Loading...
HomeMy WebLinkAboutResolution - 2004-R0134 - Contract Bid To Cover Freeway Alignment Changes - D&D Cable Services - 03_23_2004Resolution No. 2004-RO134 March 23, 2004 Item No. 27 RESOLUTION BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK: THAT the Mayor of the City of Lubbock is hereby authorized and directed to execute for and on behalf of the City of Lubbock a Change Order No. 1 to a Contract (Bid No. ITB#122-03 BM) with D & D Cable Services LTD., to cover the expenses incurred by D & D Cable Services LTD. for additional quantities of work caused due to alignment changes on the Marsha Sharp Freeway made by the Texas Department of Transportation after this project was awarded. A copy of said Change Order No. 1 is attached hereto and incorporated in this Resolution as if fully set forth herein and shall be included in the minutes of the Council. Passed by the City Council this 23rd day of ATTEST: Rebecca Garza, tity Secretary APPROVED A TO CONTENT: Chester Carthel, Water Planning Engineer APPROVED AS TO FORM: Richard K. Casner First Assistant City Attorney ke/ccdocs/ ChangeOrder.l. D & D Cable Services March 8, 2004 March , 2004. Resolution No. 2004—RO134 March 23, 2004 CITY OF LUBBOCK Item No. 27 CHANGE ORDER CHANGE ORDER #: 1 CONTRACTOR: D It D Cable Services LTD. DATE: March 3, 2004 CITY OF LUBBOCK BID#: ITB 122-03 BM PROJECT NAME: Relocate Water Supply Lines Ahead of Freeway Project Change Order within the scope of the contract means a Change Order that DOES NOT ALTER THE NATURE OF THE THING TO BE CONSTRUCTED AND THAT IS AN INTEGRAL PART OF THE PROJECT OBJECTIVE. After performance of a construction contract begins, Change Orders may be approved if necessary to 1) make changes in plans or specifications; or 2) decrease or increase the quantity of work to be performed or materials, equipment, or supplies to be furnished. This does not mean that a department can redefine the project. All work that alters the nature of the thing to be constructed or that is not an integral part of the project objective must be let out for public bid by the Purchasing Department. Description of change (alteration, deviation, addition, or deletion) caused by conditions encountered during construction not covered by the specifications and drawings of the project (attach additional pages if necessary): This Project is a water relocation proiect for the Marsha Sharp Freeway. TxDOT made changes to the alignment requirements after this voiect had been awarded. These required changes to the Droiect and the costs associated are itemized on the attached pages. Change Orders must either be negotiated in the best interest of the City of Lubbock or put out for public bid by the Purchasing Department. Where the Change Order is negotiated, the Change Order must be fully documented and itemized as to costs, including material quantities, material costs, taxes, insurance, employee benefits, other related costs, profit and overhead. Where certain unit prices are contained in the initial contract, no deviations are allowed in computing negotiated change order costs. ITEMIZED COSTS MUST BE FULLY DOCUMENTED AND ATTACHED TO THIS FORM. ITEM DESCRIPTION AMOUNT A. ORIGINAL CONTRACT VALUE: $ 903,526.23 B. AMOUNT OF THIS CHANGE ORDER: Council approval required if over $25,000'" j(� C. PERCENT OF CONTRACT VALUE THIS CHANGE ORDER (B/A): g; 7 .� �, �.,a. ,�..- D. AMOUNT OF PREVIOUS CHANGE ORDERS: $ E. TOTAL AMOUNT OF ALL CHANGE ORDERS (B+D): $ 64,969.31 yy F. PERCENT OF CONTRACT OF ALL CHANGE ORDERS (E/A): 25%Maximum G. NEW CONTRACT AMOUNT (A+E): $ 968,495.54 Change Orders over $25,000 require the following signatures: CITY OF L BOC ATTE 7: 3/23/04 3/23/04 (7) rc McDouga ayor Date (8) R&ec& Garza, Yity Secretary Date PUR-045 (Rev 03/04) Change Order #1 to ITB 122-03 BM Changes to existing contract quantities: Contract Original Unit Changed Estimated Item # Estimated Price Estimated Contract Quantity Quantity Change 1 4,085 feet $61.69 2,547 feet ($94,879.22) 2 4,115 feet $61.26 2,573 feet ($94,462.92) 3 2,938 feet $59.82 5,817 feet $172,221.78 4 240 feet $339.40 300 feet $20,364.00 Total change in original estimated quantities... $3,243.64 Additions to Contract: 320 feet of 36 inch steel encasement installed at $69.40 per foot $22,208.00 New alignment of 24 inch pipe From Toledo east is immediately adjacent to new LP&L poles. Casing was used to protect the foundation of these poles. Extra depth of installation approximately 2,750 feet at $12.00 per foot $33,000.00 The new alignment of the 24 inch water line from Toledo West is to be located deep enough to be under proposed storm water inlet boxes. Trench box rental for New Bore at Toledo. The new alignment at Toledo places a 24 inch water line adjacent to a new LP&L pole. Because of the depth of the new water line and the proximity to the pole a change was made to bore 60 feet in this area. The cost of the bore was added to the existing contract item #4, 240 of bore under 190' Street. This addition to the contract is for the rental of trench boxes and the extra footage cut for the bore pit. Trench box rental $2,646.00 Extra cut depth for bore pit $1,371.67 Reorient new tapping valve. $2,500.00 New tapping valve installed with this project will be in the way of proposed storm sewer. With TxDOT input it was decided to rotate the valve 90 degrees in order to clear any future structures. 2 Extra Calendar Days to complete project. 58 days The realignment required by TXDOT came after the project was awarded and the City was in the process of issuing the Notice to Proceed. To accommodate this realignment there were several meetings with TXDOT to firm up the new position, part of the project had to go through a redesign, new plans had to be drawn up and the material suppliers had to order and or fabricate some of the material. During this time the contractor was unable to work. Total additions to Contract $61,725.67