HomeMy WebLinkAboutResolution - 3769 - Accept Paving Improvements-Williams & Peters Inc - Lots 95-126, PH Addition - 12_12_1991Resolution No. 3769
December 12, 1991
Item #9
JWF:js
RESOLUTION
RESOLUTION ACCEPTING IMPROVEMENTS ON PORTIONS OF STREETS AND AVENUES AS
LISTED BELOW:
WHEREAS, in conformance with the paving requirement provisions of Chap-
ter 25 of the City of Lubbock Code of Ordinances, the subdivider of Preston
Hills Addition, Lots 95-126 made arrangements with Williams & Peters Construc-
tion Company, Inc. for the construction of paving improvements on certain
streets dedicated in said subdivision under the provisions of said Ordinance
prior to the recording of the subdivision plat of the above -mentioned Addition
including the following streets:
Frankford Avenue (C & G only) from its intersection with the North end
of the alley between 85th and 86th Streets to its intersection with the
North end of the alley return between 84th and 85th Streets known and
designated as New Subdivision Sub -Unit Number 50 of Unit Number 2034.
Elmwood Avenue from its intersection with the South lip line of 84th
Street to its intersection with the West end of the cul-de-sac at 85th
Street known and designated as New Subdivision Sub -Unit Number 51 of
Unit Number 2034.
Englewood Avenue from its intersection with the North end of the alley
return between 85th and 86th Streets to its intersection with the South
lip line of 85th Street known and designated as New Subdivision Sub -Unit
Number 52 of Unit Number 2034.
84th Street from its intersection with the Northeast corner of Lot 95 to
its intersection with the West end of radius at Southwest corner of 84th
Street and Elmwood Avenue known and designated as New Subdivision Sub -
Unit Number 53 of Unit Number 2034.
85th Street from its intersection with the cul-de-sac at Frankford
Avenue to its intersection with the West end of the cul-de-sac at Elm-
wood Avenue known and designated as New Subdivision Sub -Unit Number 54
of Unit Number 2034.
WHEREAS, the construction of the above improvements on the above -
mentioned streets was performed under the supervision of the City Engineer,
and said improvements have been completed and have been inspected and found to
have been constructed in accordance with City specifications and in accordance
with the provisions of Chapter 25 of the City of Lubbock Code of Ordinances;
NOW THEREFORE:
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
SECTION 1. THAT the improvements on said portions of the above -
mentioned streets BE and the same are hereby accepted and the City Engineer BE
and he is hereby authorized to notify the Developer of acceptance by the
Lubbock City Council.
SECTION 2. THAT this Resolution shall take effect and be in force from
and after its passage.
Passed by the City Council this 12th day of
ATJEST:
ane�te Boyd, City 5ecr
APPROVED,AS TO CONTENT:
y U. Herter, City tnginee
APPROVED AS TO FORM:
l j
a
orth Fullingidl, Assist City
t rney ri
December , 1991.
- 2 -
Resolution No. 3769
December 12, 1991
Item #9
CONSOLIDATED FINAL PAVING ESTIMATE
LOTS 95-126
PRESTON HILLS
PAVING QUANTITIES
DATE: November
21, 1991
$7.00
$25.00
S.Y.
$5.50
$25.00
S.Y.
UNIT
PAVING
L.F.
S.Y.
VALLEY
AND
6" CALICHE
CURB &
ALLEY
GUTTER &
SUB -UNIT LOCATION
BASE
GUTTER
RETURNS
FILLETS
2034-50 E/2 of Frankford Ave. from
N. end alley return between
85th & 86th to N. end alley
return between 84th & 85th 278.4 22.8
2034-51 Elmwood Avenue from SLL of
84th St. to West end of
cul-de-sac at 85th St. 1,200.9 681.6 40.7
2034-52 Englewood Ave. from N. end
of alley return between
86th & 85th to SLL of 85th
St. 418.2 244.5 16.7
2034-53 84th St. from N.E. corner
of Lot 95 to West end of
radius at S.W. corner of
84th & Elmwood Avenue 956.5 440.7
2034-54 85th St. from cul-de-sac
at Frankford Ave. to West
end of cul-de-sac at
Elmwood Avenue 2,466.3 1,446.2 15.6
TOTAL DEVELOPER CONTRACT QUANTITIES 5,041.9 3,091.4 63.5 32.3
FINAL COST ESTIMATE
Develouer Contract Cost
5,041.9
S.Y.
Paving 6" Base
@
$ 7.00
$35,293.30
3,091.4
L.F.
Curb and Gutter
@
5.50
17,002.70
63.5
S.Y.
Alley Returns
@
25.00
1,587.50
32.3
S.Y.
Standard Valley/Gutter Returns
@
25.00
807.50
TOTAL
$54,691.00
CONTRACT COST DISTRIBUTION
UNIT &
CONSTRUCTION
SUB -UNIT
COST
2034-50
$ 2,101.20
2034-51
13,172.60
2034-52
4,689.65
2034-53
9,119.35
2034-54
25,608.20
TOTAL
$54,691.00