HomeMy WebLinkAboutResolution - 2020-R0049 - Change Order 1 With Utility Contractors Of America, Inc. - 02/11/2020 Resolution No. 2020-R0049
Item No. 7.5
February 11, 2020
RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of LLibbock is hereby authorized and directed to execute for
and on behalf of the City of Lubbock, Change Order No. 1 to that certain Contract No. 14354 by
and between the City of Lubbock and Utility Contractors of America, Inc., for the Canyon Lakes
sanitary sewer- interceptor rehabilitation – Phase 2, and related documents. Said Change Order
No. 1 is attached hereto and incorporated in this resolution as if fully set forth herein and shall
be included in the minutes of the City Council.
Passed by the City Council on February 11, 2420
DANII:I.. M. POPE, MAYOR
Xrrt3ST:
Reb cca Garza, City Secr tart'
—)
APPROVED AS TO CONTENT:
1e ' a cl achern sistant City Manager
APPROVED AS TO FORM:
-
elli Leisure, Assistant City Attorney
ccdocs/RES.Ch-0rd#I.Contract 14354 UCA
01.16.20
Office of Purchasing and Contract Management
Change Order
Contract No: 14354 Contractor: Utility Contractors ol"America, Inc.
Change Ordcr No: 001 Contract Title: Canyon Lakes Sanitary Sewer Interceptor Rehabilitation
—Phase 2
Bid/RFP No: 19-14354-TF Project No: 92318.9242.30000
"Change Order"means a written order to a Contractor,executed by the Owner, in accordance with the Contract authorizing an addition to,deletion
from,or adjustment or revision of the requirements of the Contract documents,or an adjustment to the compensation payable to the Contactor,or to
the time for performance of the Contract and completion of the project,or a combination thereof,which does not alter the nature of project and is an
integral part of the project objective.Adjustments to"Estimated Quantities'to a line time in a Unit Price Contract do not require a Change Order.All
work that alters the nature of the construction or that is not an integral part of the project objective must be lel out for public bid.
Description of Change(alteration,deviation,addition,or deletion)caused by conditions encountered during construction not covered by the
specifications and drawings of the project attached additional pages is necessary:
The Work of the Project involves the rehabilitation of certain sections of the Canyon Lakes Sanitary Sewer and Downtown Sewer
Interceptors. Change Order#I includes modifications to the original contract documents through Proposed Contract Modifications
(PCMs) for additional work necessary to prevent Sanitary Sewer Overflows(SSOs)and protect the general public in the Park and
add 150 days to the contract. Refer to the attachments.
Where the Change Order is negotiated,the Change Order must be fully documented and itemized as to costs,including material quantities,material
costs,taxes,insurance,employee benefits,other related costs,profit and overhead. Where certain unit prices are contained in the initial Contract,no
deviations are allowed in computing negotiated change order costs.
ITEMIZED COSTS MUST BE FULLY DOCUMENTED AND ATTACHED TO THIS FORM.
ITEM DESCRIPTION AMOUNT
A. ORIGINAL CONTRACTVALUE: $5,825,039.00
B. AMOUNT OF THIS CHANGE ORDER: Note:Council approval required if(•t•/-) $50,000 $ 226,879.90
COST CENTER: ACCOUNT:
C. PERCENT OF CONTRACTVALUE THIS CHANGE ORDER(B/A) +3.89
D. AMOUNT OF PREVIOUS CHANGE ORDERS: $ 0.00
E. TOTAL AMOUNT OF ALL Cl IANGE ORDERS(B+D) $ 226,879.90
F. PERCENT OF CONTRACT OF AL I,CHANGE ORDERS(E/A):(25%maximum) +3.89%
G. NEW CONTRACT AMOUNT(A+E): $6,051,918.90
It is mutually agreed that the above dollar amount and the time extension,as applicable,asset forth in this Change Order constitutes full compensation
to the Contractor for all costs,expenses and damages to the Contractor,whether direct,consequential or otherwise,in anyway incident to,or arising
out Of,or resulting directly or indirectly;from the work performed or modified by the Contractor under this Change Order.
This Chanee Order is not valid without the following signatures(please s&n in order and return 3,2ririrnals with the Contract Cover Sheet to
Purclrasiri=rrnrr ortr ct Mona entent de vartment):
i'
01/07/2020
(1) ontractor 0.1 Date (2)P of << Architect/f nlSeer Date
(3j"Owner's Reprogfulative ate (4)Direc r of Purchasing&Contract Date
Mnnt,
(5) Capital Project Manager Date (6)Vity Attorney Date
Chatwe Orde X over$50 00 .00 e[wire a Co ct Cover Sheet and the ,ollowirn si natures:
nr_ 2/11/2020 2/11/2020
(7) Mayor Date (8) Crty S k±16
Date
Council Date: Febma-1, 1_),2Q2,Q Agenda Item#: 7 5 Resolution#: 2020-1R_0049
PUR45(Rcv 08/2018)
Lan Lockwood,Andrews
&Newnam,Inc.
A IJ r-1 A CIAI.Y COMPANY
PROPOSED CONTRACT MODIFICATION NO.1 DATE: JULY 18, 2019
Project: Canyon Lakes Sanitary Sewer Interceptor Rehabilitation Phase 2 Project No.: RFP 19-14354-TF
Contract For:City of Lubbock Contract Date: March 25,2019(NTP)
Subject of Proposed Contract Modification: Installation of a tapping sleeve and valves on the existing 14-inch recirculation line for
permanent bypass and replacement of existing drop manhole with a new fiberglass drop manhole.
