Item No. 6.4
July 23, 2015
RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock is hereby authorized and directed to execute for
and on behalf of the City of Lubbock, Change Order No. 2 to that certain Contract No. 11709 by
and between the City of Lubbock and Utility Contractors of America, Inc., for the South Lubbock
Sanitary Sewer Extension Phase — Bid Package B, and related documents. Said Change Order
No. 2 is attached hereto and incorporated in this resolution as if fully set forth herein and shall be
included in the minutes of the City Council.
Passed by the City Council on July 23, 2015
ATTEST:
Rebe a Garza, City Secretary
APPROVED AS TO FORM:
ks
RES.ChgOrd#2, Contract -Utility Contractors of America, Inc.
6/2315
M
Lubber
Office of Purchasing and Contract Management
Change Order
Contract No: 11709 Contractor: Utility Contractors of America, Inc.
Change Order No: 02 Contract Title: South Lubbock Sanitary Sewer Extension Phase I — Bid Package B
Bid/RFP No: 14 -11709 -TF Project No: 92178
"Change Order" means a written order to a Contractor, executed by the Owner, in accordance with the Contract authorizing an addition to, deletion
from, or adjustment or revision of the requirements of the Contract documents, or an adjustment to the compensation payable to the Contractor, or to
the time for performance of the Contract and completion of the project, or a combination thereof, which does not alter the nature of project and is an
integral part of the project objective. Adjustments to "Estimated Quantities" to a line time in a Unit Price Contract do not require a Change Order. All
work that alters the nature of the construction or that is not an integral part of the project objective must be let out for public bid.
Description of Change (alteration, deviation, addition, or deletion) caused by conditions encountered during construction not covered by the
Per attached backup material, Change Order #2 includes the following items: Item 1) Material change in water line pipe size from 6"
to 4" south of 50" St. in MLK Blvd. Item 2) Removal of four driveway culverts along MLK Blvd south of Loop 289 and
replacement of five culverts crossing 98" Street west of MLK Blvd. Item 3) Install SET for culverts on 98th Street. Item 4) Install
flowable fill at the low water crossing at 74" and MLK Blvd. Item 5) Mill and repave 2" of asphalt pavement on MLK Blvd. north of
741h to Loop 289 Frontage Road. A time extension of 75 days is included in this change order, 30 days for water line breaks that
caused a shutdown of the project and 45 days for weather delays above and beyond the normal weather patterns for Lubbock.
Where the Change Order is negotiated, the Change Order must be fully documented and itemized as to costs, including material quantities, material
costs, taxes, insurance, employee benefits, other related costs, profit and overhead. Where certain unit prices are contained in the initial Contract, no
deviations are allowed in computing negotiated change order costs.
ITEMIZED COSTS MUST BE FULLY DOCUMENTED AND ATTACHED TO THIS FORM.
ITEM
DESCRIPTION
AMOUNT
A.
ORIGINAL CONTRACT VALUE:
$20,293,159.95
B.
AMOUNT OF THIS CHANGE ORDER: (Note: Council approval required if over $50,000)
$51,815.69
COST CENTER: ACCOUNT:
C.
PERCENT OF CONTRACT VALUE THIS CHANGE ORDER (B/A)
0.26%
D.
AMOUNT OF PREVIOUS CHANGE ORDERS:
-$65,664.00
E.
TOTAL AMOUNT OF ALL CHANGE ORDERS (B+D)
413,848.31
F.
PERCENT OF CONTRACT OF ALL CHANGE ORDERS E/A : 25/ maximum)
-0.07%
G.
NEW CONTRACT AMOUNT (A+E):
$20,279,311.64
It is mutually agreed that the above dollar amount and the time extension, as applicable, as set forth in this Change Order constitutes full
compensation to the Contractor for all costs, expenses and damages to the Contractor, whether direct, consequential or otherwise, in anyway incident
to, or arising out of, or resulting directly or indirectly, from the work performed or modified by the Contractor under this Change Order.
Ct R7�
D to
Approved as to Content:
(' wne ep n ire ate y�
�� I2 61
(5) Capital Projects Manager Date
7/23/2015
(7) M Date
Council ate: July 23, 2015 Agenda Item #:
i
(2) Project Architect/Engineer
a
June 20, 2015
Date
ateft//r
uate
7/23/2015
Date
Resolution #: 2015-RO229
PUR45 (Rev 012012)
Kimley>Morn
June 20, 2015
Mr. Zoltan Fekete, P.E.
