directed to execute for and on behalf of the City of Lubbock, an agreement entitled
"Amendment for Authorization of Professional Services Associated with Phase C-1
Design Development Package Lubbock International Airport Corridor Improvements",
between the City of Lubbock and Wallace Roberts & Todd, LLC. Said agreement is
attached hereto and incorporated in this Resolution as if fully set forth herein and shall
be included in the minutes of the Council.
Passed by the City Council this 13th day of September , 2001.
WINDY TON, MAYOR
ATTEST:
Rebecca Garza, City Secretary
AP ROcVED TO CONTENT:
David Jones
LIA Deputy Director -Planning & Development
APPROVED AS TO FORM:
Linda L. Chamales, Supervising Attorney
gs/ccdocs/Amendment-LIA Corridor Improvements. res
September 4, 2001
Resolution No. 2001-RO348
September 13, 2001
Item No. 45
AMENDMENTFOR
AUTHORIZATION OF PROFESSIONAL SERVICES
ASSOCIATED WITH
PHASE C — CONSTRUCTION DOCUMENTS
C-1 DESIGN DEVELOPMENT PACKAGE
LUBBOCK INTERNATIONAL AIRPORT CORRIDOR IMPROVEMENTS
Lubbock, Texas
August 27, 2001
A. PROJECT UNDERSTANDING
Wallace Roberts & Todd, LLC. ("WRT") will perform Professional Landscape
Architectural, Engineering, Surveying and Irrigation services for the City of
Lubbock, Texas International Airport ("City") for Construction Documents for
Phase One improvements. These improvements will be based on the approved
Corridor Landscape Improvement Master Plan for East Regis Street between I-
27 Highway and Martin Luther King Boulevard (MLK) and for Martin Luther King
Boulevard between East Regis Street and the Airport Terminal (see attachment
"A"). WRT will retain the professional services of Parkhill, Smith & Cooper, Inc,
for the civil and electrical engineering, Smith Surveying for the topographic
survey, and Water Smart Irrigation for the irrigation services.
This scope of work includes professional services as described above for the
preparation of Construction Documents for Airport Corridor Landscape
Improvements associated with East Regis Street and MLK corridor in Lubbock,
Texas. The program and approved priorities according to an estimated
construction budget of $2 million, as shown in the approved master plan, include
the following items: establish grade elevations for the curb and gutter, grading
and drainage for the transition slopes, electrical, landscape planting, and
irrigation. The following scope of work and fee schedule is based upon these
items as identified in discussions with the City Staff to date.
WRT further understands that the above improvements will be based upon the
existing pavement cross-section and new curb and gutter for East Regis Street.
WRT understands that the City will be responsible for construction of the airport
corridor improvements and WRT has developed the following scope of services
based on the requests and direction of the client.
We propose the that the approach to this project be completed in the following
phases:
Phase 1 — Topographic Survey & Base Map Preparation
Phase 2 — Design Development
Phase 3 — Construction Documents
B. SCOPE OF SERVICES
Phase 1 — Topographic Survey & Base Map Preparation
01.6064.P06.doc
Task 1.0 The WRT team will perform a project survey of the overall
street corridor and existing elements within the corridor.
The project survey mapping will be prepared in a digital
format. The project survey will include topography,
overhead and underground utilities, R.O.W., property
lines, easements, edge of pavement, existing vegetation,
and horizontal control data.
Task 1.1 Based on the project survey information, WRT will prepare
a base drawing for use in the Phase One construction
documents.
Task 1.2 The City will be responsible for coordinating and obtaining
any additional information that is necessary to establish
the new curb and gutter for completion of the proposed
Regis Street.
Phase 2 — DESIGN DEVELOPMENT
Task 2.0 Utilizing, the base drawings prepared from the project
survey and TxDoT information, WRT will prepare design
development drawings for the proposed airport corridor
improvements. The design development drawings will be
prepared electronically in Autocad format and submitted in
hardcopy to the City for review, input and approval at an
approximate 50% level of completion.
Task 2.1 Design development drawings will include demolition
plans, layout plans, grading plans, landscape planting,
irrigation, and lighting/electrical plans.
Task 2.2 WRT will submit three (3) sets of 24"x36" Phase One
Design Development drawings to the City for review.
Task 2.3 The City will forward, in writing, to WRT all review
comments for the design development submittal. WRT will
incorporate these comments into the design development
drawings. WRT will require written approval from the City
prior to proceeding into the final construction documents.
Phase 3 - CONSTRUCTION DOCUMENTS
Task 3.0 Based upon the approved design development drawings,
WRT will prepare final construction documents for the
airport corridor improvements. The construction
documents will contain required information for the
implementation of the Phase One program of
improvements.
Task 3.1 WRT will submit three (3) sets of 24" x 36" Phase One
construction documents for final review and approval by
the City. WRT will incorporate the final written comments
01.6064.P06.doc
into the Phase One construction documents for the City to
utilize in implementing the project.
