Item 31
RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock BE and is hereby authorized and
directed to execute for and on behalf of the City of Lubbock, Change Order #1 on the
Milwaukee Avenue from 34th Street to 92°d Street Paving Improvement Construction
Contract with Granite Construction Company. Change Order is attached hereto and
incorporated in this Resolution as if fully set forth herein and shall be included in the
minutes of the Council.
Passed by the City Council this 14th day of JulY , 2005.
ZARCMCDOUdAL, MAYOR
ATTEST:
Rebe ca Garza, City Secretary
APPROVED AS TO CONTENT:
Hertel, City Engineer
APPROVED AS TO FORM:
Attorney
gs:ccdocs/Res-ChOrderl-Milwaukee 340'to 92nd
July 6, 2005
oNi-RAGT a Resolution No. 2005-RO316
CITY OF LUBBOCK
CHANGE ORDER
CHANGE ORDER #: 1 CONTRACTOR: Granite Construction
DATE: 7/5/05 BID#: 1 CONTRACT ID#: 05-029-VK
PROJECT NAME: Milwaukee Avenue Paving Impeovements - 92°d to 341h Street
Change Order within the scope of the contract means a Change Order that DOES NOT ALTER THE NATURE OF THE THING
TO BE CONSTRUCTED AND THAT IS AN INTEGRAL PART OF THE PROJECT OBJECTIVE. After performance of a
construction contract begins, Change Orders may be approved if necessary to 1) make changes in plans or specifications; or 2)
decrease or increase the quantity of work to be performed or materials, equipment, or supplies to be furnished. This DOES NOT
mean that a department can redefine the project. All work that alters the nature of the thing to be constructed or that is not an
integral part of the project objective must be let out for public bid by the Purchasing Department. Description of change
(alteration, deviation, addition, or deletion) caused by conditions encountered during construction not covered by the
specifications and drawings of the project (attach additional pages if necessary):
See Attached Cost breakdown, Work Change Directive #1, Granite RFI #1 and Granite's response to PSC RFI #1
Change Orders must either be negotiated in the best interest of the City of Lubbock or put out for public bid by the Purchasing
Department. Where the Change Order is negotiated, the Change Order must be fully documented and itemized as to costs,
including material quantities, material costs, taxes, insurance, employee benefits, other related costs, profit and overhead. Where
certain unit prices are contained in the initial contract, no deviations are allowed in computing negotiated change order costs.
ITEMIZED COSTS MUST BE FULLY DOCUMENTED AND ATTACHED TO THIS FORM.
ITEM
DESCRIPTION
AMOUNT
A.
ORIGINAL CONTRACT VALUE:
$
17,316,932.50
B.
AMOUNT OF THIS CHANGE ORDER: Council approval required if over $25,000
$
(212,840.00)
C.
PERCENT OF CONTRACT VALUE THIS CHANCE ORDER (B/A):
1.23%
D.
AMOUNT OF PREVIOUS CHANGE ORDERS:
$
-
E.
TOTAL AMOUNT OF ALL CHANGE ORDERS (B+D):
$
(212,840.00)
F.
PERCENT OF CONTRACT OF ALL CHANGE ORDERS (E/A): 25%Maximum
1.23%
G.
NEW CONTRACT AMOUNT (A+E):
$
17,104,092.50
It is mutually agreed that the above dollar amount and the time extension, as applicable, as set forth in this Change
Order constitutes full compensation to the Contractor for all costs, expenses and damages to the Contractor, whether
direct, consequential or otherwise, in anyway incident to, or arising out of or resulting directly or indirectly; from the
work performed or modified by the Contractor under this Change Order.
C T A O ate OJECT ARCHIT E INEER Date
Approved as to Con nt: Approved as to Form: t
A. Cori
(3 REPR EN T[VE -_ Date t torney Date
jy�
.�.�vutn
�
;3) Jeff fates, • of Fiscal Pu 1,;y Date ku ictcu Kiimn., urcl; tstng Manager Date
Change Orders over $25,000 require the following signatures:
C[TY B CK ATTEST:
arc McDo al, or Date (8) Reb cca Garza, City Secretary Date
PUR-045 (Rev 12/04)
Description of Change Price
By GRANITE RFI #1
Portland Cement Concrete: - $163,000
Trench Backfill Remediation - $31,000
Quality Control Testing - $46,000
Surveying for Utility work $6,000
By PSC RFI #1
12x10 Tapping Sleeve and valve (3 @ $4,945 /ea) $14,835
By Field Clarification Memo #2
16x8 Tapping Sleeve and valve (1) $6,325
TOTAL ADJUSTMENT TO CONTRACT IN CO #1-$212,840
PUR-045 (Rev 12/04)
G
Work Change Directive No.1
Date of Issuance: 717/05 Effective Date: 7/7/05
Project: Owner: Owner's Contract No.:
Milwaukee Avenue Paving Improvements City of Lubbock 05-029-VK
Contract: Date of Contract:
05-029-VK
Contractor. Engineers Project No.:
Granite Construction Company 01-2872-05
You are directed to proceed promptly with the following change(s):
Specification Section
Description
02751
Change in Specification - Contractor may substitute 5.25 sack mix with 20% of cementous material being type f fly ash, contractor
may install transverse reinforcing steel according to column <=60 on Table No.2 on sheet RD-1 by installing a construction joint at
the centerline of the roadway and contractor may reduce the sawed joints from'h" to /4" as in TxDOT standard JS-94 detail sheet.
02317
Change in Specification — For Trench Backfill remediation, Contractor may establish a rolling pattern to achieve required densities
with tests showing the densities achieved at the beginning of the operation, at each significant change in soil material and at vertical
intervals of ten feet. Density testing will be provided at specified frequency in the uppermost five feet of the trench.
