to service for which a specific rate
schedule is provided.
TERRITORY: Lubbock, Texas
RATE: Service Availability Charge: $14.28 per month per meter
Energy Charge:
$0.01573 per kWh
PURCHASED POWER The charge per kilowatt-hour of the above rate shall be increased by
COST RECOVERY the applicable recovery factor per kilowatt hour as provided in the
FACTOR: current Lubbock Power and Light "Purchased Power Cost Recovery
Factor".
FRANCHISE FEE The charge of the above rate may be increased (i) by an amount no
EQUIVALENT: greater than the equivalent franchise fee established by the City
Council of the City of Lubbock for any other electric utility; or (ii)
by an amount equal to any franchise fee obligation applicable to
Lubbock Power & Light as established by the City Council of the
City of Lubbock.
TAX: Billings under this schedule may be increased by an amount equal to
the sum of the applicable federal, state and local taxes, fees, or
charges levied, assessed and/or payable by Lubbock Power & Light
for utility services rendered, or on the right or privilege or rendering
the service, or on any object or event incidental to the rendition of
the service.
TERMS OF PAYMENT: Payment due on receipt. A late charge of 5° o will be added to all
bills not paid within 21 days after bill date. If the 21st day falls on a
weekend or an official City of Lubbock recognized holiday, the late
charge will not be applied until the next business day.
General Religious Service Rev. 10 012014
j34
CHARACTER OF AC. 60 hertz. Single-phase or three-phase, at one available
SERVICE: standard voltage.
TERMS & Service supplied under this rate is subject to the tenns and
CONDITIONS: conditions set forth in LP&L's General Terms and Conditions of the
Rate Schedule as approved by the City Council of the City of
Lubbock and on file with the City Secretary of the City of Lubbock.
EFFECTIVE DATE: For all electric meters read by LP&L on or after October 1, 2014
General Religious Service Rev: 1001 2014
35
SMALL MUNICIPAL & SCHOOL SERVICE
Rate 21
APPLICABLE: To municipal facilities and public and private schools for electric
service supplied at secondary voltage for municipal and school
purposes when all service is supplied at one point of delivery and
measured through one meter, where facilities of adequate capacity
and suitable voltage are adjacent to the premises to be served, and
whose load does not exceed 10 kW of demand in any month.
Single-phase motors not to exceed 10 horsepower, individual
capacity, may be served under this rate. Meters in which the load
exceeds 10 kW of demand in any month will be assigned to either
Rate 15 (Large School Service) or Rate 17 (Large Municipal
Service) as applicable and will not be eligible to be reassigned to
Rate 21 until there have been 12 consecutive months where loads
have not exceeded 10 kW of demand.
TERRITORY: Lubbock, Texas
RATE: Service Availability Charge: $11.05 per month per meter
Energy Charge: $0.01396 per kWh
PURCHASED POWER The charge per kilowatt-hour of the above rate shall be increased by
COST RECOVERY the applicable recovery factor per kilowatt hour as provided in the
FACTOR: current Lubbock Power and Light "Purchased Power Cost Recovery
Factor".
FRANCHISE FEE The charge of the above rate may be increased (i) by an amount no
EQUIVALENT: greater than the equivalent franchise fee established by the City
Council of the City of Lubbock for any other electric utility; or (ii)
by an amount equal to any franchise fee obligation applicable to
Lubbock Power & Light as established by the City Council of the
City of Lubbock.
TAX: Billings under this schedule may be increased by an amount equal to
the sum of the applicable federal, state and local taxes, fees, or
charges levied, assessed and/or payable by Lubbock Power & Light
for utility services rendered, or on the right or privilege or rendering
the service, or on any object or event incidental to the rendition of
the service.
Small Municipal & School Service Rev: 10 012014
P a g e
TERMS OF PAYMENT: Payment due on receipt. A late charge of 5% will be added to all
bills not paid within 21 days after bill date. If the 21 s` day falls on a
weekend or an official City of Lubbock recognized holiday, the late
charge will not be applied until the next business day.
CHARACTER OF AC. 60 hertz. Single-phase or three-phase, at one available
SERVICE: standard voltage.
TERMS & Service supplied under this rate is subject to the terms and
CONDITIONS: conditions set forth in LP&L's General Terms and Conditions of the
Rate Schedule as approved by the City Council of the City of
Lubbock and on file with the City Secretary of the City of Lubbock.
EFFECTIVE DATE: For all electric meters read by LP&L on or after October 1, 2014
Small Municipal & School Service Rev: 10/01/2014
36
GUARD LIGHT SERVICE
This rate is closed to new customers.
