RESOLUTION 1255 - 11/11/82
01
RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of LUbbock BE and is hereby authorized
and directed to execute for and on behalf of the City of Lubbock a Change
Order No. 1 to the 1982 Assessment Paving Program (G.W.O. 11,593), with
Kerr Construction Company, a copy of which is attached herewith which
shall be spread upon the minutes of the Council and as spread upon the
minutes of this Council shall constitute and be a part of this Resolution
as if fully copied herein in detail.
Passed by the City Council this llth Day of November, 1982.
Bil McAlister, Mayor
ATTEST: ,
Evelyn G fga, CityS r ary
APPROVED AS TO CONTENT:
Don J pings City Engineer
APPROVED AS TO FORI4:
hn Ross Jr., City Attorney
TO: Kerr Construction Company
Box 888
Lubbock, Texas 79408
Gentlemen:
WHEREAS, it is desirable to make changes in the plans and specifications
for G.W.O. 11,593, being namely the additional quantities for the Municipal
Garage Parking Lot Paving.
Original Amount of Contract G.W.O. 11,593 $559,700.60
Increased by Change Order No. 1 $139,914.00
Total Amount of Contract $699,614.60
Completion for this Change Order -- Same as Original Contract.
THIS AGREEMENT WITNESSETH: In consideration of the mutual advantages
gained, the Owner and -the Contractor agree to the change shown herein and in
the revised plans, the Owner agrees to pay the Contractor the amount of in-
crease in cash. the Contractor agrees to proceed with construction and to
adhere to applicable specifications, under the direction of the Engineer.
Furthermore, the parties agree that the original contract between the Owner
and the Contractor shall be modified to the extent herein indicated, including
one (1) attachment.
IN WITNESS WHEREOF, the Owner and the Contractor have hereto set their
hands this llth day of November 1982.
rr Construction Company
(Contractor) ///�
By Xi/�% �'���'�/ Title: V/
Kerr Construction Company.
CITY OF LUBBOCK
(Owner)
By Attest:
B 11 McAlister, Mayor
RECOMMENDED FOR APPROVAL
UN
Don J nings, ity Engineer
APPROVED AS TO FORM:
L
ohn C. Ross, Jr., City A torney
Evelyn Gaf ga, City
07 /
Item
3
5
GWO 11,593
CHANGE ORDER NO. 1
Quantity
Bid
& Unit
Description of Item Price
15,910 S.Y.
Paving: 1-1/2" compacted T.H.D. $6.15
Type "C" A.C. Paving with crushed
stone or crushed gravel with a
minimum of 85% crushed faces, in-
cluding subgrade preparation, 9"
of caliche base, prime and tack
coat, complete in place, per
square yard
640 L.F.
Curb and Gutter: 6" concrete curb $5.50
and gutter or 30" wide separate
gutter, including subgrade prepara-
tion, complete in place, per linear
foot
1,814 S.Y.
Valley Gutters: Reinforced Concrete $21.25
(3,000 #/7 day high early type cement)
valley gutters including subgrade pre-
paration, complete in place with loca-
tion as directed by engineer, per square
yard
Total
$97,846.50
$ 3,520.00
$35,547.5Q
Total Increase for Change Order. No. 1 $139,914.00
Original Contract Amount $559,700.60
New Contract Amount $699,6.14.00