HomeMy WebLinkAboutResolution - 2008-R0394 - Change Order For SE Water Reclamation Plant Improvement - Eagle Contracting, LP - 10/09/2008Resolution No. 2008-RO394
October 9, 2008
Item No. 5.9
RESOLUTION
IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock BE and is hereby authorized and
ted to execute for and on behalf of the City of Lubbock, Change Order No. 2 to that
in Contract by and between the City of Lubbock and Eagle Contracting, L.P., for the
least Water Reclamation Plant Improvement (ITB# 07 -730 -BM), and related
ments. Said Change Order No. 2 is attached hereto and incorporated in this
ution as if fully set forth herein and shall be included in the minutes of the City
ril
by the City Council this 9th day of October 2008.
< � 7""� *-; Z;
TOM MARTIN, MAYOR
ATTEST:
Garza, City
PPROVED AS TO ONTENT:
ood ankh
hi E weer for Water Utilities
City Manager
'ROVED AS TO FORM:
ird K. Casner
Assistant City Attorney
ATIIRICHARD\Resolutionsaes.EagleContracting. ChangeOrder2.092508. doc
CITY OF LUBBOCK
rvv .
Change Order #:
:. _
2
v++clt�vL' ViILL'
Contractor:
1C
Eagle Contracting, L.P.
Date:
September 9, 2008
BID/ITB #:
07 -730 -BM
Contract #: 8119 Project Name: Southeast Water Reclamation Plant
Improvement
Change Order within the scope of the contract means a Change Order that DOES NOT ALTER THE NATURE OF THE THING
TO BE CONSTRUCTED AND THAT IS AN INTEGRAL PART OF THE PROJECT OBJECTIVE. After performance of a
construction contract begins, Change Orders may be approved if necessary to 1) make changes in plans or specifications; or 2)
decrease or increase the quantity of work to be performed or materials, equipment, or supplies to be furnished. Description of
change (alteration, deviation, addition, or deletion) caused by ennditione n.,o..,...r...A A..—*--
the specifications and drawl sof the pr9ject (attach additional a es if necessY�V Y4 .,_._5 I VuaL[ ucuun not covered by
ar
):
This change Order includes modifications to the beams in the roof of the Intermediate Lift Station, the addition of granular fill
and filter fabric beneath BNR No. 3, modifications of the Intermediate Lift Station influent line, the reconfiguration of the
temporary return activated sludge line, the addition of a vent and clean out at the Primary Sludge Pumping Station No. 2, the
addition of carbide coating to the TWAS pumps, and AFD enclosures for the WAS and TWAS pumps. The total cost of this
change order is $117,047.09. The new contract substantial completion date will be July 28, 2011.
Change Orders must either he neuntintaA in the 1—t
—.7 — _.Y Vv;'& Vi put vut for public bid by the Purchasing
Department. Where the Change Order is negotiated, the Change Order must be fully documented and itemized as to costs,
including material quantities, material costs, taxes, insurance, employee benefits, other related costs, profit and overhead.
ITEMIZED COSTS MUST BE FULLY DOCUMENTED AND ATTACHED TO THIS FORM.
ITEM DESCRIPTION AM_ UT
A. ORIGINAL CONTRACT VALUE: $ 43,520,000.00
B. AMOUNT OF THIS CHANGE ORDER: Council approval required if over $25,000 5}"�-'
C. .PERCENT OF CONTRACT VALUE THIS CHANGE ORDER (B/A):
D. AMOUNT OF PREVIOUS CHANGE ORDERS: $ 29,583.00 -
E. TOTAL AMOUNT OF ALL CHANGE ORDERS (B+D): $ 129,630 09
F. PERCENT OF CONTRACT OF ALL CHANGE ORDERS (EIA): 25% Maximum 9 "w
G. NEW CONTRACT AMOUNT (A+E): $43,666,630.09
It is mutually agreed that the above dollar amount and the time extension, as applicable, as set forth in this Change Order constitutes
full compensation to the Contractor for all costs, expenses and damages to the Contractor, whether direct, consequential or otherwise,
in anyway incident to, or arising out of or resulting directly or indirectly; from the work performed or modified by the Contractor
under this Change Order.
This Chane Order is not valid witho t the followin si tures le a si n i order nd retu ori ita with Co act Cover Sheet to
Purchas'n a tract Ma a lit De artm lit
(1) O TRAC ' h a � - Date (2) PROJECT ARCiirrECT/ENGINEER
Date
.vppro aVContenApproved as to
f' (3) O ENTATIVE Date (4) ATTOR EY ate
RS/v� � (5) CAPITS MANAGER Date (6 PURCHASIN CONTRACT MANAGER Date
Change Orders over $25,000 require a Contract Cover Sheet and the foRnwine e:o.,,.H
=QF
CIx 10/9/08 A10/9/08
(7) MA OR Date (8) CITY ECRETARY - __�K
Date
Council Date: October 9 2008 Agenda Item #: S • 9 Resolution #: 2008—RO394
PUR-045 (Rev 02/06)
BLACK & VEATCH
r. building a World of difference -
ENERGY . WATER . INFORMATION • GOVERNMENT
City of Lubbock, Texas
Southeast Water Reclamation Plant
Contract No. 6
Mr. Soo Koon Soon, P.E.
City of Lubbock
P.O. Box 2000
Lubbock, TX 79457
Mr. Soo Koon Soon:
Resolution No. 2008—RO394
B&V Project 140092.6100
B&V File G-1.9
September 9, 2008
Subject: Change Order 02
Attached with this letter is documentation for Change Order No. 02. This change order involves the
following items.
1. It has come to our attention that the access hatches for the Intermediate Lift Station pumps are too
large to fit within the space provided between the structural beams in the roof. The spacing between
the roof beams is 4'-0". The hatch frame outside dimension is 561/2 -inches per the data included with
submittal 11150131-020. This frame will reduce the size of the structural beam by 81/2 -inches. This
change to the structural design is unacceptable. In order to minimize the delays associated with
delivery of new hatches, which could potentially be six to eight weeks, the beams were reviewed and
modified to accommodate the larger hatches. This resulting change to the beams would take
between one to two weeks. Eagle is requesting $12,234.00 and five (5) working days to complete the
work associated with this change.
The following documents are attached to support this change.
• Field Order No. 2 with the details for the recommended modifications to the roof beams.
• PCM -02 from Eagle Contracting with the cost breakdown.
2. Per Sheet MD3 (Sheet 181) Detail E, in the basins that have pressure relief valves, granular fill and
filter fabric are to be installed. There are not any installation details for the termination of the material
at the edge of the slab. Termination details were provided as Field Order No. 6, but were withdrawn
and the Contractor requested to provide termination similar to the two new clarifiers. Because of this
omission in the documents, Eagle did not provide costs in the Bid to cover the installation of granular
fill and filter fabric beneath BNR No. 3. Eagle is requesting $39,950.00 and seven (7) working days to
complete the work associated with this change.
The following documents are attached to support this change.
• Letter dated September 9, 2008 from Glenn Grant with the cost breakdown (PCM -03).
3. Per RFI -036, revisions are required to the influent line for the Intermediate Lift Station due to conflicts
with an existing electrical duct bank. The new line was to be installed at the same elevation of the
duct bank. New elevations for the new line were provided to have the line pass beneath the existing
duct bank. Eagle is requesting $26,494.00 and three (3) working days to complete the work
associated with this change.
Black & Veatch Corporation 9441 LBJ Freeway, Suite 114 Dallas, TX 75243 USA - Telephone: 214.570.7000
Page 2
City of Lubbock, TX B&V Project 140092.6100
Mr. Soo Koon Soon, P.E. September 9, 2008
The following documents are attached to support this change.
• RFI -036 with response from Laura Stratton dated August 8, 2008.
• Letter dated August 28, 2008 from Glenn Grant including the cost breakdown for the changes
(PCM -04).
4. Per RFI -037, revisions to the temporary return activated sludge line at the Aeration Distribution
Structure were required to accommodate are more equal split to each existing aeration basin. Eagle
is requesting $3,143.70 to complete this work.
The following documents are attached to support this change.
• RFI -037 with response from Laura Stratton dated August 8, 2008.
• Letter dated August 22, 2008 from Glenn Grant including the cost breakdown for the changes
(CMR -06).
5. When the Primary Sludge Pumping Station No. 2 was inspected by the City's Building Inspector, they
indicated that vent piping and clean out be added to the drain line. Eagle is requesting $1,486.39 to
complete this work.
IJ
The following documents are attached to support this change.
E-mail correspondence between Parkhill, Smith, & Cooper, Black & Veatch, and the City
concerning the addition of the vent and drain.
Letter dated August 26, 2008 from Dave Mullenix including the cost breakdown for the changes
(CMR -07).
As discussed during Progress Meeting 05 on September 4, 2008, the waste activated sludge (WAS)
pump supplier is requesting additional compensation to add a carbide coating to the two thickened
WAS pumps and AFD enclosures to the two TWAS pumps and the three WAS pumps. Under a
separate contract with the City, the pump supplier had previously installed TWAS pump P-1202 in the
Solids Building. Under this separate contract, the supplier provided an AFD without the enclosure.
This AFD was installed in an existing enclosure by the City. Similarly, for the Contract 6 work, the
supplier prepared his bid to include the AFDs for the new WAS and TWAS pumps without enclosures.
These AFDS would be supplied by others. This was despite the specifications being written that the
new AFDs were to be supplied with new enclosures. Additionally, based on inspection of P-1202 by
the supplier, he is recommending a carbide coating be added to the new TWAS pumps that are to be
installed as part of this contract to provide additional protection to the pumps. The supplier has
discussed this with plant staff during his site visit and staff indicated that this coating should be
included. Eagle is requesting $33,739.00 to complete this work.
The following documents are attached to support this change.
• Letter dated September 9, 2008 from Glenn Grant including the cost breakdown for the changes
(CMR -08).
City of Lubbock, TX
Mr. Soo Koon Soon, P.E.
Page 3
B&V Project 140092.6100
September 9, 2008
The change in contract price associated with these changes is detailed below.
Original Contract Price:
Contract Price with Change Order 01:
Net increase of this Change Order:
Contract Price with all approved Change Orders:
Original Contract Time:
Contract Time change with Change Order 01:
Net increase of time with this Change Order:
Contract Time with approved Change Order:
$43,520,000.00
$43,549,583.00
$117,047.09
$43,666,630.09
1,185 days to Substantial Completion
7 days
21 days
1,213 days to Substantial Completion
Please let me know if you have any questions regarding these changes.
Sincerely,
BLACK & VEATCH CORPORATION
Laura A. Stratton, P.E.
Engineering Manager
cc: Mr. John Kelley, P.E., Parkhill, Smith & Cooper, pdf copy
Mr. Richard Houghton, Black & Veatch, pdf copy
Mr. Gary Smith, P.E., Black & Veatch, pdf copy
Field Order No. 02
Date of Issuance: August 13, 2008
Project: Southeast Water Reclamation Plant, Water Resources Improvement Project
owner: t;ity or Lubbock, TX Owner's Contract No.: #8119
Contract: Contract No. 6
"mractor. Cagle contracting, L.P.
Engineer's Project No.: 140092
Attention:
You are hereby directed to promptly execute this Field Order issued in accordance with General Conditions
Paragraph 22. if you consider that a change in Contract Price or Contract Times is required, please notify
the Resident Project Representative in accordance with General Conditions Paragraph 47. Any
modifications, including a change to the contract price or contract requirements shall be covered by a formal
Change Order executed by Owner and Contractor.
