RESOLUTION
WHEREAS, the Metropolitan Planning Organization for the Lubbock Urbanized
Area, in cooperation with the City of Lubbock, has prepared a Transportation
Improvement Program with annual element; and
WHEREAS, the City Council of the City of Lubbock approves of the priority
projects listed by the Metropolitan Planning Organization; NOW THEREFORE:
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the 1981-1982 Transportation Improvement Program with annual element;
attached hereto and incorporated herein by reference for all purposes, is -
hereby approved by the City Council of the City of Lubbock.
Passed by the City Council this 13th day of August , 1981.
BI c TER, MAYOR
ATTEST:
_
Evelyn Gaffga, City S Cc rCt -Treasurer
i
APPROVED AS TO CONTENT:
B. H. McDaniel, Traffic Engineering Director
APPROVED AS TO FORM:
Angela Ad s, Assistant City Attorney
TRANSPORTATION IMPROVEMENT PROGRAM
FOR LUBBOCK URBANIZED AREA
FY 1982
(September 1, 1981 — August 31, 1982)
c
a
TABLE OF CONTENTS
Five-year program of projects for streets
and highways
Annual element for streets and highways
Five-year program of project for transit
Annual element for transit
Breakdown for federal participation
Items discussed in Attachment A
PAGE
1
S
7
8
9
10
s
July, 1981
TRANSPORTATION IMPROVEMENT PROGRAM
FOR LUBBOCK URBANIZED AREA
FY 1982
(September 1, 1981 - August 31, 1982)
Streets and Highways Element
The Transportation Improvement Program (TIP) is a staged
prograa developed
in cooperation with the City of Lubbock, Lubbock County,
State Department
of Highways and Public Transportation, and local transit
operators. The
TIP is in agreement with the transportation plan of the Lubbock
Urban
Transportation Study. This program follows the "3-C"-134.planning
process
outlined in United States Code 23, "Highways", and also the rules and regu-
lations set forth in the.September 17, 1975, Federal Register.
The Streets and highways element of the transportation improvement program
consists of the following projects recommended for advancement during the
period, FY 1982-1986.
Project
Estimated Cost
I. H. Extension, N. Loop 289 to S. Loop 289
Investigation Planning
$ 175,000.
US 62 (19th Street) at Avenue S
50th Street at US 84 (Avenue Q)
Intersection Revisions
$ 203,000.
Avenue A at Broadway
Traffic Signal Improvements
$ 20*000.
US 84 (Clovis Road), N Loop 289 to Avenue Q
near 3rd Street
$ 2,250,000.
4th Street (FM2255), US 82 (Brownfield Highway)
to Indiana Avenue
$ 420,000.
4th Street (FM2255), Indiana. Avenue To W Loop 289
$ 2,125,000.
IH Extension, N Loop 289 to S Loop 289
ROW Purchase
$ 110,000,000.
Quaker Avenue, S Loop 289 to 82nd Street
$ 12216,000.
Traffic Signal System Design
$ 265,000.
S
82nd Street and University Avenue
Traffic Signal Installation
I. H. 27 Extension, N Loop 289 to S Loop 289
Investigation & Planning Expense (Consultant)
Prepare ROW Plans
Prepare Plans for Construction
Central Business District
Permanent Pavement Markings
4th Street (FM2255) at Brownfield Road
Traffic Signal Installation
Clovis Road at Indiana Avenue
Traffic Signal Installation
Juniper Avenue near 31st Street
Provide RR protective devices
Avenue Q, 50th Street to 1400' nw of
Traffic Circle
Traffic Signal System Contruction
Frankford Avenue, 19th Street to 34th Street
82nd Street and Quaker Avenue
Traffic Signal Installation
I. H. 27 Extension, N Loop 289 to S
Loop 289
Investigation & Planning Expense
(Consultant)
Prepare ROW Plans
Prepare Plans for Construction
Quaker Avenue, Loop 289 to US 84
Frankford Avenue at Spur 327
Traffic Signal Installation
34th Street, 1400' SE of Cemetery Curve to Avenue A
Loop 289 at N Quirt Avenue
Traffic Signal Installation
Quirt Avenue, 52nd Street to S Loop
289
I. H. 27 Extension, N Loop 289 to S
Loop 289.