01400
Change in Quality Control Testing Specification -
- Independent lab requirement has been waived; the contractor is allowed to perform OC testing on Soils, HMAC and Portland
Cement Concrete using in-house personnel.
— Frequency of subgrade compaction testing has been reduced to 1 test / 10,000 sf
— Contractor is allowed to take concrete cylinders for compressive tests at a frequency of one set of four cylinders / 356 cy of
concrete
General Conditions
Lines and Grades —. The Contractor is directed to hire the surveyor of his choice to provide horizontal and vertical staking of the
P. 2, Paragraph 13
water and sewer line construction. This is a new item and will be paid for by a one-time lump sum payment of $6,000.
Attachments (list documents supporting change): See Granite RFI #1 Attached
Purpose for Work Change Directive:
® Authorization for Work described herein to proceed on the basis of Cost of the Work due to:
® Proposed change in various project specifications.
Necessity to expedite Work described herein prior to agreeing to changes on Contract Price and Contract Time.
Estimated change in Contract Price and Contract Times:
Contract Price $ 212,840 (insrease/decrease Contract Time
0 (increase/decrease)
days
If the change invol�s an increase, the estimated amounts are not to be exceeded without further authorization.
Re �d/for y e r:
Date
rized for Ow by
Date
p d for Contra r y:
Date
11,Vpro d y /10 A096y (if applicable):
Date:
EJCDC No. C-940 (2002 Edition) Page 1 of 1
Prepared by the Engineers' Joint Contract Documents Committee and endorsed by the
Associated General Contractors of America and the Construction Specifications Institute.
GRRnrrE
consucnon
compnm Sim
June 14, 2005
Mr. Gary Dawson P.E.
Parkhill, Smith & Cooper Inc.
4222 85 h St.
Lubbock, Texas 79423
Re: Milwaukee Ave Paving Improvements
City of Lubbock project number 90355
RFI # 1.
Mr. Dawson,
Granite Construction Co would like to offer the following changes to the project
specifications for your consideration. These changes will produce savings to the City of
Lubbock, without lowering the standard of quality required by the specifications.
SECTION 02751 PORTLAND CEMENT CONCRETE PAVEMENT
In paragraph E.2 the Class C concrete is specified to have minimum 6 sacks of cement
per cubic yard of concrete with a 7 day compressive strength of 2500 psi and a 28 day
compressive strength of 3600 psi. Granite Construction is requesting that we be allowed
to substitute a 5.25 sack, with 20% of the cementous material being type f flyash, mix for
this specification. This mix is currently being used on the Marsha Sharp Freeway phase 1
project. The minimum 7 day and 28 day strength required by the contract documents will
be met or exceeded using this design. This mix design and historical breaks will be
submitted for your review.
We are also requesting that the transverse reinforcing steel for the CRCP be installed
according to column <=60 in table No.2 on sheet RD-1 of the project plans. This will be
accomplished by installing a construction joint at the center line of the roadway. The bar
size will remain as designed. There will be no change in the longitudinal reinforcing
steel. The transverse tie bars will be spaced equal to the transverse reinforcing steel
spacing.
Additionally we request that the width of the CRCP sawed joints be reduced from %2" to
%4" as shown in TxDot specification JS-94standard joint detail.
These changes will allow for a savings to the City of Lubbock of $163,000.00
P.O. Box 3130
Lubbock, TX 79452
(806) 748-9170
FAX (806) 748-9468
TRENCH_REMEDIATION BACKFILL
Granite Construction Co. would request that the trench remediation backfill specification
be modified as follows: Contractor will establish a rolling pattern with density tests at
the beginning of the backfill operation, at each significant change in soil material and at
vertical intervals of ten feet. Provide density testing at the specified frequency of one
every five hundred feet per 6" lift in the uppermost five feet of trench.
This change in method will allow a savings to the City of Lubbock of $31,000.00
QUALITY CONTROL TESTING
Granite Construction Co requests that the requirement for an independent testing lab to
perform Quality Control testing be waived and that Granite Construction Co. be allowed
to perform QC testing on Soils, Hot Mix Asphaltic Concrete and Portland Cement
Concrete with in house ACI and TxDot certified personnel. We further request that the
frequency of tests be modified as follows:
I. Soil densities for subgrade compaction betaken at the frequency of 1 test / 10000
sf.
2. Compressive cylinders for concrete paving 1 set of 4 cylinders / 356 cy of
concrete.
These changes will produce a savings to the City of Lubbock of $46,000.00
GENERAL CONDITIONS
Paragraph 13 on page 2 of the General Conditions; require the Owners Representative to
furnish all lines and grades for the commencement of the work. We interpret this to say
that the owner will establish horizontal and vertical offset stakes, for curb and gutter and
water and sewer line construction. It is our understanding that the owner intended this to
be the responsibility of the contractor. The owner would provide control points at several
locations through out the project limits.
In the spirit of partnering we propose the following solution. Granite Construction Co
will provide the offset staking for curb and gutter and the owner will provide the
horizontal and vertical staking of the water and sewer line construction.
The cost to the City of Lubbock for the water and sewer line staking will be $6,000.00.
Should the owner elect to accept these changes the savings to the City of Lubbock will be
$240,000.
The added cost to the City of Lubbock for the water and sewer line staking will be
$6000.00.
This will make a net change in the contract of ($234,000.00).
r
Thank you for the opportunity to present these modifications. We look forward to the
City of Lubbock's decision and too a successful project for the citizens of Lubbock.
Sincerely yours
R. Michael Oliver
Project Manager