Reference:
IMLS1, IMLS2, IMLS4
(Specification Section(s)) (Drawing(s) / Detail(s))
Description: It has come to our attention by the Resident Proiect Representative that the access hatches
for the Intermediate Lift Station um s are Mn lar a to fit within the space provide9d between the structural
beams in the roof. The s acin between the roof beams is 4'-0". The hatch frame outside dimension is
56% -inches ne.r the data inch vier! uri4h e, .k—i"Z 4,t 4 nnn Y�
We have reviewed several ootions for correction of the hatch size Orae option would be for the larger
hatches to be replaced with hatches with smaller frames that could fit within the 4'-0" beam spacing. Initial
discussions with the a ui ment re resentativ ind at that deli - could take between four to six weeks:
A second option would be to modify the beams in the stab to accommodate the larger framed access
hatches. This change could take between one to two weeks In an effort to minimize the delays we
recommend that the beams be modified to accommodate the larger frames Details are attached that
indicate the revisions required
Refer to Drawing Sheets Section or Detail
Refer to: Specification Paragraphs 01300 articles 1.01 and 1 02 and General Conditions of the Contract
article 22.
Will additional drawings be necessary? (X ) ( )
Yes No
Attachments: IMLS Roof Beam and IMLS Roof Beam Support at Walls
Accepted by Owner:
Date.
Receipt Acknowledged by Contractor: I Date:
f�
0
"
IMLS ROOF BEAM
3/4"=1'-0"
(2) #5 CONT
#4x2'-6" AT 10"
HATCH
w OF • Tfjitt
* .........................:*i
41CHAEL ROLAND HOLDEP
................................
93654
i
SLAB BEYOND
r
REINF BEAM WITH
J.2) J8 TOP AND BOTTOM
3 STIRRUP AT 10"
%00v
PROJECT NAME: SEWRP SHEET: 1
ISSUE DATE: 12 AUG 2008
PROJECT ADDRESS:. REVISIONS:
LUBBOCK, TEXAS
PSC PROJECT #: 01-2680-06
REF i/IMLS4 FOR
CIAO OMk1['
fit`
MICHAEL ROLAND HOLDEF
93654
IMLS ROOF BEAM SUPPORT I AT WALLS
3/4"=1' -OR
00/ Ia
(2) #6X 52 12
CONCRETE WALL
ALREADY PLACED
PROJECT NAME: SEWRP SHEET: 2
ISSUE DATE: 12 AUG 2008
PROJECT ADDRESS:. REVISIONS:
LUBBOCK, TEXAS
PSC PROJECT f 01-2680-06
Eagle Contracting, L.P.
SEWRP - Lubbock Date: August 26, 2008
Job No. 171 Proposal: PCM -02
Work Description: Lower IMLS Wet Well Beams to make room for Access Hatches
Ref. Field Order No.2
war
"Dismantle Deck Forms and
Lower Beams"
Five Man Crew for (5 days)
Crane Operator for (3 days)
Rent of Shoring System - PERI
"Additional Beams Concrete"
Beam Sides Forms
Install Beam Sides
Additional Rebar
Additional Rebar installation
at 17.5 cents per pound rebar
Additional Concrete
60 Ton Hydraulic Crane - Eagle
Fuel, Oil, Grease & Maintnenance
(30% of Rent)
TOTAL LABOR
TOTAL LABOR W/0 BURDEN
LABOR BURDEN/BNFTS - 52%
TOTAL LABOR
TOTAL MATERIALS
TOTAL SUBCONTRACTS
SUBTOTAL
INSURANCE @ 2-1/2%
SUBTOTAL
OH&P@15%
SUBTOTAL
UNITS
200 mhs
24 hhs
0.25 mo
144
0.00
sf
0.00
44
0.00
mh
461.75
640
0.00
Ibs
0.00
640
0.00
lbs
! 112.00
1
0.25
1
Cy
mo
Is
CONTRACT TIME EXTENSION REQUEST = S WORKING DAYS
SEWRP - Lubbock
MATERIAL TOTAL LABOR TOTAL
UNIT PRICE MATERIAL UNIT PRICE LABOR
16.40 3,280.00
20.00 480.00
0.00
0.00
0.00
0.00
0.00
0.00
16.40 721.60
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
4,481.60
0.00
3,455.05
112.00
1
0.00
0.00
0.00
1,847.00
461.75
0.00
0.00
0.00
0.80
115.20
0.00
0.00
0.54
345.60
0.00
0.00
0.00
95.00
95.00
0.00
7,500.00
1,875.00
562.50
562.50
0.00
0.00
16.40 3,280.00
20.00 480.00
0.00
0.00
0.00
0.00
0.00
0.00
16.40 721.60
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
4,481.60
0.00
3,455.05
112.00
1
Detailed Proposal
fStart of Detailed Pr000sall
7. Intermediate Lift Station Shoring
7.1. Intermediate Lift Station Multiflex
Poe Qty. Un Description Art.Nr.
1
24 PC
GT24 GIRDER X 14'
075420
2
38 PC
GT24 GIRDER X 15'
075450
3
6 PC
GT24 GIRDER X 16'
075480
4
16 PC
GT24 GIRDER X 18'
075540
5
50 PC
CROSS HEAD 20124S
028680
6
32 PC
MULTIPROP 625 (246')
027305
7
18 PC
MUL71PROP 250 (98'7
027289
8
85 PC
LEDGER FRAME MRK 150
028350
Total list price
monthly rental! (28 cal. days)
US$ US$Actal
89.41
2,145.84
95.63
3,633.94
102.04
612.24
114.47
1,831.52
23.74
1,187.00
389.19
12,454.08
209.30
3,767.40
132.85
11,292.25
$1,846.21
$36,924.27
Summary Pos. 7. Intermediate Lift Station Shoring
Rental items
Pos. 7. Intermediate Lift Station Shoring
Pos. 7.1. Intermediate Lift Station Multiflex $1,846.21
monthly rental (28 cal. days) $1,846.21
Proposal summary
Rental items
Pos. 7. Intermediate Lift Station Shoring
Pos. 7.1. Intermediate Lift Station Multiflex $1,846.21
monthly rental (28 cal. days) $1,846.21
Tax not included
Weight: 11,417 lbs
Field Order No. 02
Date of Issuance: August 13, 2008
Project: Southeast Water Reclamation Plant, Water Resources Improvement Project
owner: miry Di LUDDOCK, I
Contract: Contract No. -6
Contractor: Eagle Contracting, L.P.
Owner's Contract No.: #8119
Engineer's Project No.: 140092
Attention:
You are hereby directed to promptly execute this: Field Order issued in accordance with General Conditions
Paragraph 22. if you consider that a change in Contract Price or Contract Times is.required, please notify
the Resident Project Representative in accordance with General Conditions Paragraph 47. Any
modifications, including a change to the contract price or contract requirements shall be covered by a formal
Change Order executed by Owner and Contractor.
Reference: IMLS1, IMLS2, IMLS4
(Specifrcatiorf egtion(s)) (Drawing(sy/ Detail(s)J
Refer to Drawing Sheets Section or Detail
Refer to Specification Paragraphs 013,00,articles 101 and 1.02 and General Conditions of the Contract
article 22.
Will additional drawings be necessary? (X ) ( )
Yes No
Attachments: IMLS Roof Beam and iMLS Roof Beam Support at Wails
Accepted. by Owner: I Date:
Receipt Acknowledged by Contractor: I Date:
1'-2"
1--
IMLS ROOF BEAM
3/4"=1'-0"
(2) #5 CONT
#4x2'-6" AT 10"
HATCH
j ......................:...
/;MICHAEL ROLAND HOLDER
.................................
fol . 93654
SLAB BEYOND
BEAD WITH
TOP AND BOTTOM
RRUP AT 10"
PROJECT NAME: SEWRP SHEET: i
ISSUE DATE: 12 AUG 2008
PROJECT ADDRESS:. REWSIONS:
LUBBOCK, TEXAS
PSC PROJECT #:01-2680-06
REF 1/IMLS4 FOR
CI AD D[9&IC
IMLS ROOF BEAM SUPPORT AT WALLS
3/4'=1'-0"
*100
(2) #6x 52 12
CONCRETE WALL
ALREADY PLACED
PROJECT NAME: SEWRP SHEET: 2
ISSUE DATE: 12 AUG 2008
PROJECT ADDRESS:. REVISIONS:
LUBBOCK, TEXAS
PSC PROJECT #:01-2680-06
MICHAEL ROLAND HOLDER
.................................
93654 _ .4
IMLS ROOF BEAM SUPPORT AT WALLS
3/4'=1'-0"
*100
(2) #6x 52 12
CONCRETE WALL
ALREADY PLACED
PROJECT NAME: SEWRP SHEET: 2
ISSUE DATE: 12 AUG 2008
PROJECT ADDRESS:. REVISIONS:
LUBBOCK, TEXAS
PSC PROJECT #:01-2680-06
Yahoo! Mail - g.grant@eaglecontractinglp.com
Page 1 of 1
" Print - Close Window
Date: Tue, 12 Aug 2008 13:31:20 -0700 (PDT)
From: "glenn grant"<g.grant@eaglecontractinglp.com>
Subject: SEWRP - Lubbock (IMLS Pump Hatches)
To: "Laura Stratton" <stratbonla@bv.com>
Dear Laura,
I have attached a copy of Parkhill's Beam Drawing and two Hatches Drawings from J&L.
The dimension between hatches will be different than parkhiii drew. Is this a problem?
Thank You,
Glenn Grant
Eagle Contracting, L.P.
Attachments
Files:
if IMLS_Pump Hatches_8_12_08.pdf (154k)
http://b5.mail.yahoo.com/ym/eaglecontractinglp.com/ShowLetter?box=Sent&MsgId=3080_8760577 1959 ... 8/12/2008
11
C
pro)"
PWJOuk Smith & 22MMAG.
Engineers • Architects v Planners
Job No,--. DW
LubbbOk• El Paso v Midland • Amarik ■ Odeaft cab. my By shy
of
Y�
TO/T0 3SVd 9NI10VN1N00 3-EV3 T0EZ910ZL6 9T:ET 800Z/ZT/80
PDF processed with CutePDF evaluation edition www.CutePDF.com
eF P
'SS N
C
S3
3
O
j� g
D=R���/h��J
Do
P
3
Iz
O
q a
SO a
to af)
-15.0
<
n n a
3
O =P rpt
qm h:rn
amO o m
m P m A
S•ba
•07
n O w m P Z
O *3 k
O01130
P N W a +K
O.h
O
c+ h
713
AK -1
4+rD
3 C
P P D S
n
m A 7 3 S
W p
SSP
kn ^C 3
4y
X- lo h.+sm
G
-O
r m
3q
a
L Q y
h tn< Q
p�`GO
m 111 3 P a
UI SO
a
21 m
3_y1
O' 0 P cr N= p
A33M0
pp o _S n`
CD—:3Ln0P-j
n 13
��
W�1S
�tOtfl
pN1
K a3
3 h i
S3 1
"+pm
3 3
z-•nS cnN -P)M
o• o S
I cn ^� to
LA -I m
�O.
mO.
U3N
P
rim
?- e+YI
m ;�
10ty�
�p 0
3Q.
!0
.Oa•SIT A^-
A �O f1
y £ 6
A�OmtrP 1
I UI `< 3 a
—02'
3 W
.AQ
0 P
+r
f01
0am-00
9.