Investigation & Planning Expense
(Consultant)
Prepare ROW Plans
Prepare Plans for Construction
E. 34th Street at Quirt Avenue
Grade Separation or Interchange
$ 40,000.
$ 1,500,000.
$ 2272280.
$ '100,000.
$ 409000.
$ 70,000.
$ 850,000.
No Estimate Available
$ 48 5 , 000 .
$ 40 , 000 .
$ 1,000,000.
$ 2,380,000.
$ 45,000.
$ 1,0209000.
$ 75,000.
$ 1,224,000.
$� 1,000,000.
$ 149778:,OQ0.
-2-
82nd Street, US 87 (Tahoka Road) to Elgin Avenue $ 4,000,OCO.
Frankford, Avenue (FM2528), Ursuline Street
to 4th Street (FM2255)' $ 2,130,000.
50th Street, University Avenue to Gary Avenue $ 650,0�0.
I. H. 27 Extension, N Loop 289 to Broadway
Construction $ 30,000,000.
Indiana Avenue, 95th Street to 103rd Street
Construction on east half of street $ 600,000.
Frankford Avenue (FM2528) at 4th Street (FM2255)
Traffic Signal Installation $ 45,000.
N. Quirt Avenue at FM 2641
Traffic Signal Installation $ 45,000.
I. H. 27 Extension, N Loop 289 to S Loop 289
Investigation S Planning Expenses (Consultant)
Prepare ROW Plans
Prepare Plans for Construction $ 1,000,0-DO.
Avenue A, 35th Street to 45th Street
Widen to construct continuous left turn lane $ 420,000.
Quaker Avenue, 82nd Street to 98th Street $ 2,836,020.
I. H. 27 Extension, Broadway to 34th Street
Construction $ 599000,0!0.
Indiana Avenue near Clovis Road (US 84)
Provide planking and signalization
for RR crossing
$
75,0100.
Slide Road, 19th Street to 28th Street
$
19491,000.
4th Street at Slide Road
Itersection Improvement
$
500 000.
Indiana Avenue, 34th Street to 50th Street - widen
ROW and Construction
$
5,670,000.
Municipal Drive, Quirt Avenue to Guava Avenue
$
900,030.
19th Street at Brownfield Highway
ROW for interchange
$
5,390,0D0.
4th Street at Tech Freeway
ROW for interchange
$
4,620,000.
University Avenue, Clovis Road to 4th Street
Traffic Signal Improvements
$
75,000.
-3-
usy, 1981
Frankford Avenue, Spur 327 to 82nd Street 1,755,0100.
I. H. 27 Extension, N Loop 289 to S Loop 289
Investigation & Planning Expenses (Consultant)
Prepare ROW Plans
Prepare Plans for Construction $ 7502005.
I. H. 27 Extension, 34th Street to S Loop 289
Construction $ 55,000,000.
318,497,283.
—4—
b
July, 1981
ANNUAL ELEMENT - STREETS AND HIGHWAYS -
a
• TRANSPORTATION IMPROVEMENT PROGRAM �_-
September 1, 1981 - August 31, 1982
CTh's'sifi-
Funding
cfatl6n,.
Projects
Cost
Federal
State
Local
FA-1 '=
I. H. Extension, N Loop 289
to S Loop 289
Investigation & Planning
Expense
175,000.
157,500.
17,500.
U.S. 62 (19th Street) at
Avenue S - 50th Street at
U.S. 84 (Avenue Q)
Intersection Revision
TSM 200,000.
200,000.
Avenue A at Broadway
Traffic Signal Improvements
TSM 20,000.
20,000.
\U
U.S. 84 (Clovis Road), N Loop 289
to Avenue Q near 3rd Street
2,250,000.
1,687,500.
562,500.
'kU
4th Street (FM2255), U.S. 82
(Brownfield Highway) to Indiana
Avenue
420,000.
315,000.
105,000.
FAU
4th Street (FM2255), Indiana Avenue
_
to W Loop 289
20125,000.
1,593,750.
531,250.