Page 137
APPLICABLE: For night outdoor guard lighting service where facilities of adequate
capacity and suitable voltage are adjacent to the point of service.
This rate is closed to new customers and no new lights will be
installed for existing customers. Customers of a competing utility
with existing guard light service will be allowed to transfer this
service to LP&L but no new lights will be installed for transferring
customers.
Mercury vapor lamps are no longer being manufactured or imported.
Once the inventory of mercury vapor lamps is depleted, customers
wili be given the option of having the guard light removed or
replaced with another type of light which may have a different rate.
TERRITORY: Lubbock, Texas
RATE: Each 150 Watt 15,000 lumen (nominal — actual rating may vary)
high-pressure sodium fixture installed on an overhead bracket on a
wood pole: $12.91 per month
Each 100 Watt 9,500 lumen (nominal — actual rating may vary)
high-pressure sodium fixture installed on an overhead bracket on a
wood pole: $8.77 per month
Each 150 Watt 7,000 lumen (nominal — actual rating may vary)
mercury vapor fixture installed on an overhead bracket on a wood
pole: $13.28 per month
Additional secondary line: For each additional 150 foot span of
secondary line required beyond the first 150 feet: $2.81 per month.
DETERMINATION OF 15,000 lumen HPS fixture uses 56 kWh per month.
ENERGY USE: 9,500 lumen HPS fixture uses 38 kWh per month.
7,000 lumen MV fixture uses 67 kWh per month.
PURCHASED POWER The charge per kilowatt-hour of the above rate shall be increased by
COST RECOVERY the applicable recovery factor per kilowatt hour as provided in the
FACTOR: current Lubbock Power and Light "Purchased Power Cost Recovery
Factor".
Guard Lighting Service Rev: 10.01%2014
Page 138
FRANCHISE FEE The charge of the above rate may be increased (i) by an amount no
EQUIVALENT: greater than the equivalent franchise fee established by the City
Council of the City of Lubbock for any other electric utility; or (ii)
by an amount equal to any franchise fee obligation applicable to
Lubbock Power & Light as established by the City Council of the
City of Lubbock.
TAX: Billings under this schedule may be increased by an amount equal to
the sum of the applicable federal, state and local taxes, fees, or
charges levied, assessed and/or payable by Lubbock Power & Light
for utility services rendered, or on the right or privilege or rendering
the service, or on any object or event incidental to the rendition of
the service.
TERMS OF PAYMENT: Payment due on receipt. A late charge of 5% will be added to all
bills not paid within 21 days after bill date. If the 21" day falls on a
weekend or an official City of Lubbock recognized holiday, the late
charge will not be applied until the next business day.
CHARACTER OF AC. 60 hertz. Single-phase at available standard voltage at the
SERVICE: point of service.
CONDITIONS OF Lubbock Power & Light will own, operate, and maintain on
SERVICE: Customer's premises the requested number of lights. Lights will be
photo -electrically controlled and mounted on a metal bracket
installed on Lubbock Power & Light's service poles, a separate 30
foot wood pole, or installed on any suitable mounting device
belonging to Customer. Lights will not be installed on any
mounting device, which in the opinion of Lubbock Power & Light,
is unsafe or not suitable for the purpose. One span of secondary line
not exceeding 150 feet in length may be furnished under the above
rate with each pole. Service requiring more than one span of
secondary line per pole will be furnished, provided Customer pays
the listed rate for each additional span not exceeding 150 feet in
length.
TERMS & Service supplied under this rate is subject to the terms and
CONDITIONS: conditions set forth in LP&L's General Terms and Conditions of the
Rate Schedule as approved by the City Council of the City of
Lubbock and on file with the City Secretary of the City of Lubbock.
EFFECTIVE DATE:
October 1, 2014
Guard Lighting Service Rev: 10/01/2014
J
FLOOD LIGHT SERVICE
This rate is closed to new customers.
Pit'g e X 39
APPLICABLE: For night outdoor flood light service where facilities of adequate
capacity and suitable voltage are adjacent to the premises to be
served. This rate is closed to new customers and no new lights
will be installed for existing customers. Customers of a competing
utility with existing flood light service will be allowed to transfer
this service to LP&L but no new lights will be installed for
transferring customers.