O•
'+Sn r.n1�
I ry_
'i P
•A+'S
•O S
r0
O m
��
P
•c4 ru -<
YW-?
tW
X
N D
O'
3 ry
3 ry
Sa
3
O ��{.
P C P
."On C
'0
SO
rF"4
N M
u,? m
'F
n.+
SSO
3 m�
!D O IA *0
m Pi
P rF
p.1
P
SIn337..
P_ 09 I
m=1
f0 m m P
ILIO
0K
M3-
1P�'
y,m.0
c+ -D
0:S
-ft1p3�3Q-y10j0
3man
'nN
O.
ysn
^Q
q
a
Wpoj n P
�eF�3
1
mP
O n x
3 hp
P
OT N
PP
m
PPS
'h 3
ap
1e
G
N
r
3
eF
c
/0 7
P m a
m
<
COO
ry
,�—}
S
Q,
Q
O
n 0
-~-f
-{
PDF processed with CutePDF evaluation edition www.CutePDF.com
FA
b
V
OA y F7 r--
o&aF71
efTl
Ob D
z�� Z
1 r•. i
1' rnrn 1 , Y
n� o C:) D
Rhe
-VM.
pa
N r�, CnD ^o, � o � r•co co $ � E� '� ��R'+ r; muco
cli
00m cn� g w �g�Fs o c ate $ a
IAq
r• z z R
a�$—t o OZ �g�°ad, ocr
'g tet' $`�To° �'
J3 A
R z Znn� o as a�agg o o' ��,-�
Ln
a,p
L4 �` S m0y C aro
oi� —� r�rrNg°
C,( cis+ am,. < F
September 9, 2008
Black & Veatch Corp.
9441 LBJ Freeway - Suite 114
Dallas, Texas 75243
Attn: Ms. Laura Stratton
RE: Southeast Water Reclamation Plant Improvements
Contract ITB # 07 -730 -BM — Project # 92126
The City of Lubbock, Texas
Black & Veatch Corporation
Subj.: Proposed Contract Modification (PCM -03) per Field Order No.6
(Add 6" Excavation and 6" Crushed Rock Bedding with Filter Fabric and Poly
Cover under BNR#3's Slab)
Dear Laura,
Eagle Contracting, L.P. requests the Total Lump Sum Amount of Thirty Nine Thousand
Nine Hundred and Fifty Dollars ($39,950.00) to cover the cost of this work as defined in
Field Order No.6. Please note that we have removed the extra excavation and Bedding
outside of the Slab. We also request seven days of Contract Time Extension for this
work.
XGrant
egards,
Project Manager
cc: File (Proposals), Lubbock — Soo Soon, B&V Field — Rich Houghton & Field
P.O. Box 1600 0 Keller, Texas 76244 0 Metro (817) 379-1897 0 Metro (817) 379-0610 Fax
Eagle Contracting, L.P.
SEWRP - Lubbock Date: September 9, 2008
Job No. 171 Proposal: PCM -03
Work Description: Add 6" Crushed Rock Bedding under BNR Basin #3
Ref. Field Order No.6
MATERIAL TOTAL LABOR TOTAL
UNIT PRICE MATERIAL UNIT PRICE LABOR
ACTIVITY QUANTITY UNITS SUBCONTRACT $ $
Add 6" Crushed Rock Bedding
i
7,347.20
0.00
7,347.20
LABOR BURDENIBNFTS - 52%
under BNR Basin #3
Note: this work will require an 5 man
448.00
mhs
3,820.54
TOTAL LABOR
16.40
7,347.20
crew with 3 equipment operators =8
t
11,167.74
TOTAL MATERIALS
men at 8 hours per day for 7 days at a
c
22,724.20
TOTAL SUBCONTRACTS
man hour rate of $16.40/mh.
0.00
SUBTOTAL
6" additional structural excavation
429
cys I
33, 891.95
0.00
0.00
Haul Excess to Stockpile
601
tys
3.00
1,803.00
0.00
Spread Excess at Stockpile
429
cys
34,739.25
0.00
0.00
5210.76
0.00
0.00
Filter Fabric
30063
sf
0.08
2,405.04
0.00
Crushed Rock Bedding
858
tons
15.50
13,299.00
0.00
Poly ontop of Rock
27000
sf
0.03
810.00
0.00
0.00
0.00
Construction Equipment:
0.10
mo
9,500.00
0.00
950.00
0.00
0.00
PC 480 Track Hoe - Eagle-1wk
Kawasaki Rubber Tire Load-Eagle-2wk
0.10
mo
4,600.00
460.00
0.00
Dozer - Hertz - 1 wk
0.10
mo
3,300.00
330.00
0.00
Smooth Drum Roller -ASCO - 1wk
0.25
mo
4,416.00
1,104.00
0.00
Bobcat to spread Rock - Hertz - 1wk
0.25
mo
1,178.50
294.63
0.00
Fuel, Oil, Grease and maintenance -
1 j
Is
3,138.63
941.59
0.00
30% of Rent
I
0.00'
0.00
0.00
0.00
Small Tools (5% of Labor)
1
Is
7,347.20
326.95
0.00
0.00
0.00
0.00
0.00
'TOTAL LABOR `
TOTAL LABOR W/O BURDEN
!
i
7,347.20
0.00
7,347.20
LABOR BURDENIBNFTS - 52%
I
3,820.54
TOTAL LABOR
11,167.74
TOTAL MATERIALS
22,724.20
TOTAL SUBCONTRACTS
0.00
SUBTOTAL
33, 891.95
INSURANCE @ 2-1/2%
847.30
SUBTOTAL
;
34,739.25
OH&P@15%
5210.76
SUBTOTAL
zo orn nn
CONTRACT TIME EXTENSION REQUEST = 7 WORKING DAYS
SEWRP - Lubbock
Field Order No. 06
Date of Issuance: August 26, 2008
Project. Southeast Water Reclamation Plant, Water Resources Improvement Project
Owner: City of Lubbock, TX
Contract: Contract No. 6
: Eagle Contracting, L.P.
r`s Contract No.: #8119
Englrieees
:140092
Attention:
You are hereby directed to promptly execute this Field Order Issued in accordance with General Conditions
Paragraph 23. If you consider that a change in Contract Price or Contract Times is required, please notify
the -Resident Project Representative in accordance with General Conditions Paragraph 47. Any
modifications, including a change to the contract price or contract requirements shall be covered by a formal
Change Order executed by Owner and Contractor.
Reference: A84-12, MD3
(Specification Sections)) (Drawing(s)1 Detail(s))
Will additional drawings be necessary? (X ) ( }
Yes No
Attachmenta,. Figure F06-1 showing the termination of the material at the RNR slab
Accepted by Owner: _ Date:
Re.deipt.Ackno ed b ontractor.: I Date:
9 '9- Zd3
f -ft -I SANDSTOJV,5
GROWULAR FILL.
F06-1
3/8"W_0"
OF-!
T* : ' '•�4tls* 1
6 o . ... . . . . . ..
A.STRATTON
01011,,
mqml�
10I03/� 2008 11:36 8173790610 EAGLE CONTRACTING LP PAGE 02/04
• wn AUG 0 5 2008 (2)
! o ORIGINAL INVOICE
PROGRESS BILLING
71x6!06
THANK YOU FOR RENI'zNG FROM HERTZI
CUSTOMER NUMBERc 0135262 RES/QUOTE NUMBER: 17340499 INVOICE NUMBER: 2,4596396.001
EAGLE CONTRACTING LP
PO NUMBER:
NEED
P 0 box 1600
JOB NUMBER:
1 . WATER PLANT
KELLER, TX 702441600
ORDERED BY:
SIQNED BY:
RON BRAY
DELIVERED BY,
NERC
RENTAL START DATE:
6130143 71:08
CLOSED -BY:
$ALIS REP:
DICKIE DAVIS
SHIPPING ADDRESS:
HERTZ LOCATION: 490
RENTAL DAYS:
28
WATER PLANT
3424 E. SLATON HWY
INVOICE FROM DATE:
6=108
BOTH & JAVA
LUBBOCK. TX 79404
INVOICE THRU DATE:
7/24/0$
LUBBOCK, TX 79401
Ph: 806.746.3600
Fax:805.745.4040
PAYMENT TERMS ARE NET 10 DAYS
Customer Is responslbiv /or FUEL. RATE. DAMAGE and
CLEANUP FEES,
LATE CHARGES MAY APPLY
FOR CUSTOMER SERVICE AND BELLING
INQUDUES CALL 1-80045d-f►492
93= IPAYl18�l1'i" Y'Oe
HERTZ EOUIPMENT RENTAL CORPORATION
P.O. BOX 850280
DALLAS. TX 75285-0280
ADJ
RENTAL CHARGES 3300.00
DELIVERYIPICK UP 180.00
TAXABLE CHARGES 3450.00
TAX 353.55
TOTAL CHARGES 3,65
Job --j i. phm...L
Type
-,Owe
SMUB
RM
tlbndalr �...
i7sads Due ^ Z
TOTAL
3300.00
4450.
1893"0fr
Qty agui,pme:nt 4 Mrs/ xi.n Hour nay week 4 week Ameuat
1 DOZER/90-99 XP/STANDARD TRACK/DSL 9/ 420.00
200095025 Make: DSERE MOd01: 550,7 Ser #: T05s0SX1140.12
HR O=T: 1929. MO SR IN: FM CHC;:
420,00 995.00 336:0.00 3300.00
For GREAT DEALS on USED ECUIPMINT • visk us on -sins at y_wv ,l . gylp,Fq
Detach and send bottom portion with payment.
LAW CONTRACTING L► 712E/ds Owtom4r Number, 0135202
P 0 BOX 1000 Invoice Number: 23596366-001
KELLER, TX 70244.1800
PLEASE PAY THIS AMOUNT:
r-�
�. ,.tom...
1 Of UZI/ zt3utj 11: db 131 I:.i (ybbl b EAGLE CONTRACTING LP PAGE 03/04
SM INS
LuesoOk, TEM ANA14LLo, TWCAe OMBA, TVA$ WICHITA FAUA rkXgg
PHONLN: soea4a-aW PHONE: eM99488e PHONE: 431 071.2823 PHONE: 24WW,2728
C4,AG64 0FAX: 1104048.1488 FAX; 40111372•( 01G FAX: 482!357-8979 FAX: 940(8894729
PERWfTON. TOM
DAL4AAT, Tr
*MONE eo0�43 PH MIDLAND,
ONE 432rb83 PHONE: ezel►a2 a7a�e O 9052441846 PHONE! LIC.ri0 AO
/�**001atafl� ABLI19 vela FAX: eool4mvp FAX; 4UV8.$W PAk, 57,wal-9231 FAX: OW,.14418a1 FAX: 3'25!88&4740
»'fAyLlE3tiED 1�pp
26073
custc�mar I NV 0I C E I nva f Ce P
9
Document 1
R91405
Sold To RECD JUN 0 2 2008 Ship To
EAGLE CONTRACTING CORP. RON BRAY
P.O. BCK 1600 EAGLE CONTRACTING CORP.
KtLLER TX 76244 GUAVA STREET `
LUBBOCK TX 77777
6171379-1897 817/379- i 897
ShiP Via ASCO TRUCK
------------ --------------------- ------- -w------_----_w---_--.....,.....____..__.�.._�
Br-Trk- Make w-_Modeel Sert� l Equipment Motor Sla Customer P.C.