Description:This PCM is to relocate the existing 14-inch recirculation line to an existing drop manhole(NWL-001A), replacement of
manhole 001A and includes standby bypass pumping time charged to UCA by the subcontractor.This will add 14-inch tapping sleeve
and valve and new piping to manhole 001A.The 14-inch line will also be valved and plugged on the northwest side of the installed
manhole over the recirculation line.The flow will be diverted through the new piping into manhole 001A.The manhole 001A will be
replaced with a new fiberglass drop manhole after bypass is complete in this area utilizing the existing concrete bottom due to
excessive corrosion in the riser. PCM 1 includes standby time charged to UCA by the subcontractor for standby bypass pumping due to
the delay in installation of the recirculation isolation valve. UCA had a 5-week pumping delay but was only charged for 4 weeks.
Reference the attached drawings for the proposed revision and invoice for the pumping costs.
All work will be done by Utility Contractors of America.
See proposed cost below:
PAY APPROXIMATE UNIT TOTAL UCA
ITEM QUANTITY UNITS DESCRIPTION OF ITEM PRICE COST
PROPOSAL
Remove existing manhole(all depths)and replace
8A 1 EA with new 60-inch diameter fiberglass manhole(to $16,500.00 $16,500.00
10-feet of depth), including all piping connections to
new and existing sanitary sewer mains.
Furnish and install new 60-inch diameter fiberglass
8C 4 VF manhole at extra depth for new and replacement $450.00 $1,800.00
manholes(beyond 10 vertical feet).
Relocation of 14-inch treated effluent recirculation
35' 1 LS line including:tapping sleeve,valves, piping, plug, $15,011.00 $15,011.00
equipment, labor and appurtenances.
Time charged for the delay of bypass pumping.
1 LS UCA had 5-weeks of standby pumping time but $45,848.90 $45,848.90
was only charged for 4-weeks.
TOTAL PCM 1 $79,159.90
`Indicates new bid item number
Additional cost of$79,159.90 to the contract bid amount and 40 additional calendar days.
Reason for Change:This change will help finalize the tie-in and bypass for the construction of the new 8'diameter manhole.City of
Lubbock operations was not able to stop the flow of the 14-inch recirculation line.This flow was a recirculation line from the WVVTP
effluent back to the WVVTP headworks.The existing downstream drop manhole will be replaced due to extreme corrosion in the riser.
PCM 1 includes all additions and impacts to Section 1.
Recommended Lockwood Andrews& NeWnannInc.
By: Engineer` }�
07/18/2019
Representallve Date
Accepted By: Utility Contractors of America
Contractor
07/19/2019
presentative Date
Approved By: City of Lubbock
Owner
Representative(Sign.Keep Original Copy and Return All Others.See Heading for Return Address.) Dale
LanLockwood,Andrews
&Newnam,Inc.
PROPOSED CONTRACT MODIFICATION NO.2 DATE: January 7, 2020
Project: Canyon Lakes Sanitary Sewer Interceptor Rehabilitation Phase 2 Project No.: RFP 19-14354-TF
Contract For: City of Lubbock Contract Date: March 25,2019(NTP)
Subject of Proposed Contract Modification: Installation of collapsed section of pipe in Section 1 (Sta. 1+00—Sta. 10+50). Design
was done by the City of Lubbock's Engineering Department.This also includes a repair of a failed pipe section on the Downtown 1
interceptor in Mae Simmons Park.
Description:
PAY APPROXIMATE UNIT TOTAL UCA
ITEM QUANTITY UNITS DESCRIPTION OF ITEM PRICE COST
PROPOSAL
Proposed Sewer in Section 1
Furnish and install 24-inch sanitary sewer pipe
6 112 LF (FRP or PVC)by open cut(all depths), including $260.00 $29,120.00
excavation and trench safety.
Furnish and install new 60-inch diameter fiberglass
8B 1 EA manhole(to 10-ft of depth),including all piping $15,500.00 $15,500.00
connections to new and existing sanitary sewers.
22 3 EA Abandon/Remove existing manholes $6,700.00 $20,100.00
SUBTOTAL $64,720.00
Downtown Line Repair in Mae Simmons Park
Furnish and install 24-inch sanitary sewer pipe
6 240 LF (FRP or PVC)by open cut(all depths),including $260.00 $62,400.00
excavation and trench safety.
Remove existing manhole(all depths)and replace
8A 1 EA with new 60-inch diameter fiberglass manhole(to $16,500.00 $16,500.00
10-feet of depth), including all piping connections to
new and existing sanitary sewer mains.
Furnish and install transition coupling to connect
14 1 EA existing VC sewer pipe to proposed sewer FRP or $4,100.00 $4,100.00
PVC(30°or 24")
SUBTOTAL $83,000.00
TOTAL PCM 2 $147,720.00
Additional cost of$147,720.00 to the contract bid amount and 110 additional calendar days
Reason for Change:
The failed section in Section 1 can easily be completed while UCA is still working in the project area. This Section 1 has a lot of public
traffic in the area. The repair of the failed pipe in the Mae Simmons park eliminates the possibility of future overflows in the park area.
Recommended Lockwood. Andrews& Newnam, Inc.
By:
Engineer
01/07/2020
Representative Date
Accepted By: Utility Contractors of America
Contractor
01/07/2020
resentative Date
Approved By: City of Lubbock
Owner
Representative(Sign,Keep Original Copy and Return All Others.See Heading for Return Address.) Date