HomeMy WebLinkAboutResolution - 2010-R0616 - Contract 9874 Talon/LPE For Water Well Plugging Services - 12/15/2010Resolution No. 2010-RO616
December 15, 2010
Item No. 5.21
RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock is hereby authorized and directed to
execute for and on behalf of the City of Lubbock, Contract No. 98741JOC 11 -013 -FM for
Water Well Plugging Phase II, by and between the City of Lubbock and Talon/LPE, Ltd
of Amarillo, Texas, and related documents. Said Contract is attached hereto and
incorporated in this resolution as if fully set forth herein and shall be included in the
minutes of the City Council.
Passed by the City Council on December 15, 2010
��X A�---
TOM MARTIN, MAYOR
ATTEST:
Rebe a Garza, CitySecreta
APPROVED AS TO CONTENT:
)ILJO�
Marsha Reed, P.E.
Chief Operating Officer
APPROVED AS TO FORM:
4
C ad Weaver. Assistant City Attorney
sj:ccdocs RES.Contract-Talon LPE, Ltd
11.19.10
Resolution No. 2010—RO61
Contract No.9876
City of Lubbock Job Order
This Job Order is governed by all terms and conditions of the Contract referenced below which is hereby
incorporated by reference.
Owner: Wesley Everett, Director of Facilities Management for — Water Well Plugging Phase II
NJPA Contract Number: TX04-061980-TAIL, National Joint Powers alliance (NJPA), Indefinite Quality
Construction Contract.
Contract Job Order Number: 11 -013 -FM
Date of Contract: September 25, 2008
Job Order Date: November 19, 2010
Contractor: Talon/LPE
Summary and Description of Statement of Work attached hereto: The scope of work includes plugging 25
previously identified water wells, removal of 4 submersible or turbine pumps, removal of 14 steel doghouse
structures, and the demolition of one brick building.
Talon Job Order Nuinber: 010389.00 hereto attached. and Insurance Requirements per Exhibit A, attached.
Value of Pre -Priced Work: $147,004.83
Value of Non -Pre -Priced work: $ 00.00
Payment and Performance Bonds: $3,769.73
Total Fixed Price stipulated sum for this Job Order (Job Order Sum): $150,774.56
Notice to Proceed Date for this Job Order: To be issued after City Council approval
Expected Completion Date for this Job Order: to be determined after City Council approval.
Liquidated Damages (if different than set forth in Agreement): $25 per day
CONTRACTOR:
Talon/LPE
By:
PRIN119 .AME: 13RIDGER HOWARD
TITLE: PROJECT MANAGER
COMPLETE ADDRESS:
Company: Talon/LPE
Address: 921 N. Bivins Street
City, State, Zip: Amarillo, Texas 79107
L �EVal-�
Wesley Everett, Director of Facilities
CITY OF LUBBOCK, TEXAS (OWNER)
Tom Martin, Mayor
ATTEST:
Reber a Garza, City Secretary
APPR D AS T FORM:
Assistant City Attorney
Contractor's Price Proposal - Detail Continues..
Work Order Number: 010389.00
Work Order Title: City of Lubbock - Well Plugging Phase II
Section - 02
11 02213 0004 CY Native Soil/Dirt- Common $753.76
Quantity Unit Price Factor Total
Installation 47.00 x 12.83 x 1.2500 753.76
12 02616 0019
EA Asphalt Placement For Small Repair Areas, Cold Mix Modified, Up To 3 Tons
$1,138.89
Quantity Unit Price Factor
Total
Installation 100 x 911.11 x 1.2500
1,138.89
Subtotal for Section - 02
$10,570.23
Section - 03
13 03640 0003
CF Pressure Injected Cementitious Grout
$116,263.68
Quantity Unit Price Factor
Total
Installation 6,809.00 x 13.66 x 1.2500
116,263.68
Subtotal for Section - 03
$116,263.68
Proposal Total $150,774.56
This total represents the correct total for the proposal. Any discrepancy between line totals,
sub -totals and the proposal total Is due to rounding.