-----------------------
----,—w------- ------ --"'Y------- _--- -----------
w— rww..ww ws—�.—r.—ww.ww— —_ ww
00 i
45 SUAWAs
--IF----_-_-----,w-_--.y----,_-__,YrrwY----w-_-----.w.------w
-t^ Ship 004cniption----------------------------- ------------
Ord
---•---------------- ...»-.�-�--_ Each Amount
�---------rr.,.r.,.n,---------.wa..—+.,.------ w---------
Taken By JOE ROCHA
Rental Contract R5►1405
'Perlod= 5/Z1/08 Thrw 5/17108
1 ; 80 600302 BW211 PD -3 9015800 t 104 9 4.416.00 4-416.00
90"AG 'V I HRATORY SINGLE .DRUM
1 ENVIRONMENTAL FEE 44.16 44.15
1 PICKUP/DELIVERY .00 N/C
NON-TAXABLE
MUNI ,JOB r .00
j Phase
Type .,.., ,_,-� . Code � 2.
Ar nt L
F+MT DUE ON DATE Or INvoice. ANNUA!NR
EaT OF &Z
CIL!„ BE CHARGED STARTINQ 30TH DAY AFTERDUg: DATE. 1
--------•------------------------------- _--------R_..__-----..-----w-------_
1MEiiAlr Total 4, "0.1 b
cRSi�413iT(8'W€—.`.... __.__�.__--_......"TERIP►�i�fEi"PI�BIPT'aF'fli'CldiC�---
.uatornere *009001`100 of r'"* goodE and aewraes, owtomer aareu to hee rad and eaaa;t all riens, Remit to: AaCta
is and 00ndrtlons as Wad bore and eA the re�uss arch haraed. P.O. Box 3889 . Lubboek. Texas 78452
ORIGINAL COPY
1 @/ 03! 2088 11:36 8173 �ybb1 b t1i4�L t t.�1N 7 KAl; i 11W LY t' t*= 041 U4 '
FINAL 811.1,
� D JUL 16 2008
ORIGINAL INVOICE
4krfj
7r 1 oroa
THANK YOU FOR RENTING FROM HERTZ!
CUB70MIM NUMBER; 0135842 RESrt1UOTE NUMBER, INVOICE NUMBER: 23546208.001
EAGLE CONTRACTING LP
PO NUMBER:
17124921
P 0 BOX 1800
JOS MUMMER,
1 - WATER PLANT
ORDERED BY:
DAVIS, DICKIE
RELLER, TX 76244.1800
SIONEO BY:
DAVIS, DICKIE
DELIVERED BY:
NERC
RENTAL START DATE:
8113101E 13;59
CLO9FED BY:
JAMES 9, OWENS
SAL28 REP:
DICKIE DAVIS
SHIPPING ADDRESS:
HERTZ LOCATION: 450
RENTAL DAYS;
27
WATER PLANT
2424 E. SLATON HWY
INVOICE FROM DATE:
6)13108 14:00
50TH A JAVA
LUBBOCK, TX 79403
INVOICE THRU DAYS:
7109MB 17:00
LUBSOCK. TX 79401
Ph: $06.748.3500
Pax:806-> 4!4 4046
ORIGINAL
ADJ TOTAL
PAYMENT TERMS ARE NET 10 DAYS
RENTAL CHAROft
1175.00
1175,00
OTHER CHARGES
3.50
3.80
Custanrr In rasppnslble for FUEL. FLATS, DAMAGE and
DELiVERY,PICK UP
75.00
p
CLEANUP?919.
TAXABLECHARd3S
1253.50
7253.r�p
LATE CRARGES MAY APPLY
TAX
128.44
FOR CUSTOMER SERVICE AND RML,ING
TOTAL CHARGES
1381.54
LNQUMMS CALL 1-800.436-6492
DO=
HERTZ EQUIPMENT RENTAL CORPORATION
P.O. BOX 650280
DALLAS, TX 75205.0280
104 V4t "j V, .' 5
NET DUE 1381.941
_Qty Equipment * j b +� t� Hxs/ A4im Stour bay, Wank 4 Week Aftm=t
1 CRAWLB'R WADER/1/2 YD/G=RAL/D8L S/ 1SO.00
206035034 Mekat TA=UCiHj Modal: TLI30 Ser *: 2!303401
Houro Free:
FIR OUT: 1419.200 HR .'N: 1449,600 TOTALS 37.400
FREE: 16C.000 =CESS; 0- HRS CRa, 3.672
ENVIRONMENTAL, RECOVERY FSES 6626000001 job
DATE Typ$
7110/08 HERTZ CiARGE Typvl�t.
status
Vendor
dao DLiS
160.00 395.00 1175,00 1175.00
0 40 180
.1 ! 3.50
Cade 1.81.94
For GREAT DIALS an USED EQUIPMENT . wlslt us ori.Ilne at www.hertae M,
D•teah and Send bottom portion with paymam,
EA31.E CONTRACTING LP 7110108 Customs) Numbar: 0136262
P O BOIL loco Invoice Numbor: 23549209-001
KILLER, TX 76244-1600
PLEASE PAS' THIS AMOUNT: 1381,94
i
REQUEST FOR INFORMATION
PROJECT: SOUTHEAST WATER RECLAMATION PLANT IMPROVEMENTS PROJECT NUMBER:
OWNER: THE CITY OF LUBBOCK, TEXAS 92126
CONTRACTOR: EAGLE CONTRACTING LP 171
ENGINEER: BLACK & VEATCH CORPORATION
REFERENCE DATA.-
Contractor
ATA:Contractor RFI No. 036 Spec Section N/A Page No. N/A Para. N/A
Drawing No. CY9 & E2 and Sketches
CONTRACTOR REQUESTS: ® Information ❑ Interpretation ❑ Clarification
We have found that the existing Duct Bank south, west and north of the West end of the Headworks
conflicts with the 36" Headworks Discharge Piping (48" IMLS Influent). The top of the new 36' Piping is
at 3148.00 and the top of the 30" thick Ductbank is at 3149.34. How do you want to re-route this piping?
CONTRACTOR'S PROPOSED SOLUTION:
REQUESTED BY: DATE: 08/05/08
ENGINEER'S RESPONSE: ❑ Information ❑ Interpretation ® Clarification
For the items described above or in the attached material referenced:
The pipe should be lowered 30 -inches to accommodate the duct bank.
See attached sketch.
RESPONSE BY: Laura Stratton DATE:08/08/2008
S:MvWF E"Is Contacling ResWb FNes1171- Lubbock W WTP%RF1's%RFl-036 Confllcs 43 IMLS Pipe and Electdcal Ductbank.doc
rqY wN:MM aMt lf..Y:rNrx J•�, u�� '�vw>YA'r�
w 2ij •v .2?%s. ES37Z_40�h%Zdfm �`•1HU 83LYM 1.Sb8117
00+8 Y1S 3Ntleq,M
I •e< ys rcw r
I • $ 3u 00.0 r[ II ■ y
f � n
$ 8
Ldr dsf .a - wacw nd »a
gs
3 ti
;8
�,•e �.. �_ i 9
f .ae•v vo.o ru fe
8 Y RY
I
-
� � n •ordaEed te•eduEutii .
fb .ww ero. a re'�_ R g
W� � Ltltidtee.)eL •.deau.,r R 8
aLe .dr • n n,.z
R 'dime vp
fNr i)I�. 1 1 • Y{
%rGNd LVOd .IL X3 ' LL♦E Yyq ,y
«
' � O<♦2 Yld fN
r:. g" waA na rd I
�.L eua or.a ud
TILs- . td
y
} s
C
a•r .c..v uer.E rad ram �� h
R fF0 Y13 M qe
� F xLr dtt .x tadd♦d rl txl O-R
S y�
"L i eaeeEui�s'�i[.d d Z
~ �f
yy^9 wl,w eaed .r= p - diw ras 2211
Ls .c..Y r7u.=ras raLLu `8�4II .ir di r g .. =EY
lorrldwr er
3< d.�Yrra[ aari,
8 8
J .sr ao -i w wd
e j 8
i � 8
L sr. nEad res re , i �� • e
Od'eb . fi'dd1dWW /"
8 II 00♦B Y1S 3N77w ty" Y R
08/05/2008 09:49 9724752301 EAGLE CONTRACTING PAGE 02/03
W"
00 700
OO
O CD
� 000
000
OOOOOe I 0000
000040 0000
000000 0000
O C`7 CD 0
Wj�j�ja(ri�j�j�(110jT!
rr
'
rMKI�EVf` ut7 arAPPbv �WIDItsr�TlWf
I411'
BLAcKa vK-arck
Sm x w eu.4 A vnsu c.�q, 26- — ..,.
08/05/2008 09:49 9724752301 EAGLE CONTRACTING PAGE 03/03
aaan
alm •
f
o
aim
nr
a1f4 a
S
Irrn :t
Afar
.do
A'
1 0.0o who ,.wo
L �� ACV."
V0 i_ r.Mtwhi, R NRMAON 1.1' OM
famVlNfL A ' am. NANrNA7 to
� S rNSTAiI Nmv p.
h114'1 �f��> iuh
-r% pRD w 0
31t.0
4$'._PRXX4RY USTM&MON STAUDVRB
Mu IST
NON$: f'1201
Vdart 1'-10,
am
RiNW
frac Z-40
48' zNZR-WArAM_LTFr STATION
�NFLU6NT
Norrrz: r' -an'
rffifrt f• fog
Pr00
uwv rwuo 0t40
0
NMI -•^ ON
MMATE, AE7nNA, Z M.
CWMM b 1 1l2' "1 AS
A@TALL M* P1P$.
ae'
i
aaan
alm •
f
o
aim
nr
a1f4 a
S
Irrn :t
Afar
.do
A'
1 0.0o who ,.wo
L �� ACV."
V0 i_ r.Mtwhi, R NRMAON 1.1' OM
famVlNfL A ' am. NANrNA7 to
� S rNSTAiI Nmv p.
h114'1 �f��> iuh
-r% pRD w 0
31t.0
4$'._PRXX4RY USTM&MON STAUDVRB
Mu IST
NON$: f'1201
Vdart 1'-10,
am
RiNW
frac Z-40
48' zNZR-WArAM_LTFr STATION
�NFLU6NT
Norrrz: r' -an'
rffifrt f• fog
Pr00
uwv rwuo 0t40
0
NMI -•^ ON
MMATE, AE7nNA, Z M.
CWMM b 1 1l2' "1 AS
A@TALL M* P1P$.
ae'
August 28, 2008
Black & Veatch Corp.
9441 LBJ Freeway —Suite 114
Dallas, Texas 75243
Attn: Ms. Laura Stratton
RE: Southeast Water Reclamation Plant Improvements
Contract ITB # 07 -730 -BM — Project # 92126
The City of Lubbock, Texas
Black & Veatch Corporation
Subj.: Proposed Contract Modification (PCM -04) per RFI -036
(Lower the new 48" IMLS Influent Piping at the Headworks to miss the Existing
Electrical Duct Banks)
Dear Laura,
Eagle Contracting, L.P. requests the Total Lump Sum Amount of Twenty Six Thousand
Four Hundred and Ninety -Four Dollars ($26,494.00) to cover the cost of this extra work.
We also request three days of Contract Time Extension for this extra work.
This change will delete the conflict between the two electrical duct banks and the new
48" IMLS Influent Piping at the Headworks.
With Kindest Regards,
G enn- rant
Project Manager
cc: File (Proposals), Lubbock — Soo Soon, B&V Field — Rich Houghton & Field
P.O. Box 1600 Keller, Texas 76244 Metro (817) 379-1897 Metro (817) 379-0610 Fax
Eagle Contracting, L.P.
