AN APPROPRIATION ORDINANCE
WHEREAS, the City Council of the City of Lubbock finds it is
necessary to appropriate certain specific funds out of bond funds for
an approved project:
NOW THEREFORE,
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
There is hereby appropriated out of the following described bond
fund, to-wit: Sanitary Sewer Capital Project Fund
The sum $
For the following purpose:
Passed by
A£ril
Passed by
April
Construction of major trunk sewer lines.
The net cost to the City will be $727,000.
See attached.
AND IT IS SO ORDERED
the Council on first reading this 9th day of
' 1~4
the Counci 1 on second reading this 23rd day of
, 19 64
, MAYOR .
APPROVED
GWO 10425 Downtown Trunk Sewer and Treated Effluent Line
Contract
Engr,
Paving repair
$ 142,596.66
7,129,83
2,500,00
$ 152,226,49
GWO 10426 Extension to Northwest Trunk Sewer and Acuff Road
Trunk Sewer
Contract
Engr.
Paving repair
$ 379,813.24
5,097.47
1,500,00
GWO 10427 Oak Avenue Lift Station Sewer and Cresthill Trunk Sewer
Contract
Engr,
Paving repair
$ 444,522,30
22,226,12
500,00
$ 467,248.42