Subcontractor Listing Page 2 of 2
EZIQC - Buy Board 11/16/2010
Contractor's Price Proposal - Summary
Date: November 16, 2010
Re: IOC Master Contract*
Work Order #:
Owner PO #:
Title:
Area 1-1- TAL
010389.00
City of Lubbock - Well Plugging Phase II
Contractor: Talon/LPE
Proposal Value: $150,774.56
Section - 01 $23,940.65
Section - 02 $10,570.23
Section - 03
$116,263.68
Proposal Total $150,774.56
Thisl total represents the correct total for the proposal. Any discrepancy between line totals,
sub -totals and the proposal total Is due to rounding.
Contractor's Price Proposal - Summary Page 1 of 1
EZIQC - Buy Board 11/16/2010
Contractor's Price Proposal - Detail
Date: November 16, 2010
Re: IQC Master Contract #:
Area 1-1- TAL
Work Order #:
010389.00
Owner PO M
Line Total
Title:
City of Lubbock - Well Plugging Phase 11
Contractor:
Talon/LPE
Proposal Value:
$150,774.56
Contractor's Price Proposal - Detail Page 1 of 2
EZ/QC - Buy Board 11/16/2010
Sect
Item Mod.
UOM Description
Line Total
Labor
Equip.
Material (Excludes)
Section - 01
1
01590
0228
WK 36" Wide, 1/8 CY Bobcat, With Full -Time Operator
$5,682.08
Quantity Unit Price Factor
Total
Installation 3.00 x 1,515.22 x 1.2500
5,682.08
2
01590
0327
WK 1/2 To 5/8 CY, 65 HP, Loader -Backhoe, With Full -Time Operator
$6,740.18
Quantity Unit Price Factor
Total
Installation 3.00 x 1,797.38 x 1.2500
6,740.18
3
01590
0904
WK 1-1/2 Ton Flat Bed Truck, 4 x 2, With Full -Time Truck DriverNote: Includes
$5,812.39
hydraulic tiltbed.
Quantity Unit Price Factor
Total
Installation 3.00 x 1,549.97 x 1.2500
5,812.39
4
01590
0911
WK 1/2 To 3/4 Ton Light Duty Truck, 4 x 2 Conventional PickupNote: With full-time
$5,099.74
truck driver
Quantity Unit Price Factor
Total
Installation 3.00 x 1,359.93 x 1.2500
5,099.74
5
01590
0999
EA Bobcat Delivery, Mobilization And DemobilizationNote: Use for bobcat, lifts up to
$116.33
35' or similar sized equipment Includes delivery fee, delivery, set-up and return.
Quantity Unit Price Factor
Total
Installation 100 x 93.06 x 1.2500
116.33
8
01590
1001
EA Backhoe, Dozer Or Roller Up To 250 HP Delivery, Mobilization And
$489.93
DemobilizationNote: Use for backhoe, dozer, roller, loader, excavator, lifts over 40'
to 60' or similar sized equipment Includes delivery fee, delivery, set-up and return.
Quantity Unit Price Factor
Total
Installation 100 x 391.94 x 1.2500
489.93
$23,940.65
Subtotal for Section - 01
Section - 02
7
02111
0009
CCF Demo Steel Framed Building With Bulldozer/Excavator Remove Building
$2,436.00
Quantity Unit Price Factor
Total
Installation 112.00 x 17.40 x 1.2500
2,436.00
8
02111
0015
CCF Demo Masonry Building With Bulldozer/Excavator Remove Building
$224.93
Quantity Unit Price Factor
Total
Installation 1152 x 15,62 x 1.2500
224.93
9
02112
0091
CF Demo Reinforced Concrete Building Foundation
$3,676.65
Quantity Unit Price Factor
Total
Installation 772.00 x 3.81 x 1.2500
3,676.65
10
02115
0040
HR Hourly Office Work For Both For Reports Required For EPANote: Includes title
$2,340.00
searches, well survey data, drawing site drawings. filing preliminary work with EPA
for feedback, prepare on CAP -A and CAP -B plans, etc. Hours not to be used in
association with other tasks performed.
Quantity Unit Price Factor
Total
Installation 40.00 x 46.80 x 1.2500
2,340.00
Contractor's Price Proposal - Detail Page 1 of 2
EZ/QC - Buy Board 11/16/2010