HomeMy WebLinkAboutOrdinance - 2004-O0131 - Approving Second Amended North Overton District Tax Increment Reinvestment Zone - 11/04/2004Fust Reading
November 4, 2004
Second Reading
November 18, 2004
Item No. 33 It9mNo. 24
<'-'
ORDINANCE NO. 2004-00131
AN ORDINANCE APPROVING IBE SECOND AMENDED NORTH
OVERTON DISTRICT TAX INCREMENT FINANCE REINVESTMENT
ZONE PROJECT PLAN AND FINANCE PLAN AS ADOPTED BY THE
BOARD OF DIRECTORS OF THE NORTH OVERTON TAX INCREMENT
FINANCING REINVESTMENT ZONE.
WHEREAS, the City Council of the City of Lubbock, upon receipt of a
petition requesting creation of a tax increment financing district from the owners of
more than 50 per cent of the appraised value of an area within the City of Lubbock
bounded by the Marsha Sharp Freeway on the north, University A venue on the
west, Broadway on the south and the alley between A venue R and A venue Q on the
east, adopted Ordinance No. 2002-029, March 14, 2002, establishing the North
Overton District Tax Increment Finance Reinvestment Zone and defining its
boundaries in accordance with the provisions of the Tax Increment Financing Act,
V.T.C.A. Tax Code, Chapter 311 (the "Act''); and
WHEREAS, the Board of Directors of the North Overton Tax Increment
Financing Reinvestment Zone, in accordance with the Act, prepared and adopted a
North Overton Area Project Plan and a North Overton Area Financing Plan, which
was approved June 26, 2002, by Ordinance No. 2002-0075; and
WHEREAS, due to increased development and changed circumstances, the
Board of Directors of the North Overton Tax Increment Financing Reinvestment
Zone adopted a First Amended Project Plan and a First Amended Finance Plan
which was approved by the City Council June 12, 2003, in Ordinance 2003-00062;
and
WHEREAS, the Board of Directors of the North Overton Tax Increment
Financing Reinvestment Zone has adopted a Second Amended Project Plan and a
Second Amended Finance Plan and has submitted these plans to the City Council
for approval; NOW THEREFORE:
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
SECTION 1: THAT the facts and recitations contained in the preamble of
this ordinance are hereby found and declared to be true and correct.
SECTION 2: THAT the City Council of the City of Lubbock makes the
following findings regarding the Second Amended North Overton Tax Increment
Financing Reinvestment Zone Project Plan and the Second Amended North
Overton Tax Increment Financing Reinvestment Zone Finance Plan, as adopted by
the Board of Directors of the North Overton Tax Increment Financing
Reinvestment Zone:
a) That the Second Amended North Overton Tax Increment Financing
Reinvestment Zone Finance Plan includes, as required by § 311.011 of the
Act, all of the following items:
1) a detailed list describing the estimated project costs of the zone, including
administrative expenses;
2) a statement listing the kind, number, and location of all proposed public
works or public improvements in the zone;
3) an economic feasibility study was included in the original project plan;
4) the estimated amount of bonded indebtedness to be incurred;
5) the time when related costs or monetary obligations are to be incurred;
6) a description of the methods of financing all estimated project costs and
the expected sources of revenue to finance or pay project costs, including
the percentage of tax increment to be derived from the property taxes of
each taxing unit that levies taxes on real property in the zone;
7) the current total appraised value of taxable real property in the zone;
8) the estimated captured appraised value of the zone during each year of its
existence; and
9) the duration of the zone.
b) That the Second Amended North Overton Tax Increment Financing
Reinvestment Zone Project Plan includes, as required by§ 311.011 of the
Act, all of the following items:
1) a map showing existing uses and conditions of real property in the zone
and a map showing proposed improvements to and proposed uses of that
property;
2) proposed changes of zoning ordinances, the master plan of the
municipality, building codes, and other municipal ordinances;
3) a list of estimated nonproject costs; and
4) a statement of a method of relocating persons to be displaced as a result of
implementing the plan.
c) That the Second Amended Plan is feasible and conforms to the City of
Lubbock Comprehensive Plan.
SECTION 3: That the Second Amended North Overton Tax Increment
Financing Reinvestment Zone Project Plan and the Second Amended North
NO TIF Second Amended Project Plan Ordinance Page2
Overton Tax Increment Financing Reinvestment Zone Finance Plan, as adopted by
the Board of Directors of the North Overton Tax Increment Financing
Reinvestment Zone are approved. A copy of each plan is attached hereto and
incorporated into this Ordinance as if fully set forth herein.