Task 3.3 The City will be responsible for submitting the final
construction documents, including review and inspection,
to the Texas Department of Licensing and Regulation or
independent contract provider for review. Revisions to the
drawings by WRT, as necessary to obtain the appropriate
approvals will be considered an additional service. Fees,
permits, and costs associated with the project review will
be the responsibility of the City.
Task 3.4 WRT will provide one set of 24"x36" reproducible drawings
to the City for their use. All costs associated with the
printing and duplication of the drawings will be the
responsibility of the City.
Phase 4 - BIDDING PHASE
Task 4.0 Bidding services as required for publicly bidding the project
is not included in the Scope of Services contained herein.
Phase 5 - CONSTRUCTION PHASE
Task 5.0 Construction observation and administration services as
required for implementation of the project are not included
in the Scope of Services contained herein.
C. COMPENSATION
The Professional fees noted below are based upon the Scope of Services
described herein.
Should the scope of services be modified or additional services be required or
requested by the City, WRT and the City will re-evaluate the scope of work and
determine the basis of compensation in accordance with revisions to the scope.
WRT guarantees the fee for this proposal for ninety days from the date of this
proposal. If after ninety days a contract has not been entered into then WRT
reserves the right to renegotiate fees for the scope of services contained herein.
Compensation for the work will be a lump sum fee, and includes reimbursable
expenses.
Phase 1 — Base Map Preparation $ 1,680.00
Phase 2 — Design Development $ 54,525.00
Phase 3 — Construction Documents $ 54,525.00
Topographic Survey $ 16,800.00
Reimbursable Actual Expenses Not to Exceed $ 5,000.00
TOTAL CONSTRUCTION DOCUMENT SERVICES $132,530.00
01.6064.P06.doc
D. REIMBURSABLES
Reimbursable expenses include but are not limited to: mileage, meals,
reproduction, printing, courier/delivery, photography, aerial photography, film,
film processing, mounting, framing, matting, postage & shipping, long distance
telephone calls or faxes, and any other additional items not included in the above
stated services. Reimbursable expenses will be paid for by the City at cost and
are not included in the Total Basic Services amount.
E. ASSUMPTIONS
1. The City will provide as expeditiously as possible any additional base
information that it can gather and as necessary to complete the scope of
services described herein. All information provided by the City is
assumed accurate and complete, unless indicated otherwise by the City.
2. All printing and reproduction costs for master plan documents, review
sets, final construction drawings, specifications, and artwork will be the
responsibility of the City.
3. Additional meetings and/or presentations beyond what is indicated in this
scope of services will be additional services.
4. Any opinions of probable construction costs provided by WRT will be on a
basis of experience and judgment. WRT has no control over market
conditions or bidding procedures and cannot warrant that bids or ultimate
construction costs will not vary from these opinions of probable
construction costs.
5. The City will be responsible for coordination of all public meetings and all
administration of the construction contract and coordination with the
contractor.
6. The City and the contractor during construction will perform location,
verification and coordination of construction work around existing
underground and overhead utilities.
7. The contractor will be responsible for all "as -built" drawings at the
completion of the project. This scope of work does not include any "as -
built" drawings by WRT.
8. A Storm Water Pollution Prevention Plan (SWPPP) is not included in this
scope of services. Any services for environmental engineering such as
an Environmental Assessment (E.A.) or Environmental Impact Statement
(E.I.S.) would be considered additional services
9. It is anticipated that Phase One airport corridor improvements will be
prepared as one bid package. Additional bid packages as required by
the City for phasing breakouts, will be considered additional services.
01.6064.P06.doc
WRT will negotiate with the City the scope of services to address
additional fees not covered in this scope of work.
10. All front-end documents, contracts, insurance requirements, general
conditions, etc. used in preparing the contract documents are not
included within this scope and will be provided by the City.
11. If the City determines it necessary to submit the construction documents
for review by TxDoT, any necessary revisions to the documents, as a
result of that review, will be considered additional services.
IN WITNESS WHEREOF, THE CITY OF LUBBOCK has caused this Agreement to be
signed on this day 13th of September , 2001 in its name by its Mayor, and
the consultant of Wallace Roberts & Todd, LLC has caused this Agreement to be signed
in its name by its representative.
SEAL:
ATTEST:
L
Rebecca Garza
City Secretary
APPROVED AS TO CONTENT:
Mark i &le, Director
CITY OF LUBBOCK, TEXAS
BY: v 4*�_
NAME: Windy Sitton
TITLE: Mayor
DATE: September 13, 2001
WALLACE ROBERTS &,TODD, LLC
BY:
NAME: 1 KennetljR. Howell, Jr., ASLA
APPROVED AS TO FORM: TITLE: Director, Dallas Office
DATE:
William deHaas
Competition & Contracts Attorney
01.6064.P06.doc
August 27, 2001
Resolution No. 2001