HomeMy WebLinkAboutResolution - 143 - CO#2 To Contract-Anthony Mechanical-Digester Adds., SE Water Reclamation Plant - 04_26_1979D JCR:cl - RESO #143 - 4/26/79
RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock BE and is hereby authorized and
directed to execute for and on behalf of the City of Lubbock a Change Order
No. 2, Digester Additions, S.E. Water Reclamation Plant GWO 10949, between
the City of Lubbock and Anthony Mechanical, Inc., attached herewith which shall
be spread upon the minutes of the Council and as spread upon the minutes of
this Council shall constitute and be a part of this Resolution as if fully
copied herein in detail.
Passed by the City Council this 26th day of April ,1979.
10,
DIRK WEST, MAYOR
ATTEST:
Evelyn Gaf ga, City Sec et ry reasurer
APPROVED AS TO CONTENT:
Wil rd Watson, City Engineer
APPROV D AS TO FORM:
�- �. .
ohn C. Ross, Jr., City Attorney
r r.. TIED TO RESO. #143 - 4/26/79
Change Order No. 2
Digester Additions
S.E. Water Reclamation Plant
GWO 10949
TO: Anthony Mechanical, Inc.
P.O. Box 2706
Lubbock, Texas 79408
Original amount of the contract $119,897.00
Change Order No. 1 $ 695.75
Net amount this Change Order $ 3,614.00
Amended amount of contract $124,206.75
Additional time of completion To May 10, 1979
WHEREAS, it is desirable to make changes in the plans and specifications
for this project;
THIS AGREEMENT WITNESSETH: In consideration of the mutual advantages
gained, the Owner and the Contractor agree to the change shown herein
and in the attached exhibits and data and the Owner and the Contractor
agree that the original contract between them shall be modified and
amended to the extent herein indicated.
IN WITNESS WHEREOF, the Owner and the Contractor have hereto set
their hands this the 26th day of April , 1979.
Anthony Mechanical, Inc.
By/S
Approved as to form;
John
CITY OF LUBBOCK
OWNER
Mayor
ATTEST:
City Secretary
RECO NDED FOR APPROVAL:
&�
City E6giAeer
City MfWr
Attachment to Change Order No. 2
Anthony Mechanical, Inc.
G.W.O. 10949
EXPLANATION OF CHANGE'
2" gas supply line installed to provide adequate gas pressure to
new Heat Exchanger installed in control chamber of Digesters 6.and';'7..
Anthony Mechanical, Inc.
Contractor