SECTION 4: That if any section, paragraph, clause or provision of this Ordinance
shall for any reason be held to be invalid or unenforceable, the invalidity or
unenforceability of such section, paragraph, clause or provision shall not affect any
of the remaining provisions of this Ordinance.
AND IT IS SO ORDERED
PASSED by the City Council on first reading this 4th day of November , 2004.
PASS ED by the City Council on second reading this 18th day of November,
2004.
TOM MARTIN, MAYOR PRO TEM
ATTEST:
~~d~ Rebecca Garza, City Secretary
CONTENT:
Craig arme , Managing Director
of Planning and Transportation
APPROVED AS TO FORM:
r---~c c;_.y. /7,-:? ~· .. ~"" ~ C ~ , ~ ~~~.------------Linda L. Chamales
Senior Attorney, Office Practice
LC: cityatt/Linda/TIF-NO SECO1',.'D AMENDED PLAN APPROVAL ORDINANCE
October 20, 2004
NO TIF Second Amended Project Plan Ordinance Page3
Ordinance No. 2004-00131
-------:N-orth 0verton-A:rea
Tax Increment Finance Reinvestment Zone
LUBBOCK, TEXAS
Prepared for
City of Lubbock
October 2004
Second Amended Project Plan
The North Overton Area was established in 1907 and over the next 20 years developed as
a middle-class neighborhood, with home ownership predominating. Following World
War II, the growth of Texas Tech stimulated a need for student housing. This need was
provided by many non-conforming apartments, converted garages, and subdivided
houses, reducing home ownership considerably. Continued growth of Tech encouraged
development of apartment buildings, further destroying the stability of the area.
By the 1980' s, the City of Lubbock recognized the need to "'explore methods of
stabilizing property values while allowing the area to develop to its fullest potential" and
appointed the Overton North Study Committee. This Committee formulated strategies to
address the area's problems and potential. Among the strategies was the possibility of
utilizing Tax Increment Financing. The City also retained RTKL in 1989 to prepare a
Redevelopment Plan for Downtown Lubbock, which included the North Overton area.
RTKL's plan identified many of the same issues as the Study Committee and more
particularly indicated, "the City must develop creative public/private joint development
opportunities and provide public improvements as incentives for development".
Through a series of economic and real estate factors, nothing materialized from the two
studies during the 1990's, and the situation in North Overton continued to stagnate.
However, at this time, a local developer has come forward with a plan to redevelop about
90% of the North Overton area and has petitioned the City to establish a Tax Increment
Financing (TIF) District to provide the necessary public funds to enter into a public-
private partnership. City staff, working with the developer, has prepared a list of public
infrastructure projects, which will stimulate and enhance the redevelopment of North
Overton. It is expected that the North Overton Area Tax Increment Financing
Reinvestment Zone planned expenditure of approximately $51.9 million for public
infrastructure improvements will result in future development/redevelopment in the Zone
which will increase the taxable value by approximately $317 Million over the Zone's 30-
year life.
As set forth in Section 311.011 of the Tax Increment Financing Act of the Tax Code, the
Project Plan for the North Overton Area Tax Increment Finance Reinvestment Zone,
Lubbock, Texas must and does include the following elements:
1. A map showing existing uses and conditions of real property in the
Zone and a map showing proposed improvements to and proposed
uses of the property.
Following is a map showing uses of real property in the North Overton
Area TIF Reinvestment Zone and a map indicating potential locations of
proposed public improvements in the zone.
Page 1
North Overton Second Amended Project Plan
City of Lubbock
Second Amended Project Plan
2. Proposed changes of zoning ordinances, the master plan of the
municipality, building codes, and other municipal ordinances.
No changes anticipated at this time except to zoning ordinances. Zoning
ordinances will be modified to provide architectural guidelines and special
zoning considerations to provide for redevelopment of the North Overton
area as a pedestrian-oriented, neo-traditional development.
3. A list of estimated non-project costs.
Non-project costs within the Zone area are those development costs not
paid for by the Zone. These costs will include, but are not limited to,
$333,955 Million of new development.
4. A statement of a method of relocating persons to be displaced as a
result of implementing the plan.