TERRITORY: Lubbock, Texas
RATE: The charge per month shall be the sum of Rate sections A+B+C+D:
RATE A: Charge per light for the first light on each 30 foot wood pole with
First Light Charge overhead service:
Lamp Wattage Metal Halide High Pressure Sodium
150 NIA $19.04
175 $19.15 N/A
250 $20.53 $20.62
400 $21.36 $21.82
1,000 $32.68 $33.06
RATE B: Additional charge per month for each additional light per pole:
Additional Light Charge
Lamp Wattage Metal Halide High Pressure Sodium
150 NIA $7.37
175 $7.47 N/A
250 $8.52 $8.61
400 $9.23 $9.63
1,000 $19.29 $19.60
Flood Light Service Rev: 1001 2014
E40
RATE C: Additional charge per month per pole:
Metal Halide
High Pressure Sodium
Additional Pole Charge
Lunen
kWh
Lumen
kWh
150
Overhead
Underground
Overhead
Underground
Pole
Wood
Wood
Steel
Steel
Height
Pole
Pole
Pole
Pole
30'
$0.00
$3.20
$5.34
$8.56
35'
$1.58
$4.78
$6.92
$10.13
40'
$3.37
$6.59
$8.72
$11.93
45'
$4.77
$7.99
$10.12
$13.34
50'
$6.31
$9.53
N/A
N/A
RATE D: For each additional 150 foot span of secondary line required beyond
Additional Service Span the first 150 feet: $2.66 per month.
Charge
DETERMINATION OF
ENERGY USE: Lamp
Metal Halide
High Pressure Sodium
' Wattage
Lunen
kWh
Lumen
kWh
150
N/A
N/A
16,000
56
175
14,000
62
N/A
N/A
250
20,500
97
27,500
97
400
36,000
136
50,000
159
1,000
110,000
359
140,000
350
PURCHASED POWER The charge per kilowatt-hour of the above rate shall be increased by
COST RECOVERY the applicable recovery factor per kilowatt hour as provided in the
FACTOR: current Lubbock Power and Light "Purchased Power Cost Recovery
Factor".
FRANCHISE FEE The charge of the above rate may be increased (i) by an amount no
EQUIVALENT: greater than the equivalent franchise fee established by the City
Council of the City of Lubbock for any other electric utility; or (ii)
by an amount equal to any franchise fee obligation applicable to
Lubbock Power & Light as established by the City Council of the
City of Lubbock.
TAX: Billings under this schedule may be increased by an amount equal to
the sum of the applicable federal, state and local taxes, fees, or
charges levied, assessed and/or payable by Lubbock Power & Light
for utility services rendered, or on the right or privilege or rendering
the service, or on any object or event incidental to the rendition of
the service.
Flood Light Service Rev: 10/01"2014
Page
TERMS OF PAYMENT: Payment due on receipt. A late charge of 5% will be added to all
bills not paid within 21 days after bill date. If the 215 day falls on a
weekend or an official City of Lubbock recognized holiday, the late
charge will not be applied until the next business day.
CHARACTER OF AC. 60 hertz. Single-phase. 120 or 240 volts.
SERVICE:
CONDITIONS OF Lubbock Power & Light will own, operate, and maintain on
SERVICE: Customer's premises the required number of overhead flood lights.
Lights will be photo -electrically controlled and mounted on LP&L
poles of the type and size selected by Customer and available under
the rate. One span of secondary line not exceeding 150 feet in
length may be furnished under the above rate with each pole.
Service requiring more than one span of secondary line per pole will
be furnished, provided Customer pays the listed rate for each
additional span not exceeding 150 feet in length.
41
LP&L will not construct, own, or maintain underground lines on
Customer's premises for flood light service. Construction for
underground lines will be per the specifications of LP&L and will be
arranged and paid for by Customer. Customer is responsible for any
trenching and backfilling necessary for construction.
TERMS & Service supplied under this rate is subject to the teens and
CONDITIONS: conditions set forth in LP&L's General Terms and Conditions of the
Rate Schedule as approved by the City Council of the City of
Lubbock and on file with the City Secretary of the City of Lubbock.
EFFECTIVE DATE:
October 1, 2014
Flood Light Service Rev: 10 012014
MISCELLANEOUS SERVICE CHARGES
Page 142
APPLICABLE: The service charges listed below are applicable to all customers
served by Lubbock Power & Light and are in addition to any other
charges made under Lubbock Power & Light's tariff for electric
service.
TERRITORY: Lubbock, Texas
RETURNED CHECK $30 as of 05/21/2007 but may be changed up to the maximum
CHARGE: allowed by applicable law without further action by the City Council
of the City of Lubbock.
This charge is made when Customer's check has been dishonored
and returned to Lubbock Power & Light.
SERVICE INITIATION $55.00 during business hours.
FEE: $87.00 after business hours.