SEWRP - Lubbock
Date:
August 28, 2008
Job No. 17i
Proposal:
PCM -04
Worts Description: Lower 48" IMLS Influent Piping to go under Existing Electrical Duct Banks
Ref. RFI -036
MATERIAL
TOTAL
LABOR TOTAL
UNIT PRICE
MATERIAL
UNIT PRICE LABOR
ACTIVITY
QUANTITY
UNITS
SUBCONTRACT $
$
Lower 48" IMLS Influent PIR2 to go
under Existing Elec.Duct Banks
Note: This work will take a (7) man
crew (3) days -168 mhs x $16.40/mh
Additional Pipe Excavation
144
cy's
0.00
4.00 576.00
Hand Excavation @ two Duct Banks
6
cy's
0.00
30.00 180.00
Support Duct Banks @ Crossings
2
ea
0.00
200.00 400.00
Feed Pipe under Duct Bank -
19
If
0.00
35.00 665.00
Added difficulty In pipe Installation
0.00
0.00
Additional Pipe Backfill
150
cy's
0.00
6.00 900.00
Purchase changes In Pipe from -Hanson
1
Is
15,000.00
0.00
15,000.00
0.00
0.00
Kobelco 480 Track Hoe - Eagle
0.15
mo
9,500.00
0.00
1,425.00
0.00
0.00
Kawasaki Rubber Tired Loader - Eagle
0.15
mo
4,600.00
690.00
0.00
Walk Behind Compactor - Hertz
0.25
mo
1,400.00
350.00
0.00
Fuel, 011, Grease & Maintenance -
1
Is
2,465.00
739.50
I 0.00
30% of Rent
i
0.00
0.00
Small Tools (5% of Labor)
1
Is
136.05
0.00
136.05
0.00
0.00
0.00
0.00
0.00
18,340.55
TOTAL LABOR
2,721.00
TOTAL LABOR W/0 BURDEN
0.00
LABOR BURDEN/BNFTS - 52%
2,721.00
1 1,135.92,414.92
TOTAL LABOR
TOTAL MATERIALS
18,340.55
TOTAL SUBCONTRACTS
0.00
SUBTOTAL
22,476.47
INSURANCE @ 2-1/2%
561.91
SUBTOTAL
23,038.38
OH & P @ 15%
I
f
3,455.62
SUBTOTAL
26,494.00
0.00
TOTAL
1 26,494.00
CONTRACT TIME EXTENSION REQUEST = 3 WORKING DAYS
SEWRP - Lubbock
Yahoo! Mail - g.grant@eaglecontractinglp.com
"30PD.-OLSMAL115vs1
From: "T. Scott Baugh` <tsbaugh@baughinc.com>
To: "'glenn grant'"<g.grant@eaglecontractinglp.com>
Subject: RE: FW: SEWRP - Lubbock (RFI -036)
Date: Wed, 27 Aug 2008 11:32:44 -0500
Page I of 2
Print - Close Window
Since the pipe for IMLS was all build some of the changes are additonai materials and some are modifications to materials that
have already been built. When I made the estimate I didn't know for sure what could be salvaged and what would have to be
remade. Based on the release drawings the cost will be $15,000.00 for the followin changes:
Sheet 16A
8233 - 36" 15.00° Bend, w/ Bell Prepped for JH (additional materials)
B235 - 36" 15.000 Bend, w/ Bell Prepped for JH (additional materials)
8236 - 36" 15.000 Bend, w/ Bell Prepped for JH (additional materials)
8238 - 36" 15.000 Bend, w/ Bell Prepped for JH (additional materials)
BX88 - 36" B-303 Short Pipe LL = 17.26' (modified from BX88 LL=28.25')
BX234 - 36" B-303 Short Pipe LL = 8.00' (modified from BX88 LL = 28.25')
BX92 - 36" B-303 Short Pipe LL = 21.01' (modified from 92 LL = 32.00')
BX237 - 36" B-303 Short Pipe LL = 8.00' (modified from 92 LL = 32.00')
6 Ea. 36" Snap -Rings (additional materials)
Sheet 16
BX83 - 48" B-303 Short Pipe LL = 8.21', w/ 0.480 Bevel (modified from BX83 LL = 8.25', w/ 1.400 Bevel)
Sheet 15
B77 - There is no change to this pc, however it will now be rolled down 0.920.
Sheet 24 - this is not related to the change in the IMLS piping.
BX162 - revised lay length to match the contact drawings stationing.
Please let me know if you have any additional questions. In a nut shell the $15K pays for the 4- New 36,015.00* Bends and
additional snap -rings to change the elevation of the line. Plus some additional expense to modify pipe that had already been
fabricated to the new lengths required to install the bends.
Thanks,
Scott
--Original Message -----
From: gienn grant[maiito:g.grant@eaglecontractingip.com]
Sent: Wednesday, August 27, 2008 10:42 AM
To: tsbaugh@baughinc.com
Subject: Re: FW: SEWRP - Lubbock (RFI -036)
Dear Scott,
Which pieces of pipe have changed (that make up the 18K of change? is it every piece that you show on your drawing?
Glenn Grant
Eagle Contracting, L.P.
"T. Scott Baugh" <tsbaugh@baughinc.com> wrote:
Resending ..... price for change is $18,000.00
-----Original Message-----
http://b5.mail.yahoo.com/ym/eaglecontractinglp.com/ShowLetter?box=Inbox&MsgId=7323_31823498 35... 8/27/2008
REQUEST FOR INFORMATION
PROJECT: SOUTHEAST WATER RECLAMATION PLANT IMPROVEMENTS PROJECT NUMBER.
OWNER. THE CITY OF LUBBOCK TEXAS 92126
CONTRACTOR. EAGLE CONTRACTING LP iT9
ENGINEER: BLACK & VEATCH CORPORATION
REFERENCE DATA:
Contractor RFI No. 036 Spec Section N/A Page No. N/A Para. N/A
Drawing No. CY9 & E2 and Sketches
CONTRACTOR REQUESTS: ® information ❑ Interpretation 0 Clarification
We have found that the existing Duct Bank south, west and north of the West end of the Headworks
conflicts with the 36" Headworks Discharge Piping (48" IMLS Influent). The top of the new 38" Piping is
at 3148.00 and the top of the 30" thick Ductbank is at 3149.34. How do you want to re-route this piping?
CONTRACTOR'S PROPOSED SOLUTION:
REQUESTED BY:
DATE: 8/05/08
ENGINEER'S RESPONSE: ❑ Information ❑ Interpretation
For the Items described above or in the attached material referenced:
The pipe should be lowered 30 -inches to accommodate
See attached sketch-
® Clarification
the duct bank.
RESPONSE By. Laura Stratton DATE:08/08/2008
SiSand8E291e Contracting FHUU* FW171 - Lubbock W WrP%RF1`$%RFW38-Cwff* 48 IMLs Ptpe and 8"OW Ductbank.doo
I
Sim -rms
y8 3 A
MOV OR.
S37rp
AOAILI$
.ON IN&=
&"SAO" 114 Nazlww7m W1,W
I
Sim -rms
y8 3 A
MOV OR.
08/05/2008 09:49 9724752301
tAGLE CM47WTING PAGE 02/03
�Q Q(2) (D
Sao Quo
� 00
e oao
oonoo0
000
000c�
oa0000
oQQo
� 000000
oaoo
Oooe
mill
i
08/05/2008 09:49 9724752301 EAGLE CONTRACTING PAGE 03/03
i
42' PRMARr osstl?XWYt0N 9Tf1U047/AE
vm�r7 1••1Dt
me@_
am
t
9100
�IY�l-YPL:
Of�O
r
re a 41.00—�
+w 3 y 91e0 o7ae o�10 f�10 " 1.so Zoo s+eD oo anrar � popr-
MATS,
Afro i : MM
caxrnu a i f/t av AS
rdN.�1R1• b ARMCO f4. 00711 ravm 1/9Y PlAB.
L911'flpl. a 59 M )MAD M
S 74TALL 48• ZNTFJ�i�fP_LM r T 30• I
pp �I
v"�ir r;: oA
314P. 1�D)
r�aD
m
ai7D ,
4110 t
A
r
r,
ono
rano
AM
42' PRMARr osstl?XWYt0N 9Tf1U047/AE
vm�r7 1••1Dt
me@_
am
t
9100
�IY�l-YPL:
Of�O
r
re a 41.00—�
+w 3 y 91e0 o7ae o�10 f�10 " 1.so Zoo s+eD oo anrar � popr-
MATS,
Afro i : MM
caxrnu a i f/t av AS
rdN.�1R1• b ARMCO f4. 00711 ravm 1/9Y PlAB.
L911'flpl. a 59 M )MAD M
S 74TALL 48• ZNTFJ�i�fP_LM r T 30• I
pp �I
v"�ir r;: oA
314P. 1�D)
August 27, 2008
Eagle Contracting
P.O. Box 1600
Keller, Texas 76244
Attention: Mr. Glenn Grant
SUBJECT: LUBBOCK, TEXAS
Southeast Water Reclamation Improvements
Hanson Job No. 08-022B
Gentlemen:
■N■
was
"' Hanson
Hanson Pipe,& Proem% Inc
South Central Region
1003 R MacArthur Blvd
Grand Prairie
TX 75050
Tel 972 262 3600
Fax 972 264 6236
www hansonpipeandprecastcom
Enclosed are one copy of our drawings No. 08-0228, sheets 15, 16, 16A, 24, D18A, D19A,
D22A, D24, D44A, D45A, D55, which show the material we are furnishing for the subject
project. Please arrange for the distribution of the enclosures.
These drawings have been approved and issued for the manufacture of the material as
shown.
Please note the following items:
1. On sheet 15, we have revised the profile of pieces B77 thru BX81 to reflect the profile
changes requested by the consulting engineer.
2. On sheet 16, pieces BX88 thru A90, 92 thru TP97, and JH4 thru JH7 have been moved
to sheet 16A.
3. On sheet 16, we have revised the bevel angle and laying length of piece BX83 to reflect
the profile changes requested by the consulting engineer.
4. On sheet 16A, pipe #92 has been deleted, pieces B233 thru 8238 & BX92 have been
added, and BX88 has been revised to reflect the profile changes requested by the
consulting engineer.
was
r*•
8"Hanson
Page 2
08.0228
If you have any questions In regard to delivery, please contact Jerry Vaughn at
9721262-3600.
Please feel free to call on us whenever we may be of further assistance.
Very truly yours,
Hanson Pressure Pipe
r
Jimmy Torres
Senior Engineering Coordinator
Enclosures
cc: Baugh & Associates, Attn: Mr. Scott Baugh, 1 copy
VIU3Of r�i 01 BiFN
12
^ "9
W W
Fu-
SSY13 UO CU ssVID roc -e „9► mm
8
0. M•,�
Zp
•r
�
�O
�•
3
r
< <7
cd
$
�r
a
<<e scxe
sc rcxe
so -z ,oa•st ,tie te-m sz•cc os'r
�
r
sy��ga
�e8�8�
H �n
c p 8
oi
r}im'M
go S
zwIt
z
Z.
O
O
Ntn
gg �gz
a r3
11:1 11 li III
SSY13 1 (.L 1) Cq ssro
gig
y�
NoW
WW
a
g��c1
za�j
t5 d'
a
gig
�
WW
i9 7
E 31942.30
"��
r�
�
J
•rr•
"
0+47.59
�e�� �,�
•$.
r � �
IES 31142.542.5 0
Ile
•G�� �,
0+59.79
O` t• �.
y5.