In the process of developing and redeveloping the Zone, it is not
contemplated there will be any involuntary relocations. However, it may
be necessary to relocate individuals and businesses through voluntary
buyout. In the event that this is required, the City or private developer will
follow the procedures that would be used in the development or
construction of other public or private improvements outside the Zone.
Page 2
North Overton Second Amended Project Plan
City of Lubbock
Second Amended Project Plan
Street reconstruction/resurfacing
A/E services
Reconstruction, curb & gutter
Rotaries
Rotary amenities
A/E services
Landscaping • irrigation,
lighting, street furniture
Glenna Goodacre Boulevard
A/E services
Replace cum & gutter
ROW acquisition
Glenna Goodacre Blvd. Amenities
A/E services
Landscaping -irrigation,
lighting, street furniture
Landscaping Parkway
A/E services
Landscaping -irrigation,
lighting, street furniture
Water/Waste Water
Replacement & relocation
Electric utility -underground
Pioneer Park Improvements
Marsha Sharp Frwy. Frontage
University Ave. Improvements
Replace cum & gutter
Incentive Projects
Subtotal
• Administration
Total Phase 1 TIF Cost
Phase 2, Years 7 • 30
~:~·-• ,, .. ,,-_-. .,,;,;:-. ---.
$1,252,311
$40,000
$373,074
$350,000
$629,093
$496,810
$653,712
0
0
0
$3,795,000
Public infrastructure -TIF reimbursement as per statute
•$900,000 reimbursement to developer as per agreement
Funds available after bonds are paid & bond interest
Total TIF Cost
$5,000,439 $6,252,750
$235,000 $275,000
$1,976,926 * $1,450,000
$950,000 $1,300,000
$920,907 $1,550,000
$2,753,190 $3,250,000
$3,338,538 $3,992,250
$500,000 $500,000
$1,000,000 $1,000,000
$900,000 $900,000
$3,500,000 $3,500,000
$23,970,000
$340,000 $340,000
$21,415,000 $24,310,000
$41,810,000
$66,121,000
Page 3
North Overton Second Amended Project Plan
City of Lubbock
Exhibit "A"
EXISTING LAND USE
r-1 North Overton TIF Boundary
Existing Land Use October 2004
• Commercial
Industrial
-Park
• Public Use
• High Density Residential
Medium Density Residential
Low Density Residential
Vacant land
Transportation Communication and Utilities
Ordinance No. 2004-00131
Exhibit«A"
North Overton Second Amended Project Plan
Ordinance No. 2004-00131
Exhibit "B"
PROPOSED IMPROVEMENTS AND PROPOSED USES
·-_.,..__ -------rm--~-...... .vrJl4rtaRt~
~.L.~~~
Overton Park Master Plan
I ' '\\,
The Lofls on Main "\\ di!IIJls -Sterling Univcnil)' Trails' ,_
Main Street Condominiums' It) \I l \ '.\s IL'>
Exhibit "B"
North Overton Second Amended Project Plan
Ordinance No. 2004-00131
North Overton Area
Tax Increment Financing Reinvestment Zone
LUBBOCK, TEXAS
OCTOBER 2004
Financing Plan
The Financing Plan provides information on the projected impact that the North Overton Area
Tax Increment Finance Reinvestment Zone (Zone) could have on the property described in
Exhibit A. It will also describe how that impact could be utilized to enhance the area and region
through leveraging the resources of each entity that participate in the project.
Below is a summary of the Financing Plan items required by law:
1. The proposed public improvements in the Zone are as follows:
• Capital costs, including the actual costs of the acquisition and construction of
public works, public improvements, new buildings, structures, and fixtures; the
actual costs of the acquisition, demolition, alteration, remodeling, repair, or
reconstruction of existing buildings, structures, and fixtures; and the actual costs
of the acquisition of land and equipment and the clearing and grading of land;
• Financing costs, including all interest paid to holders of evidences of indebtedness
or other obligations issued to pay for project costs and any premium paid over the
principal amount of the obligations because of the redemption of the obligations
before maturity;
• Any real property assembly costs;
• Professional service costs, including those incurred for architectural, planning,
engineering, and legal advice and services;
• Any relocation costs;
• Organizational costs, including costs of conducting environmental impact studies
or other studies, the cost of publicizing the creation of the Zone, and the cost of
implementing the project plan for the Zone;
• Interest before and during construction and for one year after completion of
construction, whether or not capitalized;
• The amount of any contributions made by the municipality from general revenue
for the implementation of the project plan;
• Imputed administrative costs, including reasonable charges for the time spent by
employees of the municipality in connection with the implementation of a project
plan;
• The cost of operating the Zone and project facilities; and
Pagel
North Overton Area Second Amended Fimncing Plan
City of Lubbock
Financing Plan
• Payments made at the discretion of the governing body of the municipality that
the municipality finds necessary or convenient to the creation of the Zone or to
the implementation of the project plans for the Zone.