City of Lubbock, Texas
1625 13th Street
Lubbock, Texas
RE: South Lubbock Sanitary Sewer Extension, Phase I — Bid Package B
Change Order Number 2
KHA No. 063126015
Dear Zoltan:
The following is a description of the items that are involved in change order number two for the above
referenced project.
1. It was determined by City staff and the Engineer that the water line relocation as shown on
Sheet C 54 would be replaced with a 4" PVC water line in lieu of a 6" PVC water line. This
was a material change only resulting in a credit of $981.75.
2. It was determined by City staff, Lubbock County, and the Engineer that four culverts along
MILK Blvd. (74th, 82n4, 841", and 881" Streets) would be replaced with low water crossings.
Also, during construction is was discovered that the two culverts crossing 9P Street at
approximate STA. 253+30 (Sheet C 72) were corroded beyond repair and would need to be
replaced. City staff and the Engineer proposed to replace the two culverts with five culverts.
The net change in number of culverts is a negative 16 linear feet. The change for these two
items results in a credit of $816.00.
3. In relation to item two above, eight safety end treatments (SET's) would be removed from the
project and ten safety end treatments would be added resulting in a net change of two SETS
and an increase of $2.000.00.
4. It was determined by City Staff and the Engineer that using flowable fill at the low water
crossing subgrade would provide a more stable crossing and reduce the potential for wash
out of the roadway resulting in an increase of $7,700.44.
5. The 300 -foot section of MLK Blvd. north of 74t1 Street was originally designed to be replaced.
However, it was not damaged during construction. Therefore, due to the existing pavement
condition it was determined by City Staff and the Engineer that 2 -inches of the pavement
would be milled and repaved from W to the Loop 289 frontage road (approx. 750 LF)
resulting in a net increase of $43.913.00.
The change in contract price associated with these changes is detailed below:
• Original contract price: $20,293,159.95
• Net change of this change order: $51,815.69
• Amount of previous change orders: -$65,664.00
• Contract price with all approved change orders: $20,279,311.64
Kimley>>> Horn
Page 2
As you are aware, during construction a few of the City water lines broke causing water to flow into
the construction area. This caused a delay in UCA's progress along the construction route, an
additional 30 days are recommended to be added for this delay. Also, it was agreed that an
additional 45 days be added to the contract due to weather delays above and beyond the normal
weather patterns for Lubbock. This results in a total of 75 days that are recommended to be added to
the contract.
• Original contract time: 360 days
• Original NTP date: May 19, 2014
• Contract time change with this change order: 75 days
• Contract time change of previous change orders: 65 days
• Contract time with all approved change orders: 500 days
• Revised Substantial Completion Date: September 30, 2015
Should you have any questions please do not hesitate to give me a call.
Sincerely,
KINLEY--HORN AND ASSOCIA TES, INC.
Texas Firm Registration No. F-928
Aaron K Rader, P.E.
Copy to: City of Lubbock: Wood Franklin, P.E., John Turpin, P.E., Josh Kristinek, EIT
LICA: Ty Lane, Jonathan Ziegner, P.E.
Walker RPR Services: Ricky Walker, Mark Perry
Kimley-Horn: Jeff James, P.E.
K:1F74V_Wities106312&IISSLSSE Ph18P8CCAWFVCHG ORD\Change Odee 21SLSSE Ph1 BPB Change Oder2 KHA Leflerd=
KIMLEY-HORN AND ASSOCIATES, INC.
801 Cherry Street, Suite 950
Fort Worth, TX 76102 Daae: June 20. 201
CHANGE OR EXTRA WORK ORDER NO.2
PROJECT DESCRIPTION:
South Lubbock Sanitary Sewer Extension Phase 1, Bid Pacakge B
KHA Project No.:
063126015
OWNER:
City of Lubbock
CONTRACTOR:
Utility Contractors of America
ORIGINAL CONTRACT AMOUNT:
$20,293,159.95
REVISED CONTRACT AMOUNT PER
CHANGE ORDER No. 1:
$20,227,495.95
REVISED CONTRACT AMOUNT PER
$63.25
CHANGE ORDER No. 2:
$20,279,311.64
CHANGE OR EXTRA WORK TO BE PERFORMED
Item
No.
Approx.