° "" 0.
,
yr y��
b
+m' �y
"p;� 1 1
4
A
'lrybyp'ry
xry
20 °r�
La Fm
�3ZH
� A�
G
o
O
w
6
pi�K
FF
RS
�'p
aaO
WF
6
Q
cni nr(
G�
V
Y 4Y aE
r'
��m
►
� � IAV
xR
LL
��
}(�f y`y
�•N�
Z
�vl
yJ dG
VI�
YH
V ��
Jr� pZ 4y LL
"FNNN
V(t(
1os�
"�N
,L T
`�
p
%i3J
r�;
T,N,N p
3s31
ii33
5i 3 3
9�3
i{3J
iia
p
R3J
�S33'A
lug
LO��
7{33
tll
:1i33
r
w
w
w
w
N
w
w
w
..
'•
N
t.��
�
ss+no
(,01) cu ssvio coc—S „9c
J
.09T
4 Z H
6 Tj
=u !
+�
Lir
0+05.00
N 7259044.66
E 963010.12
r
1
NT. 90.00' LT
IE- 3143.008
1A
Y O 1Z.
XG
m
Ilydr�„JJIE
0+16.59
982946.53
VT- 15.00' DN
0+09.50 w
E 982996.62
<
IE- 3145.00
1�
VT. 15.00' ON
JE- 3145.00
7n
d
0+25.92
E 962989.20
N
0+18.63 <
E 952987.29
c VT- 15.00' UP
IE- 3142.50
Vi 15.00' UP d
IE_ 3142.50
<
N
io
F a
0+47.59
E 98296742.53
IES 31,50
0+36.73 !
E 962969.37 ^ M"`
�� 3142.50 q ni
r
Le
Zf a
`
p
77
k
2
E)§�
§.
§
■
7..j6
w7k
«
%§
%/K
e
/(
in
%
&
■
&
���
)
�
�
�\
■
io
§
Ln
§
§
°
�§
(L
---
/
}LU
�\
]
§13
§
�bj
§ CL
2\
2
f
/ai0
2\
§
o
%K
�G
¥
2�
e
■
§°
§
K2
|Ek
�!
)
ad d
2
e
\8
&
\
$
\
---
.
�
&.
-
\
�
q
-
@
e
§
®
�k
k
§
2
e
k
§
§/
e\.
a)
�`
§
/
k/
®�
I
§ &
4
■s�
`LIM
2A
S
■
e
I]
]
k
'
\
�
,
_
�
@
m
a
LU
. §
Iq`
$
u
,
/
§
q
n�
§
�»
°in w
/
\\
22
�
Ph
k
}|
$�
§
)
�k
§ ■K
a @
!
�
e
`E�§a■.=<
■
�
� §
�
q 8
)
k
7
.kms. . . . .. .
} /
b
\
co
!�k
|
�
2§%
� ■
mak■
kȤ
2$ �
S
■
��
�2
)|
2§
.a
e
�
§
�§
lk
§
®
!
5-}\v\
alm,;_
°$
\
}�
�
�
.-
-
B2
�� •
.. . .... .
to
to
!
� �
----fm
m
&
/
7
..
t)./Zf•f3)§
-
®
�)
SEE ;
2 — REQT
PC, NO. 8235 t 8238 ID- 38'
lEG1 --
LL- 0.66'
X- 1.53'
BEVEL.
JOINT TYPE: SR 8-303 SPIGOT
LENGTH- 5 1/2'
BACKUP RING:
RING ID -
RING CO -
CHECK LENGTH. 12 3/16'
SEE SHEET 38.
OD CYL= 37 71W
i=
LL- 1.00'
Y- 2.2r
BEVEL -
JOINT TYPE: HARN. B-303 BELL
LENGTH- 4 1/2'
BACKUP RING:
RING ID -
RING OD -
CHECK LENGTH- 11 15/16'
MARK IN WATERPROOF PAINT ON EACH PIPE
OR FITTING:
a. PIPE CLASS
A. DATE OF MANUFACTURE
c. TRADEMARK
d. ON BENDS. THE ANGLE TURNED AND
THE LONG AND SHORT SIDES.
EACH END OF ALL SPECIALS AND FITTINGS
Stall BE MARKED ALONG T.O.P. CENTERLINE
WITH A STRIPE OF WATERPROOF PAINT
APPROXWfATELY 1 1/2' WIDE AND 2' LONG.
ANGLE. 15.00' FULL CUTS- 1
CUT ANGLE- 7.500' OVERALL CAN LENGTH- 14
DISTANCE
DISTANCE FROM END TO EA. CUT
AROUND CIR.
CUTI
1) 0'
9 3/16'
2) 14 7/8'
8 1/2'
3) 29 3/4'
5 11/16'
4) 44 5/8'
4 15/16'
5) 59 1/2'
4 3/16'
FlTfINGS
3OCK. TEXAS
RELEASE COPY
AUG 2 7 2008
Is=FWINMATM
TYPE 3
. « _—%
§
■
k2
k�
�§
�
f■
!
k
�
§�
§■K�
§\
k�
7
/
§
kk
u
«
§
2
b
§/3
. ±
�
2
\|k
k
k
�
7
/...,.x
\
}f]
■
�
.|
.
a
9
§
�ww�k�wwk
2_�2..§§,E
E
3«3333333
K
2A
.�«. «
«
|
a§
aKa■gz&
■
�■
. « _—%
\
■
�
r
§�
§■K�
A
7
/
§
§
�
§
§/3
§2
2
�
k
k
7
/...,.x
\
}f]
■
�
.
a
9
§
�ww�k�wwk
. « _—%
■$22§■m�2
r
A
7
/
§
§/3
§2
2
�
k
k
7
/...,.x
\
■
�
.
9
§
�ww�k�wwk
2_�2..§§,E
E
3«3333333
K
2A
awaa.�_
Is -
. « _—%
r
7
/
§
§2
2
�
k
k
-
���■2
\
��/�
.
��■m§.aa2
2_�2..§§,E
K
2A
awaa.�_
Is -
a§
aKa■gz&
07, U,
_
�,k)
]�
q
®-
�
2
333
3
a
REQUEST FOR INFORMATION
PROJECT: SOUTHEAST WATER RECLAMATION PLANT IMPROVEMENTS PROJECT NUMBER:
OWNER: THE CITY OF LUBBOCK. TEXAS 92126
CONTRACTOR: EAGLE CONTRACTING, LP 171
ENGINEER: BLACK & V_EATCH CORPORATION
REFERENCE DATA:
Contractor RFI No. 037 Spec Section 01015 Page No. 8 Para. 10.02.08-8a
Drawing No. CY3 and Black and Veatch Sketch
CONTRACTOR REQUESTS: ® Information ❑ Interpretation ❑ Clarification
Per the request of Rich Houghton, Eagle is submitting this RFI as follows.
We have routed the 16"RAS Temporary to the Existing Aeration Distribution Structure and were planning
to 90 down into this structure to discharge this RAS. The Flow could be split to either BNR#1 or BNR#2
by means of the Slide Gate that splits flow to either basin. Yesterday Laura Straton and Rich Houghton
requested a different means of discharging the RAS into the Aeration Distribution Structure (see the
attached sketch that shows what Black & Veatch wants).
Eagle will request extra money to cover the costs of this extra work.
CONTRACTOR'S PROPOSED SOLUTION:
REQUESTED BY: DATE: 08/07/08
ENGINEER'S RESPONSE: ❑ Information ❑ Interpretation 91 Clarification
For the items described above or in the attached material referenced:
See attached for response.
RESPONSE BY: Laura Stratton DATE: 08/08/2008
SASandMagle Conftdin® FtleaUob Fllea1171- Lubbock W WfP1 RARFi-037 -16 Temp.RAS to Aer.Dist.SWcture.doe
RFI -037 Response
08/08/2008
An equal hydraulic split cannot occur by adding RAS to one
side of the Aeration Distribution Structure and opening gate
SG -403. As detailed on Sheet 12, RAS would mix with the
effluent from Primary Clarifier No. 2. With SG -403 open,
there will be some mixing between the sides of the box, but
an equal split of the RAS will not occur. An equal RAS
split to Basins 1 and 2 is important to the biological
process.
Upon review of the contract documents, it appears that not
enough detail was provided for the bypass line. Per Sheet
12, the RAS line was to be fed to the west side of the
Aeration Distribution Structure only. A second feed point
into the east side of the structure was not indicated but is
required. The attached detail indicates the changes to this
line to accommodate a hydraulic flow split between the two
basins.
Based on the contract documents and the required changes, it
appears that Eagle may ask for additional compensation to
purchase a 16"x10" Tee. Per Sheet 12, 1611 pipe was to be
installed over the structure. A 16"x10" Tee is now
required.
In order to protect the grating, it should be removed from
the structure and replaced with plywood cut to accommodate
the ductile piping.
A revised sketch of the piping arrangement is attached to
this response.
S
..,C;. WWI.
Jill,
lu
I
..,C;. WWI.
lu
I
a3
pYgglio
a3
08/07/2008 13:08 9724752301
EAGLE CONTRACTING
Fj
PAGE 01/01
os�vo, a�«e
��nnaw«n
4
«
i
w
T
y
I
August 22, 2008
Black & Veatch Corp.
9441 LBJ Freeway —Suite 114
Dallas, Texas 75243
Attn: Ms. Laura Stratton
RE: Southeast Water Reclamation Plant Improvements
Contract ITB # 07 -730 -BM — Project # 92126
The City of Lubbock, Texas
Black & Veatch Corporation
Subj.: Contractors Modification Request (CMR -06) per RFI -37 (Additions to 16" Temp.
Pipe at the Aeration Distribution Structure)
Dear Laura,
Eagle Contracting, L.P. proposes to add the necessary piping at the Aeration
Distribution Structure per RFI -037 for the total lump sum amount of Three Thousand
One Hundred Forty Three Dollars and Seventy Cents ($3,143.70).
With Kindest Regards,
j
Glenn Grant
Project Manager
cc: File (Proposals) & Field
P.O. Box 1600 a Keller, Texas 76244 Metro (817) 379-1897 Metro (817) 379-0610 Fax
Eagle Contracting, L.P.
SEWRP - Lubbock Date: August 22, 2008
Job No. 171 Proposal: CMR -06
Work Description: Add 2nd drop of 16"RAS Temp. into Aeration Distribution Structure
Ref. RFI -037
.... T[ • . • -
16" X 10" MJ Tee
labor to install tee
16" Megalugs
labor to install megalugs
10" Megalug
labor to install megalug
Freight to job for pipe
Cut 16" Pipe for Tee
Remove pipe listed above
Remove & Replace Grating
Temporary Plywood in place of grates
Install /Remove plywood
Rubber Tired Loader/Backhoe-Eagle
Fuel, Oil, Gas & Maintenance -30% rent
Small Tools 5% of Labor
TOTALLABOR
TOTAL LABOR W/0 BURDEN
LABOR BURDENBNFTS - 52%
Below is Eagle's Breakdown of Costs:
FICA - 7.65%
SUTA - 3%
FUTA - 0.8%
Workers Compensation -12.8%
Overtime - 5%
Vacation - 3%
Health Insurance - 7%
401 K - 3.75%
Housing, Furniture, Utilities, Meals & Ga:
-9%
4ote: the only two items above that are
fixed are FICA and FUTA, all other
tems are variable, subject to change,
averages and considered estimates.
