February 10, 2000
Item No. 44
RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK
THAT the Mayor of the City of Lubbock BE and is hereby authorized and
directed to execute for and on behalf of the City of Lubbock, by and between the City of
Lubbock and David Wood Construction Company, a Change Order # Three (3) to
provide a sprinkler system in the vehicle maintenance building of Fire Station #2
Complex, and related documents. Said Change Order is attached hereto and incorporated
in this resolution as if fully set forth herein and shall be included in the minutes of the
City Council.
Passed by the City Council this 10th day of February 2000.
Max Ince, Mayor Pro Tem
APPROVED AS TO CONTENT:
Facilities Manager
APPROVED AS TO FORM:
William de Haas
Competition and Contracts Manager/Attorney
Ccdoca/Safe Communities Program.Res
CITY OF LUBBOCK
CHANGE ORDER
CHANGE ORDER #: Three (3)
DATE: January 7, 2000
Resolution No. 2000—R0042
February 10. 2000
Item No. 44
CITY OF LUBBOCK BID#: 98212 PROJECT NAME: Fire Station #2 Complex
CONTRACTOR: David Wood Construction Company
DESCRIPTION OF WORK:
This change order will provide for a wet sprinkler system in the entire Vehicle Maintenance Building as
shown below:
CCR#50B: Add wet sprinkler system to Vehicle Maintenance Building
TOTAL CHANGE ORDER #3
ITEM DESCRIPTION
A. ORIGINAL CONTRACT VALUE:
B. AMOUNT OF THIS CHANGE ORDER:
C PERCENT OF CONTRACT VALUE THIS CHANGE ORDER (B/A)
D. AMOUNT OF PREVIOUS CHANGE ORDERS:
E. TOTAL AMOUNT OF ALL CHANGE ORDER (B+D):
F. PERCENT OF CONTRACT OF ALL CHANGE ORDERS (E/A):
G. NEW CONTRACT AMOUNT (A+E):
SIGNATURES AND DATE
L/ 11 / z4oa
REPRESENTATIVE
DEPARTMENT
2* & asp
CITY MANAGER
$37,112.00
$37,112.00
VALUE
$4,587,900.00
$15,951.00
$53,063.00
$4,640,963.00