FAI
I.H. Extension, N Loop 289 to
S Loop 289
RbW Purchase
110,000,000.
99,000,000.
11,000,000.
Qunitar Avenue, S Loop 289
to 82nd Street
11216,000.
11216,000.
Traffic Signal System Design
TSM 265,000.
265,000. �
82nd Street and University
Avenue
-
Trnf.fic Signal. Instntlation
TSM 40,000.
40,000.
-5-
July, 1981 ,
Classifi- Funding
cation Projects Cost Federal State - 'Local-
IAll I. H. 27 Extension, N Loop 289 to
S Loop 289
Investigation & Planning Expenses (Consultant)
Prepare ROW Plans
Prepare Plans for Construction
T�rVeme n t
1,500,000. 1,350,000. 150,000.
MhTking• Central Business District
Dmn►-' Permanent Pavement Markings TSM 227,280. 227,280.
s:tra t f an
PrViect
M
TOTALS 11894389280. 104,331,030. 12,366,250. 1,741,000.
-6-
i
i y
TRANSPORTATION IMPROVEMENT PROGRAM
FOR LUBBOCK URBANIZED
AREA
(September 1, 1981 - August
31, 1982)
Transit Element
The Transit Element of
the Transportation
Improvement Program
consists
of
the following projects
recommended for advancement during
the period
FY
1982-1986. These projects are suported by
the Transportation
System
Management Element.
Funding
Projects
Cost
Federal
State Local Share
Operating Assistance
(FY 1981)
TX-05-4101
1,323,166
661,583
661,583
Capital Improvement
(FY 1981)
TX-05-0068
2,707,619
2,1661095
351,991
189,533
Operating Assistance
(FY 1982)
11482,792
741,396
741,396
Capital Improvement
'
(FY 1982)
137,280
1091825
17,846
9,609
Operating Assistance
(FY 1983)
19648,728
824,364
824,364
Capital Improvement
(FY 1983)
1,517,000
1,214,000
197,000
10,13,000
Operating Assistance
(FY 1984)
1,834,576
917,288
9179288
Capital Improvement
(FY 1984)
318,000
255,000
41,000
22,000
Operating Assistance-
(FY 1985)
1,875,450
937,725
9372725
Capital Improvement
1,204,000
964,000
156,000
84PO00
(FY 1985)
Operating Assistance
2,0001000
1,000,000
1,000,000
(FY 1986)
TOTALS
16,048,611
9,791,276
7633,837
5,4930498
'iL
a�iy; lit
ANNUAL
ELEMENT - TRANSIT
TRANSPORTATION IMPROVEMENT
PROGRAM
FY 1982 (September
1, 1981 - August
31, 1982)
Classifi-
Funding
cation
Projects
Cost
Federal State
Local Share
Section
Operating Assistance
5
(FY 1981)
TX-05-4101
1,323,166
-661,583
661,583
Section
Capital Improvement
5
(FY 1981)
TX-05-0068
20707,619
2,166,096 351,990
189,533
Section
Operating Assistance
5
(FY 1982)
114821792
741,396
741,396
Section Capital Improvement
5 (FY 1982) 1371280 109,825 17,846 9,609
Section Operating Assistance
5 (FY 1983) 1,648,728 824,364 824,364
TOTALS 7,299,585 4,503,264 369,836 2,426,485
BREAKDOWN OF FEDERAL PARTICIPATION
TYPE PROJECT TOTAL COST FEDERAL SHARE
FAI 1111675,000. 100,507,500.
FAU 49795,000. 3,596,250.
Pavement Marking
Demonstration Project - 227,280. 227,280.
TOTALS 116,697,280. 104,331,030.'
-9-
T�.tv, i981
The following subjects are discussed in Attachment A:
Actions taken on TSME projects in the FY 1981 TIP/AE
Streets and Highways Projects
Transit Projects
Transportation for the Elderly and Handicapped
Project budgets for gragt applications
Section 5 - Operating Assistance FY 1981
Section 5 - Capital Improvement FY 1981
Section 5 - Operating Assistance FY 1982
Section 5 - Capital Improvement FY 1982
Sectopm 5 - Operating Assistance FY 1983
-10-
11
.0