TOTAL LABOR
TOTAL MATERIALS
IOTAL SUBCONTRACTS
��sL'- I[a]cl I
1
7.01
2
7.07
1
2.21
1
1
8.14
UNITS
ea
mh
ea
mh
ea
mh
Is
mh
mh
6 mh
150 sf
9 mh
0.05
1
mo
Is
Is
SEWRP - Lubbock
MATERIAL TOTAL LABOR TOTAL
UNIT PRICE MATERIAL UNIT PRICE LABOR
524.00
273.00
56.00
315.00
0.80
1,000.00
15.00
33.15
524.00
0.00
546.00
0.00
56.00
0.00
315.00
0.00
0.00
0.00
0.00
0.00
120.00
0.00
0.00
50.00
15.00
33.15
16.40
16.40
16.40
16.40
16.40
16.40
16.40
0.00
114.96
0.00
115.95
0.00
36.24
0.00
0.00
16.40
133.50
0.00
98.40
0.00
147.60
0.00
0.00
0.00
0.00
0.00
663.05
344.79
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1,659.15
0.00
0.00
INSURANCE @ 2-1/2%
SUBTOTAL
OH&P@15%
SUBTOTAL
SEWRP - Lubbock
66.67
Aug 13 2cce 3;DBPM LDNESTRR PLeh t-MbK14Rt }utl yr .
LONESTARPIPE PABIUCA-Rolo , IN(;.
211 Sansom Bawd,
saginaw. Tx 76179
819 To
EAGIX 60NTRACr1NCi
607 S. PF499ON
&EL,LEk TX 76249
Ship To
SAME CONTRALTWO
3603 CTUAVJS AVE
LUSSOCK 79404
A'I T1: RON SkAY
Involcl
involm #
811; JM008 940
P.O. No, Timms Ship bets Ship Via
171-29032 Nnt30 8J121„048
POB
LoneStar Job #
44V Unit
FFA
73$
' DaSCliptlpn
1
ZACK 16" X 10" DI MJ TtE
Tag 0
Rate
Amount
2 EAC'I 16 SEIMS 3000 p S-rAR GEIP W/ AC
524.00
S24.00
1 EACH 10SOMS 3000 P STARGRIP WJ AC
2n•00
546.00
1 BACK FREIGHT
56.00
36.00
/10
31s.00
315.00
l
M9 nnt
Cu -r 9' F1
re17'n
r
Mance:
Loncstw pipe pobrja4#ozL I=
P.O. BOX 79230
Saginaw, TX 76179
Ph: 817-439-5575
Fax: 517-439-3738
Total
$1,441.00
10/10 3SVd ONI OVNIN00 TIM3 IOEZ9LVZL6 BT:St Booz/EI/Bo
REQUEST FOR INFORMATION
PRO. CT: "S(ii fiHEAST WATER RECLAMATION PLANT IMPROVEMENTS PROJECT NUMBER:
ow(Jgj� _ THE• CITY OF LUBBOCK TEXAS 92128
CONTRACTOR: —EAGLE CONTRACTING, LP 171
ENGINEER: BLACK'& VEATCH CORPORATION
REFERENCE DATA:
Contractor RFI NO' .'037 Spec Section 01016 Page No. 8 Para. 10.0208 — 8a
Drawing No. CYS and Black and Veatch Sketch
CONTRACTOR REQUESTS: ® Information 0 Interpretation 0 Clarification
Perthe request df*Rlch Houghton, Eagle is Submitting this RFI as follows.
We- have routed the 16"RAS Temporary..to the Existing Aeration Distribution Structure and were planning
to 90 down Into this structure to discharge this RAS. The Flow could be split to either BNR#1 or BNR#2
by means of the Slide Gate that splits flow to either basin. Yesterday Laura Stratton and Rich Houghton
requested a different means of discharging the RAS into the Aeration Distribution Structure (see the
attached sketch that shows what Black & Veatch wants).
eagle- will-requestrextrwrnoneyto-cover the -costs -of this extra -work.
CONTRACTOR'S PROPOSED SOLUTION:
REQUESTED BY: �.�`.''`a�. DATE: 08/07/08
ENGINEER'S RESPONSE: 0 Information ❑ Interpretation M Clarification
For the items described above or In the attached material referenced:
See attached for response.
RESPONSE BY: Laura Stratton DATE: 08/08/2008
WSandAftle Contracting FgeeWob 1`11ea1171 • Lubbock W W'iP%RF1's1RF1-087 AS Temp.RAS to Aer.D19LSWctwe doc
RFt' 037 'Response•.
08/0'8%2008
An equal hydraulic split- cannot' occur by adding RAS to one
side of they Aeration Distribution. Structure, -and- opening gate
SG 403 As detailed on Sheet I2: RAS would mix with the'
effluent, froirt" rimarp .Clarifler No: 2': With 8G-403 open.,
there.:,will 'be's'ome mixing between.. the sides' of, the: box, but
an equal split of the RAS. will; not occur::..An, equal RAS
split: to.. Basins 1 and -2 is' important to' the .biological
process.: -
Upon.review of the contract documents, it appears that not
enough detail was -provided for the bypass line. Per Sheet
12, the RAS line` was 'to be fed to the west side of the
Aeration Distribution Structure only.... A second feed point
into the.east,•side of. the structure was not. indicated but is
required, The attached'detail. indicates the changes 'to this
line to accommodate a hydraulic flow split. between the two
... -bas=ins.,---_._....._-..- _-.-,_._T...,�__._.�.�. _......._._... ,.,..�....__,� .• .._. _.._._..�.._.. .._....,_ .
Based on the contract documents and the required changes, it
appears that Eagle may ask for additional compensation to
purchase a 16"x1011 Tee. Per Sheet 12, 16" pipe was to be
installed over the structure. A 16"x10" Tee is now
required.
In order to protect the grating, it should be removed from
the structure and replaced with plywood cut to accommodate
the ductile piping.
A revised sketch of the piping arrangement is attached to
this response.
' �,S�• �v - t G ,. L Vin, � . �- ��; y�-,��„� r�u. + t s, --} �i ��, � t,
'�'++}td3' i` • `e'r ..s st,( -,t ,e ', ii r r 1 i +-! y, ij {, r i- v F s• 'e'r.� r
i
-.r.ir;c;•"r�'si bbt',i1�•r}` i i ,��"• .,+ trss°'S- i !i*�,T+ 1 r �'i`�-'r c j �''.
o.
3?�•Ys i n irzN-i�rjF 4 f .i';L.,r3.1 r.i "f C� '� -Ls.. 3 Ire 1 L
�� rr t{7 r ri rr t . to Ft
fa
.T!'7�
�'
t �� {; L .• it� � •-- r.: T7 Tr. i'-¢ 34 L" r 4 4 -} .�r 7'.
�1 G t.�J 1}. 1 y rtr 7 '1 r 13 •T 7L' Y 3 -fir
za
Vr •vim r.IF
t z ••6,y. ,. ¢q`,'' s t r.l
.,,1 •j+.r # x� x r 2t #' f �` `f -,�„ * h !..�::� � 5- xr ,1 - 3�. �
�'� '` �# x i }•'. .� S. yl'+".�. t ?r y:a. r- 'p(-- #`i{,Cr r }, .'� r _! r; t j- ,
'ttr,"4�' �� 1 r! y y- -�•r S T f ; F! L 7 i[ a. ` [ - jI ti ,� �.
h-�
r�' ?F�- z ` t -� � '� t� "k� �3�'+'.�� �k�, Ssy�•� . _ 1 � c• 1* � rF•° i ' +t.:' I 1 �� , 1� 4; '{ r ,.
4.7, •.� t }{ic � . ix � r.-��-t Li �ti u� 4r-'• r *{s��a«�r
J
i �s. f '.^.`.._^T�" r n••4:m�.��«.� r+^a . r �h it e� rr:- �r, r i!r•la rn��F'� S+ u •r -- -moi -. `..
•..F
_ - T :..� i
i. i t
� r
�v
..... .. ...
err anwr uraraa
L rrwa uranw
li
I—but
I -4 .�
u: 1
a 4-
a``�� Kto.C7•r �
err anwr uraraa
L rrwa uranw
08/07/2008 13:09 9724752301
I
v j+
S
0
Stratton, Laura A.
From: Soo Soon [SSoon @mail. ci. lu bbock. tx. us]
Sent: Thursday, July 24, 2008 9:18 AM
To: Houghton, Richard H.
Cc: Stratton, Laura A.
Subject: Fwd: RE: FW: Lubbock SEWRP
Rich,
Please request a change order from Eagle contracting as soon as possible.
Soo Koon Soon
>>> Steven O'Neal 7/24/2008 8:56 AM >>>
Soon,
I spoke with Chad (one of my plumbing inspectors), and he does not recall the conversation or having seen the
drawing before. He does concur that the vent is needed and is OK as proposed. He did add that a cleanout fitting
needs to be added at the upstream end of the 4" horizontal drain line, however. Replacement of the last 45 degree
sweep with a wye fitting and adding of a 90 degree sweep, riser and floor clean-out plug will do it.
Thanks,
Steve
>>> Soo Soon 7/23/2008.2:30 PM >>>
Steve,
Any idea what this is about?
Soo Koon Soon
>>> "Houghton, Richard H." <HoughtonRH@bv.com> 7/23/2008 2:14 PM >>>
Ron meet with someone named Chad at the plumbing department and he said they want a second vent added in
that same area, at the other end of the floor drains. I need to go over routing with PSC and then get a cost proposal
from Eagle, it could take a week or 2. - -
From: Soo Soon fmailtoSSoon@meil.ciaubbockax,usj
Sent: Wednesday, July 23, 2008 1:58 PM
To: Houghton, Richard H.
Cc: Stratton, Laura A.; Steven O'Neal
Subject: Re: FW: Lubbock SEWRP
Rich,
The City building official will accept the proposed of the 2 inch air ventilation pipe. Please process the change order
asap.
Soo Koon Soon
>>> "Houghton, Richard H." <HoughtonRH@bv.com> 7/15/2008 4:41 PM >>>
Soon, here is a small issue that might cost a few bucks. We have to add
a stink vent for plumbing code up to the roof. See plan sheet P5.
9/9/2008
-----Original Message -----
From: Roland Holder [mailto:RHolder@team-DSC.coml
Sent: Monday, July 14, 2008 3:31 PM
To: Houghton, Richard H.; Stratton, Laura A.
Subject: Lubbock SEWRP
Keven Willis's response to the plumbing issue.
Roland
RH
-----Original Message -----
From: Arch_xerox@corp.team-psc.com[mailto:Arch_xerox@corp.team-psc.com]
Sent: Monday, July 14, 2008 2:47 PM
To: Roland Holder
Subject: Scan from a Xerox WorkCentre Pro
Please open the attached document. It was scanned and sent to you using
a Xerox WorkCentre Pro.
Sent by: Guest [Arch_xerox@corp.team-psc.com] Number of Images: 1
Attachment File Type: PDF
WorkCentre Pro Location: Lubbock Architecture Device Name: XRX ARCH
For more information on Xerox products and solutions, please visit
htt�:JLwvwv.xerox.com ( http [/www.xerox.com� }
9/9/2008
-21 Am Ff" YARD
AEFER TO CY SFQWTS
FCR owilmArrav
--__._ -- - -•—ter'.__ � -�� , �_ ";.j .._ " qi
.. . .......... ..... ......
I rill
---- - - ------- -.. ..........
>
t Jw-
L
mmCmW*Ctrot
1 7 FOR OUNooMlr
I T.PPUAR
y
F0.1 CIARIFIER NO, 3
� � i f I i I j I
T t
if
p
e?