$115.00 when cut at the pole during business hours.
$150.00 when cut at the pole after business hours.
This charge is made when Customer requests reconnection of
electric service after having been disconnected because of a
delinquent account.
RESTORATION OF $200.00 each occurrence plus expense for damages plus recovery of
TAMPERED SERVICE lost sales that are based on historical data or average use for
CHARGE: similarly situated customers.
This charge is applied to any customer who has tampered with the
meter installed on the customer's premises, or by any manner or
means has prevented the total energy from being registered by the
meter installed for such purposes.
METER TESTING $50.00 if meter test is requested by Customer. No charge to
CHARGE: Customer if meter test shows meter accuracy to be outside
acceptable tolerances.
Miscellaneous Service Charges Rev: 10101/2014
43
AGREED PAYMENT $30.00
PLAN CHARGE:
This charge is made when a customer requests and receives an
agreed payment plan (payment arrangement) using the services of an
LP&L Customer Service Representative. This charge will be
waived for self-service agreed payment plans made via LP&L's
automated phone system or online at www.LPandL.com.
DUPLICATE SILL $5.00 for each duplicate bill.
CHARGE:
This charge is made when a customer requests a copy of a
previously received bill. Copies of bills (12 month history) can be
obtained free of charge at www.LPandL.com.
MISCELLANEOUS At cost. This charge may be made for miscellaneous and non -
CHARGES: routine services perfonned at the request of Customer but not
covered specifically by any rate or fee. The charges will be the
reasonable costs incurred for performing such services including but
not limited to labor, materials, transpbrtation, miscellaneous
expenses and all applicable overheads for the service provided.
PULSE METERING At cost. These charges may be made when Customer requests
EQUIPMENT access to pulses from the revenue meter. The charges will be the
INSTALLATION AND reasonable costs incurred for providing such service including but
REPLACEMENT not limited to labor, materials, transportation, miscellaneous
CHARGE: expenses and all applicable overheads for the service provided.
TERMS & Service supplied under this rate is subject to the terms and
CONDITIONS: conditions set forth in LP&L's General Terms and Conditions of the
Rate Schedule as approved by the City Council of the City of
Lubbock and on file with the City Secretary of the City of Lubbock.
TAX: Billings under this schedule may be increased by an amount equal to
the sum of the applicable federal, state and local taxes, fees, or
charges levied, assessed and/or payable by Lubbock Power & Light
for utility services rendered, or on the right or privilege or rendering
the service, or on any object or event incidental to the rendition of
the service.
EFFECTIVE DATE:
October 1, 2014
Miscellaneous Service Charges Rev: 10/01/2014
PURCHASED POWER COST RECOVERY FACTOR:
44
The Purchased Power Cost Recovery Factor (PPRF), provides for the recovery of all purchased
power costs incurred by LP&L in serving system demand and energy requirements. The PPRF shall
be adjusted a minimum of two times per year, once during the non -summer season of October
through May and once during the summer season of June through September. The PPRF will have
a demand (PPRF-D) and energy (PPRF-E) component or rate. The PPRF rates shall be established
with the intention of snatching PPRF revenues with actual purchased power costs over the course of
a fiscal year, giving consideration to seasonal fluctuations in load and in purchased power prices.
The PPRF may be adjusted more frequently if any over or under recovery exceeds the maximum
variance as defined below.
For a particular customer class, the PPRF-E shall be adjusted by the following voltage level factors:
Primary Voltage: 1.0409
Secondary Voltage: 1.06340
On a monthly basis, LP&L shall track actual revenues collected from the PPRF and compare these
revenues to actual total purchased power costs incurred. The cumulative balance representing the
difference between total PPRF revenues collected less total purchased power costs incurred over
the period shall be reported to the LPL&L Board on a monthly basis.
A PPRF balancing account will be established with a cap equal to five percent of total annual
budgeted or forecasted purchased power costs to manage the monthly over/under collection of, or
differences in, the monthly PPRF revenues and monthly purchased power costs. If at any time, the
reported cumulative balance of the difference between total PPRF revenues collected and
purchased power costs is greater than the PPRF balancing account cap, an adjustment may be made
to the PPRF rates with the intention of refunding the over recovery amount. In addition, if at any
time the reported cumulative balance of the difference between total PPRF revenues collected and
purchased power costs is approaching or less than zero, an adjustment may be made to the PPRF
rates with the intention of replenishing the PPRF stabilization fund.
All adjustments to the PPRF shall be approved by the LP&L Board.
Purchased Power Cost Recovery Factor Rev. 10 01 2014