2. Estimated Project Cost of Zone, including administrative expenses.
• Project cost estimates currently total $3.795 Million for Projects 1, 2 & 3 and
$20.515 Million for remaining projects, for a total of project cost of $24.31
Million. Administrative expense estimates currently total $340,000.
3. Economic Feasibilty Study.
• An economic feasibility study has been completed and is included as a part of this
Financing Plan.
4. The estimated amount of bonded indebtedness to be incurred.
• The debt capacity produced from the estimated tax increment through the 2010
period should yield approximately $24.3M at issuance and an estimated additional
$1. 7M from coverage. This should yield a total of approximately $26M in
funding capacity over this time period.
5. The time when related costs or monetary obligations are to be incurred.
• Monetary obligations will be incurred with each bond issue; however, it is
expected that development agreements will be in place, which would provide
sufficient tax increment to pay debt coverage for each bond issuance.
6. A description of the methods of financing all estimated project costs and the
expected sources of revenue to finance or pay project costs including the percentage
of tax increment to be derived from the property taxes of each taxing unit on real
property in the Zone.
• Project costs will be financed using bond issues with payment provided by tax
increment funds received. The revenue sources will be the real property taxes
captured by the Zone, which will account for I 00% of revenues used to fund
project costs and bonds issued. For the Financial Plan, it is assumed that all
taxing jurisdictions will participate at I 00% of their incremental taxable value.
7. The current total appraised value of taxable real property in the Zone.
• The appraised value of the taxable real property in the Zone that the Lubbock
Central Appraisal District certified in July 2002 was $26.9 Million. This amount
is the base value for the district in calculating future increments.
Page2
North Overton Area Second Amended Fi1U11cing Plan
City ofLubbock
Financing Plan
8. The estimated appraised valued of the improvements in the Zone during each year
of existence.
Table 1
YEAR
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
TOTAL
• The estimated appraised value of the improvements in the Zone per year is listed
in the following table.
ANNUAL CAPTURED VALUE
ESTIMATED
DEMOLITIONS I K -
(2,019)
(12,395)
(2,362)
-
---
-------
---
-
-
--
-------
--
06z776l
ESTIMATED
ESTIMATED ADJUSTED CAPTURED
NEW DEVELOPMENT i K VALUE$K -
12,406
21,632
22,142
126,305
102,144
35,913
13,413 --
---
--
---------------.
333z955
-
10,387
9,237
19,780
126,305
102,144
35,913
13,413
---------
-
----
-----
--
-
-
317:179
Page3
North Overton Area Second Amended Finaicing Plan
City of Lubbock
Table 2
YEAR
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
TOTAL
Financing Plan
• The estimated annual incremental funds available from development and
redevelopment in the Zone are listed in the following table.
ANNUAL INCREMENTAL FUNDS AVAILABLE
ESTIMATED ESTIMATED ESTIMATED
ADJUSTED CAPTURED CUMULATIVE CAPTURED ANNUAL TAX
VALUE, $K VALUE. $K INCREMENT1 $K *
---
10,387 10,387 -
9,237 19,624 96
19,780 39,404 178
126,305 165,709 339
102,144 267,853 1,361
35,913 303,766 2,187
13,413 317,179 2,478
-317,179 2,586 -317,179 2,586
-317,179 2,586
-317,179 2,586
-317,179 2,586
-317,179 2,586
. 317,179 2,586
-317,179 2,586
-317,179 2,586
-317,179 2,586
-317,179 2,586
-317,179 2,586
-317,179 2,586
-317,179 2,586
-317,179 2,586
-317,179 2,586
-317,179 2,586
-317,179 2,586
-317,179 2,586
-317,179 2,586
-317,179 2,586
-317,179 2,586
-317,179 2,586
66:121
* Based on 100% participation and projected tax rates of: City-$ 0.45970; Counly-$0.255870; Hospital-$0.107420; Water District-
$0.008300.
Based on estimated collected amount of increment (97.34% collection rate)
Page4
North Overton Area Second Amended Fimncing Plan
City of Lubbock