TlEgmitiA115
T-1
PRIMARY CLARIFIER NO. 3 PUMP STATION - PLUMING PLM
KEYED NOTES
IMIC.'a oy.. Cr --
I AOM MW PIPIAlf AS WON At MQUY".
PA VIW &ZAV PL4N* RM FUr(W Q*MCVlAV MWAVION
AW?f S, AM crt* to MMEMI PJW STAIM WW.
4 AUMI * AW LlAff SM WAL M W- 1. Air14 •1 AT
so, A. PIP,
August 26, 2008
Black & Veatch Corp.
9441 LBJ Freeway —Suite 114
Dallas, Texas 75243
Attn: Ms. Laura Stratton
RE: Southeast Water Reclamation Plant Improvements
Contract ITB # 07 -730 -BM— Project # 92126
The City of Lubbock, Texas
Black & Veatch Corporation
Subj.: Contractors Modification Request (CMR -07 -Provide Plumbing Clean out and
Vent in the Primary Clarifier Pump Station)
Dear Laura,
Eagle Contracting, L.P. proposes to add the necessary Vent piping and Clean out
at the Primary Clarifier Pump Station for the total lump sum amount of One Thousand
Four Hundred Eighty Six Dollars and Thirty Nine Cents ($1,486.39).
Sincerely,
Dave Mullenix
cc: File (Proposals) & Field
P.O. Box 1600 0 Keller, Texas 76244 0 Metro (817) 379-1897 Metro (817) 379-0610 Fax
Eagle Contracting, L.P.
SEWRP - Lubbock
Job No. 171
Date: August 26, 2008
Proposal: CMR -07
Work Description: Provide additional Cleanout and Vent not detailed for the plumbing in the Primary Clarifier Pump Station
MATERIAL TOTAL LABOR TOTAL
UNIT PRICE MATERIAL UNIT PRICE LABOR
,mTv uuT�+ t. It
Install Vent and Clean Out Piping
for Drains In the Primary Clarifier
Pump Station
Subcontractor time to install material.
9
MH
702.00
0.00
0.00
Journeyman Plumber ($78 per hour)
0.00
0.00
0.00
0.00
4" Cl DBL Wye
1
EA
53.96
53.96
0.00
4"x2" Cl Wye
2
EA
49.10
98.20
0.00
2" Cl 1/8 Bend
2
EA
11.88
23.76
0.00
2" CI 1/4 Bend
5
EA
14.27
71.35
0.00
2" CI Soil Pipe
50
EA
3.68
184.00
0.00
4" Clean Out cover
1
EA
27.72
27.72
0.00
Pipe/Fitting Gaskets
20.00
EA
5.00
100.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
702.00
558.99
TOTAL LABOR
0.00
0.00
TOTAL LABOR W/0 BURDEN
0.00
LABOR BURDEN/BNFTS - 52%
0.00
Below is Eagle's Breakdown of Costs:
0.00
FICA - 7.65% '
0.00
SUTA - 3%
0.00
FUTA - 0.8%
0.00
Workers Compensation - 12.8%
0.00
Overtime - 5%
0.00
Vacation - 3%
0.00
Health Insurance - 7%
0.00
401 K - 3.75%
0.00
Housing, Furniture, Utilities, Meals & Ga
0.00
-9%
0.00
Note: the only two items above that are
0.00
fixed are FICA and FUTA, all other
0.00
items are variable, subject to change,
0.00
averages and considered estimates.
0.00
0.00
TOTAL LABOR
TOTAL MATERIALS
558.99
TOTAL SUBCONTRACTS
702.00
0.00
SUBTOTAL
1,26D.99
INSURANCE @ 2-1/2%
31.52
1,292.51
SUBTOTAL
OH & P @ 15%
193.88
1,486.39
SUBTOTAL
0.00
TOTAL
1,486.39
��SMAI.L.Bt3$ilN
1iOD5TONWW" <rebecca.freathy@ferguson.com>
Frain: "Rebecca Freathy - 11Q7 7
Subject: Email Bid# 6112230
To: d.mullenix@eaglecontracting p.co ...... ...................
Date: 1 Jul 2008 17:26:30 -0400 _ _._-...._._......._........ .._.___
Price Quotation # B112230
Ferguson Waterworks #788
2650 S Pipeline Road
Euless, TX 76040
Phone: 817-267-3900
Fax: 817-267-3912
Bid No.......: B112230
Bid Date...: 06127/08
Quoted By: RLF
Customer.: LUBBOCK SEGLE R\NTR RECLAMATION
PO BOX 1600
KELLER, TX 76244
Cust PO#..: CHANGE ORDER
item Description
Print - Close Window
Cust Phone: 817-379-1897
Terms.........: NET 10TH PROX
Ship To.......: NTRACTING
LUBBOCKLE USE WT'R RECLAMATION
PO BOX 1600
KELLER, TX 76244
Job Name.: LUBBOCK SE WTR RECLAMATION
Quaniiiy Net Price UM Tatal
1399... 7/1/2008
i httpJ/b8.maii.yahoo
� vORKS DWG Pi
4
109.000 EA
436.00
*0505 3 NH ROOF DRN W/Dohe
7 543 EA
75.43
W3003NH
10
NH9M
3 NH 114 BEND.
4
7.543 EA
30.17
NH4M
3 NH 1/8 BBN)
130
468.338 C
608.84
NHPM10
3X10 NH SOIL PIPE
25
9.714 EA
242.85
NHWBCM
3 HUSKY HD 2000 NH COUP
2
142.285 EA
284.57
W3943NH
3 NH NB DSPT NOZ
2
7.055 EA
14.11
*0704 3 NH END CAP
ZP886E3
PLANT FOUR PRIMARY
CLARIFIER SLUDGE PS
DWG PS
4
77.715 EA
310.86
W 1104STD6
4 C1 FLR DRN W/ ADJ STRN
4
58.958 EA
235.83
SVDSPTP
4 SV DP SEAL P TRAP
7
71371 EA
121.60
SV4P
4 SV 1/8 BEND
3
53.95
161.87
SVDYP
4 SV DBL WYE
80
771.250 C
617.00
SV SHPP 10
4X 10 SV SH SOIL PIPE
275.000
EA
135.00
4 SV TYSEAL GSKT
SVTGP
1399... 7/1/2008
i httpJ/b8.maii.yahoo
� Ol JOB NVUCE
611 1 Li `}
M-37270,
J �
TERMS:
PHONE
DATE OF ORDER
ORDER TAKEN BY
CUSTOMER ORDER NUMBER
DAY WORK 0 CONTRACT Q EXTRA
JOB NAME NUMBER
JO N` fie
JO
STARTING DATE
rb:Y.SF ,�y.�k3 V4
yp� :ti
4
t a ..y
i •
rjF, i •'r:' wPi`v
� -�
to 6F
�.
%rid r n i y T Pa
G
� � I
manR 3
A
TOTAL OTHER
I qS 13
1 p
I
t
TOTAL LABOR
DATE COMPLETED
TOTALMATERIALSL
�t
; ;
TOTAL MATERIALS Z q
r..S.B.P.E P.O. Box4200 Ausdn, 7 785 12) 488-2145
TOTAL OTHER
Work ordered by
y
TAX
Signature
I hereby acknowledge the satisfactory completion of the above described work.
TOTAL 2 �'1
t4
September 9, 2008
Black & Veatch Corp.
9441 LBJ Freeway —Suite 114
Dallas, Texas 75243
Attn: Ms. Laura Stratton
RE: Southeast Water Reclamation Plant Improvements
Contract ITB # 07 -730 -BM — Project # 92126
The City of Lubbock, Texas
Black & Veatch Corporation
Subj.: Contractors Modification Request (CMR -08 - Addition of Pump Linings for the
TWAS Pumps and Cabinets and Controls for the Free Standing RFD's for five
Pumps)
Dear Laura,
Eagle Contracting, L.P. proposes to add Pump Linings to the two TWAS Pumps
and add Cabinets and Controls for all five of the Double Disc Pumps AFD's for the total
lump sum amount of Thirty Three Thousand Seven Hundred and Thirty Nine Dollars
($33,739.00).
With Kindest Regards,
Glenn Grant
Project Manager
cc: File (Proposals) & Field
P.O. Box 1600 Keller, Texas 76244
0 Metro (817) 379-1897 a Metro (817) 379-0610 Fax
Eagle Contracting, L.P.
SEWRP - Lubbock
Job No. 171
Date: September 9, 2008
Proposal: CMR -08
Work Description: Provide cabinets & controls for the Double Disk Pumps and also a tungsten carbide lining
MATERIAL TOTAL LABOR TOTAL
UNIT PRICE MATERIAL UNIT PRICE LABOR
ACTIVITY QUANTITY UNITS SUBCONTRACT S $
Provide AFD Cabinets & Controls
for the Double Disc Pumps
Purchase Cabinets & Controls
5
ea
5,669.80
28,349.00
0.00
0.00
0.00
Provide Tungsen Carbide Lining
0.00
0.00
for Double Disc Pumps
0.00
0.00
0.00
0.00
Purchase Linings for TWAS Pumps
2
ea
1,500.00
3,000.00
0.00
0.00
0.00
0.00
31, 349.00
TOTAL LABOR
i
0.00
TOTAL MATERIALS
31,349.00
TOTAL SUBCONTRACTS
0.00
0.00
SUBTOTAL
31, 349.00
INSURANCE @ 2-1/2%
783.73
SUBTOTAL
32,132.73
OH & P @ 5%
I
I
1,606.28
SUBTOTAL
33,739.00
i
i
0.00
TOTAL
33,739.00
1
Resolution No. 2008—RO394
South Western Environmental Equipment Technicians
7904 La Cosa Drive
Dallas, TX 75248
(972) 233-1602 a Fax (972) 866-6852
Email: ejeortez@sbcglobal.net
QUOTATION # 967TX6-Revision # 1
To: Eagle Contracting L.P. Date: September 8, 2008
PO Box 1600 Terms: Per Contract
Keller, TX 76244 Submittals: 2-3 weeks from Change Order
Attn: Glenn Grant Delivery: See below
Phone: 817-379-1897
Email: a.grant0eaglecontracting1p.com
TY Description
Price
Amount
Changes to Contract and Pre -Negotiated Double Disc Pumps for
the Lubbock SE WRP Improvements Contract 6
Purchase Order # 171-1103
2 -lot Adder for Tungsten Carbide Coating on Housings for each Double
1,500.00
$3,000.00
Disc Pump Furnished
5 -lot Adder to Furnish Complete Enclosures and Controls for AFD Units
$6,000.00
$30,000.00
already being supplied, per Specification Section 16150P2 and all
related Drawings.
Unit Designations:
SCSC-P-4601, WAS -P-4602, WAS -P-4603, TWAS-P-2501 and
TWAS-P-2502
Exceptions:
Section 16150P2 1-4t Harmonic Testing Plan is not included.
Section 16150P2 1-6 Spare Drive will be provided in lieu of Spare
Parts Listed
Section 16150P2 3-5.02 Harmonic Testing is not included.
Note: Exceptions listed above are the same as approved on SWEET
Proposal # 106-A, dated 11/2/08
Less 5% Discount for Pre -Negotiated Package
($1,651.00)
Total Adder Price
$31,349.00
Revised Contract Price
$220,665.00
Note: Once approved and change order is issued. SWEET will
provide a new submittal to incorporate all the changes.
Delivery: Pumps -6 weeks from Approval
AFD Control Panels -8-10 weeks from Approval
Quotation By Christo=hex J Cartez