Quantity
Description of Item
Unit Price
Decrease in
Conn. Price
Increase in
Contr. Price
44
(561)
LF 6" C-900 DR -I8 PVC Water Pipe
$65.00
($36.465.00)
77
561
LF 4" C-900 DR -18 PVC Water Pipe
$63.25
$35,483.25
61
(16)
LF Corrugated Metal Pipe Culvert (24")
$51.00
($816.00
62
2
EA Safety End Treatment (24")
$1,000.00
$2,000.00
77
1
LS Flowable Fill at Low Water Crossing
$7,700.44
$7,700.44
51
(867)
SY 12" Compacted Subgrade
$4.00
($3.468.00)
52
(867)
SY Flexible Base (6')
$11.00
($9.537.00)
53
(867)
SY HMAC Type C (2")
$14.00
($12.138.00)
78
2,158
SY Mill and Repave 2" Asphalt Pavement
$32.00
$69,056.00
Total increase in Contract Amount: $114,239.69
Total Decrease in Contract Amount:
Net Change in Contract Amount:
Percent of Contract Value This Change Order:
Amount of Previous Change Orders:
Total Amount of All Change Orders
Percent of Contract Value All Change Orders:
Revised Contract Amount:
Original Contract Time
Net Change in Contract Time of Completion previous change orders:
Net Change in Contract Time of Completion per CO2:
Revised Contract Time of Completion:
($62.424.00)
$51,815.69
0.26%
($65.664.00)
($13.848.31)
-0.07%
$20,279,311.64
360
65
75
500
Utility Contractors of America, Inc.
MfL
5805 CR 7700
Lubbock, TX 79424
Kimley-Horn Proposal
Attn: Aaron Rader June 12, 2015
13829 Technology Drive, Suite A-2
Oklahoma City, OK 73134
Item Description Quantity Unit Unit Cost Total Cost
SLSSE - Proposal for 4" water line for Item 44
Install 4" water line in lieu of 6"
(Bid Item 44)
Page 1
561.00 LF 63.25
35,483.25
TOTAL $ 35,483.25
Utility Contractors of America, Inc.
5805 CR 7700
Lubbock, TX 79424
(806)863-2642
To: Kimley-Horn and Associates From: LICA
Attn: Aaron Rader Date: February4, 2015
Project: South Lubbock Sanitary Sewer Extension - Phase 1
Contractor's Request to Change
Changes: LICA is respectfully requesting to change the proposal to include the following items.
Description
quantity
Unit
Unit Cost
Total
Cost Breakdown for adding CSB around low water crossing
Labor: Forming
1
EA
$638.00
$638.00
Labor: Pouring
1
EA
$1,232.00
$1,232.00
Equipment: Motorgrader
1
EA
$687.50
$687.50
Equipment: Backhoe
1
EA
$412.50
$412.50
Equipment: Front End Loader
1
EA
$550.00
$550.00
Equipment: Dump Truck
1
EA
$467.50
$467.50
Materials: Flowable Fill
35
CY
$73.70
$2,579.50
Materials: Misc Form Work
1
EA
$433.40
$433.40
Subtotal
$7,000.40
Overhead & Profit
10%
$700.04
Date: y /s
Accepted:
Total: $7,700.44
Cbrrs Balios
LICA
Signature:
Date: Title:
UC A
Kimley-Horn
Attn: Aaron Rader
Utility Contractors of America, Inc.
5805 CR 7700
801 Cherry Street, Suite 950
Fort Worth, TX 76102
Item Description
Lubbock, TX 79424
Proposal
May 5, 2015
Quantity Unit Unit Cost Total Cost
SLSSE - Proposal for Paving
Repair North of the Low Water Crossing
along
MLK
Mill 2" and Pave
2,158.00 SY
32.00
69,056.00
TOTAL $ 69,056.00
Page I
UTILITY CONTRACTORS OF AMERICA, INC.
5805 CR 7700 – Lubbock, Texas 79424
June 8, 2015
45 DAYS TOTAL
Days Unable to Work: 84 Due To:
May 6 3 DAY
Thursday, May 22, 2014------- Rain
Friday, May 23, 2014 Rain
(806) 863-2642, Fax # (806) 863-4132
^aua r�
uc u.
UTILITY CONTRACTORS OF AMERICA, INC.
