HomeMy WebLinkAboutResolution - 216 - Accept Paving Improvements - Kerr Co - Lots 1-126, Ridgewood Two Addition - 07_26_1979RESO #216 - 7/26/79
RESOLUTION
RESOLUTION ACCEPTING IMPROVEMENTS ON PORTIONS OF STREETS AND AVENUES AS LISTED
BELOW:
WHEREAS, in conformance with the paving requirement provisions of City
Ordinance 1331, the subdivider of Ridgewood Two Addition, Lots 1-126, made arrange-
ments with Kerr Construction Company for the construction of paving improve-
ments on certain streets dedicated in said subdivision under the provisions of
said Ordinance prior to the recording of the subdivision plat of Ridgewood Two
Addition, Lots 1-126 including the following streets:
21st Street from its intersection with the West Raw Edge of Milwaukee
Avenue to its intersection with a line 15.00 feet South of South Property
Line of 21st Street at Norwich Avenue known and designated as New Sub-
division Sub -Unit Number 75 of Unit Number 2019.
22nd Street from its intersection with the East Lip Line of Norwich Avenue
to its intersection with the West Property Line of Milwaukee Avenue known
and designated as New Subdivision Sub -Unit Number 76 of Unit Number 2019.
22nd Place from its intersection with the East Lip Line of Norwich Avenue
to its intersection with the West Property Line of Milwaukee Avenue known
and designated as New Subdivision Sub -Unit Number 77 of Unit Number 2019.
23rd Street from its intersection with the East Lip Line of Norwich Avenue
to its intersection with the West Raw Edge of Milwaukee Avenue known and
designated as New Subdivision Sub -Unit Number 78 of Unit Number 2019.
24th Street from its intersection with the East Lip Line of Norwich Avenue
to its intersection with the West Property Line of Milwaukee Avenue known
and designated as New Subdivision Sub -Unit Number 79 of Unit Number 2019.
25th Street from its intersection with the East Lip Line of Norwich Avenue
to its intersection with the West Property Line of Milwaukee Avenue known
and designated as New Subdivision Sub -Unit Number 80 of Unit Number 2019.
North 1/2 of 26th Street from its intersection with a line 607.56 feet
West of West Property Line of Milwaukee Avenue to its intersection with
the West Lip Line of Milwaukee Avenue known and designated as New Sub-
division Sub -Unit Number 81 of Unit Number 2019.
Norwich Avenue from its intersection with the North Lip Line of 26th
Street to its intersection with a line 15.00 feet South of South Property
Line of 21st Street known and designated as New Subdivision Sub -Unit
Number 82 of Unit Number 2019.
West 1/2 of Milwaukee Avenue (concrete only) from its intersection with
a line 7.00 feet North of North Property Line of alley North of 21st
Street to its intersection with the centerline of 26th Street known
and designated as New Subdivision Sub -Unit Number 83 of Unit Number 2019.
AND WHEREAS, the construction of the above improvements on the abovementioned
streets was performed under the supervision of the City Engineer, and said improve-
ments have been completed and have been inspected and found to have been con-
structed in accordance with City specifications and in accordance with the
provisions of City Ordinance 1331.
THEREFORE, BE IT RESOLVED BY THE CITY OF LUBBOCK, TEXAS.
I.
That the improvements on said portions of the abovementioned streets be and
the same are hereby accepted and the City Engineer be and he is hereby authorized
to direct the payment of the City's portion of the cost and to release escrow
money.
II.
This resolution shall take effect and be in force from and after its passage.
PASSED AND APPROVED THIS 26th DAY OF July , 1979
071>ma
C1 -.04
rk West, Mayor
ATTEST:
%tvelyn Gaffgaf City m e ry
APPROVED AS TO�CONTENT:
-44qd D. Watson, City Engineer
AS TO FORM:
v /+- —
hn C. Ross, Jr., City Attorney
Tied to Reso #216
7/26/79
CONSOLIDATED FINAL ESTIMATE
Ridgewood II Addition Lots 1 - 126
Accepted July 26, 1979
QUANTITIES
S.Y. Alley
S.Y.
Return and
S.Y.
Unit &
Paving
L.F.
Drainage
Valley
Sub -Unit
Location
6" Base
C & G
Channels
Gutter
NS
2019-75
21st Street from West raw edge of Mil-
waukee Avenue to 15 ft. South of SPL
of 21st Street.
3,077.29
995.95
NS
2019-76
22nd Street from E.L.L. of Norwich
Avenue to W.P.L..of Milwaukee Ave.
1,701.30
955.56
4.56
NS
2019-77
22nd Place from E.L.L. of Norwich
Avenue to W.P.L. of Milwaukee Ave.
1,701.30
955.56
.4.56
NS
2019-78
23rd Street from E.L.L. of Norwich
Avenue to West raw edge of Milwaukee
Avenue.
2,509.72
931.12
52.54
NS
2019-79
24th Street from E.L.L. of Norwich
Avenue to W.P.L. of Milwaukee Ave.
1,648.76
955.56
4.56
52.54
NS
2019-80
25th Street from E.L.L. of Norwich
Avenue to W.P.L. of Milwaukee Ave.
1,648.76
955.56
4.56
52.54
NS
2019-81
North 1/2 of 26th Street from 607.56
ft. West of W.P.L. of Milwaukee Ave-
nue to West raw edge of Milwaukee Ave.
2,358.76
543.58
32.94
NS
2019-82
Norwich Ave. from N.L.L. of 26th St.
to 16 ft. South of S.P.L. of 21st
Street.
7,452.62
3,089.83
133.62
NS
2019-83
West 1/2 of Milwaukee Avenue from
7' North of N.P.L. of alley North
of 21st St. to centerline of 26th
Street. (Concrete Only)
1,768.93
156.95
TOTAL QUANTITIES
22,098.51
11,151.64
308.81
190.56
COST ESTIMATE
22,098.51
S.Y.
Paving 6" Base
11,151.64
L.F.
Curb &. Gutter
308.81
S.Y.
Alley Return & Drainage Channels
190.56
S.Y.
Valley Gutter
COST DISTRIBUTION
I
Unit & Contract
Sub -Unit Cost
@ $ 4.55 $100,548.23
@ $ 4.25 $ 47,394.48
@ $19.50 $ 6,021.80
@ $19.50 $ 3,715.92
CONTRACT COST $157,680.43
City Prepaid
Property Account to
Owner Cost Contractor
NS
2019-75
$18,234.46
$18,234.46
N$
2019-76
$11,890.97
$11,890.97
NS
i
2019-77
$11,890.97
$11,890.97
NS
2019-78
$16,401.01
$16,401.01
NS
2019-79
$12,676.44
$12,676.44
NS
2019-80
$12,676.44
$12,676.44
NS
2019-81
$13,684.91
$13,312.98 $371.93
i
NS
2019-82
$49.646.79
$49,646.79
N5
2019-83
$10,578.44
$10,578.44
TOTAL
$157,680.43
$157,308.50 $371.93