HomeMy WebLinkAboutResolution - 2001-R0104 - Change Order - Lubbock Building Services, Inc. - 04/12/2001Resolution No. 2001-RO104
April 12, 2001
Item No. 31
RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK
THAT the Mayor of the City of Lubbock BE and is hereby authorized and
directed to execute for and on behalf of the City of Lubbock, Change Order #l, to RFP
#00-228, between the City of Lubbock and Lubbock Building Services, Inc., for the
Police Academy Firing Range, and related documents. Said Change Order is attached
hereto and incorporated in this resolution as if fully set forth herein and shall be included
in the minutes of the City Council.
Passed by the City Council this 12th day of April , 2001.
r , YS — Ti i� rR
ATTEST:
Rebecca Garza
City Sccretary
APPROVED AS TO CONTENT:
dG8U,O!tg' A�,arnager hies ith, R.A.
a
APPROVED AS TO FORM:
, 114, �
William de Haas
Contract Manager/Attorney
Dh/Cedocs /ChanaeOrder.LubbocicBuildi ngServi ces,Inc. res
March 21, 2001
Resolution No. 2001-RO104
April 12, 2001
Item No. 31
CITY OF LUBBOCK
CHANGE ORDER
CHANGE ORDER #: One (1) DATE: February 27, 2001
CITY OF LUBBOCK BID#: 00-228 PROJECT NAME: Police Academy Firing Range
CONTRACTOR: Lubbock Building Services, Inc.
DESCRIPTION OF WORK:
This change order will provide for the following:
I . CPR#01: Plug and abandon existing water well as per TNRCC regulations $5,427.06
2. CPR#02: Import 10,750 CY of soil. Plow and turn soil for drying for 40 hrs 49,687.00
Total amount of Change Order #1 $55,114.06
ITEM DESCRIPTION VALUE
A. ORIGINAL CONTRACT VALUE: $848,600.001,
B. AMOUNT OF THIS CHANGE ORDER:
C PERCENT OF CONTRACT VALUE THIS CHANGE ORDER (B/A)
D. AMOUNT OF PREVIOUS CHANGE ORDERS: $0.00
E. TOTAL AMOUNT OF ALL CHANGE ORDER (B+D): $55,114.06
F. PERCENT OF CONTRACT OF ALL CHANGE ORDERS (E/A): NINE,
G. NEW CONTRACT AMOUNT (A+E): $903,714.06.00
[VE 4CTR4ACiTOR SIGNATURE
blfp
PURCHA 'M DEPARTMENT
MAYOR
WINDY SITTON
��iGL G& jyi j l / � l a /
LEGAL DEPARTMENT
REBECCA GARZA