5805 CR 7700 – Lubbock, Texas 79424
June 8, 2015
45 DAYS TOTAL
Days Unable to Work: 84 Due To:
May 6 3 DAY
Thursday, May 22, 2014------- Rain
Friday, May 23, 2014 Rain
(806) 863-2642, Fax # (806) 863-4132
June
Tuesday, May 27, 2014 Too Wet To Work
Monday, June 09, 2014 Rain
B days Oklis i ei t eF exist; ig pipe H at vies i reerreet—
Raised bet still �e�erlfed
Rail ad but 9tili rrerked
July 6 3 DAY
Wednesday, July 02, 2014 ain
mace&wFd.,,, 1wly US 2Q!4 IIBhday
Reil res'-bnt-�liJFsaeriee'
Reined bet still %OFI(ed
Thursday, July 17, 2014 Rain - UCA did not work, Southland worked
Tuesday, July 29, 2014 Rain - UCA did not work, Southland worked
August 2 1 DAY
RaiaadIshit still v0sAked
Friday, August 29, 2014 Rain - UCA did not work, Southland worked
Page 1 of 3
^aua r�
June
Tuesday, May 27, 2014 Too Wet To Work
Monday, June 09, 2014 Rain
B days Oklis i ei t eF exist; ig pipe H at vies i reerreet—
Raised bet still �e�erlfed
Rail ad but 9tili rrerked
July 6 3 DAY
Wednesday, July 02, 2014 ain
mace&wFd.,,, 1wly US 2Q!4 IIBhday
Reil res'-bnt-�liJFsaeriee'
Reined bet still %OFI(ed
Thursday, July 17, 2014 Rain - UCA did not work, Southland worked
Tuesday, July 29, 2014 Rain - UCA did not work, Southland worked
August 2 1 DAY
RaiaadIshit still v0sAked
Friday, August 29, 2014 Rain - UCA did not work, Southland worked
Page 1 of 3
September
14
S•mday, Septamlaer 97, 2934 Rain
Thursday, September 11, 2014 Rain - UCA did not work, Southland worked
Friday, September 12, 2014 Rain - UCA did not work, Southland worked
Senday, September 397 2911 Rain
-f uesday, September 16, 2014 Rained but still worked
'A', r' - i- 17 'o', Rained but still worked
Thursday, September 18, 2014 Rain - Damage from rain
Friday, September 19, 2014 Rain - UCA did not work, Southland worked
984Isday-5ep40FAl88F 49, 2944
Sundayy Sa{atemlaer 21, 2914 Rain
Monday, September 22, 2014 Too wet to work
Tuesday, September 23, 2014 Too wet to work
Rained bdt still vierleed
Thursday, September 25, 2014 Rain
October 1 1 DAY
Monday, October 27, 2014 Rain - UCA did not work, Southland worked
November 2 1 DAY
Tuesday, November 04, 2014 Rain - UCA did not work, Southland worked
December
Tuesday, December 30, 2014 Snow - UCA worked 1/2 day
Wednesday, December 31, 2014 Snow - No Work
January
Friday, January 02, 2015 Snow - No Work
Thursday, January 22, 2015 Snow - No Work
Friday, January 23, 2015 Snow - No Work
Page 2 of 3
February
Monday, February 23, 2015 Snow - No Work
Thursday, February 26, 2015 Snow - No Work
Friday, February 27, 2015 Snow - No Work
March 6 5 DAY
Monday, March 02, 2015 now - No Work
Tuesday, March 03, 2015 No Work - too wet
Wednesday, March 04, 2015 Rain/Sleet - No work
Thursday, March 05, 2015 No Work - snow melting
Friday, March 06, 2015 Only 1 crew worked - too wet
April 4 4 DAY
Monday, April 13, 2015 Rain - No Work
Tuesday, April 14, 2015 Too Wet to Work - 1 crew tested
May
Monday, April 27, 2015 Rain - Lone Star worked (milling) only
Tuesday, April 28, 2015 Wet - Lone Star worked only
16 9 DAY
Tuesday, May 05, 2015
Wednesday, May 06, 2015
Thursday, May 07, 2015
Friday, May 08, 2015
2"-3" Rain
Too Wet to Work
Wet - Light Drizzle
Rain PM
Wednesday, May 13, 2015 1" Rain
Friday, May 15, 2015 1.5" Rain - Only Lone Star milling
Friday, May 22, 2015 Too Wet - Pumping Water
sef"Fday., 11448", 23, ;I@is Too Wet PtimpingWateF
Thursday, May 28, 2015 1.5" Rain - Pumping Water
Friday, May 29, 2015 Too Wet - Pumping Water
Sam day, May 98, 20is .5" Ram PEI P 4 is yeate
c,.. d -y A42y 21 ,n, c Tao Wai Romping Water
Page 3 of 3