RESOLUTION
RESOLUTION 1178 - 8/12/82
(Amends Reso 924, 9/24/81
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock BE and is hereby authorized and
directed to execute for and on behalf of the City of Lubbock Change Order No.
1 to a Contract heretofore entered into by and between said City and Row -Wall
Electric, Inc. for the installation of remote control facilities at Bailey
County Well Field pursuant to W.W.O. 11609 to increase the number of wells from
120 to 143 and extend Contract time to November 15, 1982, attached herewith
which shall be spread upon the minutes of the Council and as spread upon the
minutes of this Council shall constitute and be a part of this Resolution as if
fully copied herein in detail.
Passed by the City Council this 12th
I ATTEST:
Elvelyn Ga ga, City S t y-Treasurer
APPROVED AS TO CONTENT:
r
Wi r D. Watson, Chief
Water tilities Engineer
APPROVED AS TO FORM:
V L
J. rth Full ngim, Asst. City A rney
day of Au u t ,1982.
i
LL MEALISTER, MAYOR
RESOLUTION 1178 - 8/12/82
CHANGE ORDER NO. 1
Remote Control Facilities
Bailey County Well Field
City of Lubbock, Texas
TO: ROW -WALL ELECTRIC, INC.
P. 0. BOX 1914
LUBBOCK, TEXAS 79408
General description of work included in the original contract:
Install remote control facilities for 120 wells in the City's Bailey
County Well Field using one-way FM radio channel for communication between
the central control point and the individual well sites.
Original Amount of Contract $ 197,975.00
Change Order No. 1 ADD 46,126.40
Adjusted Contract Amount $__244,101.40
Construction Time Extended to Q Nov. 15, 1982
WHEREAS, it is desirable to make changes in the work to be constructed
under this project.
THIS AGREEMENT WITNESSETH: In consideration of the mutual advantage
gained, the Owner and the Contractor agree to the changes indicated below and
further agree that the.amount of the contract and the construction time shall
be adjusted by the amounts shown above.
1. Increase the number of wells provided with
remote control facilities from 120 to 143.
ADD` $ 43,556.80
2. Provide and install a stand-by transmitting
unit at the central control point.
ADD $ 2,927.00
3. Furnish 4 printed -circuit boards for
maintenance of the facilities.
ADD $ 449.60
4. Reduce the number of Hand -Off -Automatic
switches installed in'existing starters
from 50 to 20 units.
DEDUCT $ 807.00
5. Construction time to be extended to
November 15, 1982, to allow time for
delivery and installation of equipment
included in this Change Order.
6. Retainage on the work completed under
the original contract to be reduced to
$1,000 until final completion of the
project.
IN WITNESS WHEREOF, the Owner and the Contractor have hereto set their
hands this 12th day of August , 1982.
-----------------------------------------------------------------------------
RECOMMENDED: PARKHILL, SMITH & COOPER, INC., Consulting Engineers
B� ,Project Engineer,-�?/2-,-1982
APPROVED: ROW -WALL ELECTRIC, INC., Contractor
By Vice -President , Sept. 2082
APPROVED: CITY OF LUBBOCK, TEXAS, Owner
By ,
NIAY0P, , . AUG 12 JgR